TDOT contract CN264039 bid tabulation

The ramp improvements on i-40 (exit 101) at the s.r. 104 interchange (l.m. 5.73), including grading, drainage, lighting, and paving. Let by Tennessee DOT on May 8, 2026, Henderson County. 3 bids received; low bid $7,297,325 by Jones Bros. Contractors, LLC.

Owner
Tennessee DOT
Letting
08 MAY 2026
Pay items
145
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Jones Bros. Contractors, LLC$7,297,325Low
2Delta Contracting Company, LLC$7,311,2850.0%
3Precise Concrete Works, LLC$10,796,053+48%
TDOT contract CN264039: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Jones Bros. Contractors, LLC2. Delta Contracting Company, LLC3. Precise Concrete Works, LLC
1Construction stakes, lines and grades (105-01)LS1$50,000$95,000$103,307
2Clearing and grubbing (201-01)LS1$18,000$160,000$211,005
3Removal of structures and obstructions (202-01)LS1$7,000.00$10,000$111,722
4Removal of asphalt pavement (202-03.01)SY1,851$9.00$15.00$18.50
5Road & drainage excavation (unclassified) (203-01)CY28,622$19.00$19.00$22.87
6Borrow excavation (select material) (203-03.01)CY3,472$43.00$15.00$37.78
7Placing and spreading topsoil (203-04)CY4,943.59$3.00$18.50$26.75
8Undercutting (203-05)CY3,472$19.00$22.50$29.00
9Water (203-06)MG265$25.00$50.00$34.00
10Channel substrate (203-20.01)CY19$52.50$24.00$180.00
11Backfill material (flowable fill) (204-08.01)CY25$400.00$400.00$432.00
12Brooming & degrassing shoulders (208-01.05)LM5$1,800.00$1,050.00$4,323.00
13Protected area marker (white with decal) (209-03.99)EACH2$350.00$350.00$159.00
14Sediment removal (209-05)CY1,565$17.00$14.50$18.00
15Temporary silt fence (with backing) (209-08.02)LF2,511$5.50$3.85$5.98
16Temporary silt fence (without backing) (209-08.03)LF4,518$2.00$1.95$4.43
17Rock check dam (209-08.07)EACH45$900.00$650.00$890.00
18Enhanced rock check dam (209-08.08)EACH5$1,400.00$1,600.00$1,450.00
19Sandbags (209-09.01)BAG6,000$3.00$2.00$4.60
20Polyethylene sheeting (6 mil. minimum) (209-20.03)SY32$35.00$0.85$6.00
21Catch basin protection (type A) (209-40.30)EACH4$450.00$500.00$420.00
22Mineral aggregate, type A base, grading D (303-01)TON20,453$35.00$47.50$46.00
23Mineral aggregate (size 57) (303-10.01)TON13$55.00$100.00$57.00
24Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON86$163.00$165.00$162.02
25Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON53$125.00$124.00$164.70
26Asp. conc. mix(PG64-22) (BPMB-HM) GR. A-S (307-01.20)TON85$157.25$130.00$171.39
27Asp. conc. mix(PG76-22) (BPMB-HM) GR. A-S (307-01.22)TON851$157.25$130.00$190.14
28Asphalt concrete mix (PG76-22) (BPMB-HM) grading A (307-03.01)TON885$163.00$165.00$198.17
29Asphalt concrete mix (PG76-22) (BPMB-HM) grading B-M2 (307-03.08)TON3,070$125.00$124.00$214.00
30Asphalt concrete mix (PG76-22) grading CM (307-03.12)TON3,595$124.00$123.00$223.00
31Bituminous material for prime coat (PC) (402-01)TON32$1,000.00$200.00$1,274.00
32Aggregate for cover material (PC) (402-02)TON1,043$20.00$5.00$70.20
33Bituminous material for tack coat (TC) (403-01)TON23$775.00$200.00$1,430.00
34Saw cutting asphalt pavement (407-20.05)LF1,805$4.00$6.00$6.50
35Acs mix(PG76-22) grading D (411-03.10)TON1,582$142.00$168.00$206.21
36Acs mix (PG76-22) ogfc (411-03.23)TON2,391$176.50$185.00$230.31
37Scoring shoulders (continuous) (16IN width) (411-12.01)LM5$2,550.00$1,625.00$5,623.80
38Cold planing bituminous pavement (415-01.01)TON5,563$36.00$29.25$25.35
3918" concrete pipe culvert (class III) (607-03.02)LF73$147.00$73.00$120.80
4024" concrete pipe culvert (class III) (607-05.02)LF73$730.00$94.00$163.30
4160" concrete pipe culvert (class II) (607-11.02)LF40$936.00$325.00$442.80
42Sapl type 1 grout (pipe/culvert repair) (607-25.01)CF283$150.00$150.00$193.20
43Spray applied pipe liner (sapl) (607-25.02)CF212$250.00$250.00$315.60
44Junction box, type 1 (611-02.10)EACH1$5,975.00$4,050.00$7,475.00
45Class A concrete (pipe endwalls) (611-07.01)CY18$750.00$1,985.00$1,322.50
46Steel bar reinforcement (pipe endwalls) (611-07.02)LB856$5.00$5.50$2.60
4724IN endwall (cross drain) 3:1 (611-07.57)EACH2$3,200.00$3,806.84$4,025.00
4818IN endwall (median drain) (611-07.73)EACH1$2,200.00$3,000.00$2,300.00
4936" temporary drainage pipe (621-03.05)LF140$80.00$80.00$230.00
50Guardrail transition 27IN to 31IN (705-02.10)EACH2$500.00$500.00$1,897.50
51W beam GR (type 2) MASH TL-3 (705-06.01)LF2,253$30.00$30.00$35.70
52GR terminaltrailing end (type 13) MASH TL-3 (705-06.10)EACH2$2,000.00$2,000.00$2,127.50
53Tangent energy absorbing term MASH TL-3 (705-06.20)EACH6$3,500.00$3,500.00$4,830.00
54Thrie beam bridge transition MASH TL-3 (705-06.25)EACH2$2,500.00$2,500.00$4,945.00
55Cable barrier (MASH TL-3) (705-06.40)LF3,782.15$42.00$42.00$46.80
56Cable barrier anchor (MASH TL-3) (705-06.41)EACH4$4,500.00$4,500.00$4,306.80
57Guardrail removed (706-01)LF1,782$1.00$1.00$5.20
58Cable barrier terminal (removal) (706-80.18)EACH4$500.00$500.00$799.80
59Cable barrier (removal) (706-80.19)LF3,291$15.00$15.00$2.70
60Stock fence (707-03.01)LF1,724$12.00$8.50$18.40
61Removal of fence (C.A.) (707-06.01)LF1,647$1.75$6.00$5.80
62High-visibility construction fence (707-08.11)LF2,961$3.00$1.75$6.30
63Markers (concrete R.O.W. posts) (708-02.01)EACH16$425.00$343.00$373.80
64Machined rip-rap (class A-3) (709-05.05)TON200$70.75$55.00$82.80
65Machined rip-rap (class A-1) (709-05.06)TON68$69.00$56.00$78.20
66Machined rip-rap (class C) (709-05.09)TON154$72.00$55.00$108.10
67Aggregate underdrains (with pipe) (710-02)LF4,444.10$13.00$13.50$21.90
68Lateral underdrain (710-05)LF1,472$12.50$12.50$18.40
69Lateral underdrain endwall (3:1) (710-06.12)EACH7$1,200.00$1,200.00$1,380.00
70Lateral underdrain endwall (6:1) (710-06.15)EACH19$1,200.00$1,200.00$1,782.50
7151IN single slope concrete barrier wall (711-05.71)LF110$400.00$400.00$676.80
72Traffic control (712-01)LS1$50,000$137,000$430,675
73Interconnected portable barrier rail (712-02.02)LF5,000$90.00$46.00$59.10
74Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH9$6,226.00$4,065.00$5,906.40
75Flexible drums (channelizing) (712-04.01)EACH290$29.00$45.00$67.70
76Warning lights (type A) (712-05.01)EACH24$23.00$25.00$43.50
77Signs (construction) (712-06)SF1,047.86$7.00$7.35$17.80
78Arrow board (type C) (712-08.03)EACH2$1,100.00$1,250.00$2,276.40
79Digital speed limit sign assembly (712-08.09)EACH2$4,500.00$4,500.00$9,597.90
80Queue protection truck (712-08.12)DAY50$1,150.00$1,100.00$2,399.50
81Removable pavement marking (6" line) (712-09.08)LF35,786$5.00$6.00$2.50
82Class A concrete (foundation for sign supports) (713-01.01)CY4$670.00$670.00$2,415.00
83Steel bar reinforcement(foundation for sign supports) (713-01.02)LB825$3.15$3.15$2.60
84Flexible delineator (white) (713-02.14)EACH82$62.00$45.00$69.00
85Steel I-beams & WF-beams(breakaway) sign support (713-06)LB6,204$7.98$7.98$8.10
86"U" section steel posts (713-11.01)LB1,692$4.00$4.00$7.50
87Perforated/knockout square tube post (713-11.02)LB595$4.10$4.10$9.50
88P post slip base (713-11.21)EACH5$520.00$520.00$805.00
89Flat sheet aluminum signs (0.080" thick) (713-13.02)SF193$12.00$12.00$50.60
90Flat sheet aluminum signs (0.100" thick) (713-13.03)SF395$13.12$13.12$57.50
91Extruded aluminum panel signs (713-14)SF737$30.75$30.75$89.70
92Removal of signs, posts and footings (713-15)LS1$3,000.00$3,000.00$5,175.00
93Remove sign, support & footing (713-15.36)EACH5$200.00$200.00$862.50
94Changeable message sign unit (713-16.01)EACH2$5,100.00$5,900.00$8,280.00
95Jacked or bored conduit (714-03)LF1,380$12.00$12.00$142.80
96Direct burial conduit (2" PVC, schedule 40) (714-03.01)LF9,380$6.50$6.50$20.50
97Pull boxes (type C) (714-05.04)EACH22$1,230.00$1,230.00$2,608.20
98Cable (1/C # 10 AWG) (714-06.03)LF29,920$1.10$1.10$3.40
99Cable (1/C # 6 AWG) (714-06.05)LF17,400$1.70$1.70$5.20
100Light standards (40' M.H.) (714-08.09)EACH27$4,410.00$4,410.00$10,557
101Light standards (high mast - 100' M.H.) (714-08.11)EACH6$46,760$46,760$89,424
102Foundation for light standards - high mast (high mast) (714-08.27)EACH6$15,750$15,750$27,324
103Foundation for light standards - roadway (40' standard) (714-08.28)EACH27$1,585.00$1,585.00$6,458.40
104LED luminaires (126 watt LED for offset poles) (714-09.47)EACH27$1,310.00$1,310.00$1,614.60
105LED luminaires-high mast (4 luminaires @90 degrees, 199W) (714-09.64)EACH2$5,000.00$5,000.00$5,713.20
106LED luminaires-high mast (4 luminaires @90 degrees, 295W) (714-09.65)EACH4$5,235.00$5,235.00$8,073.00
107Control center (no. 1) (714-12.01)LS1$12,300$12,300$52,164
108Control center (no. 2) (714-12.02)LS1$12,300$12,300$52,164
109Electrical connection (control center no. 1) (714-25.01)LS1$3,660.00$3,660.00$15,525
110Electrical connection (control center no. 2) (714-25.02)LS1$3,695.00$3,695.00$15,525
111Raised PVMT markers (BI-directional) (1 color lens) (716-01.11)EACH2,764$15.00$16.00$15.00
112Raised pavement marker removal (716-01.14)EACH2,764$15.00$8.00$4.60
113Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23)EACH352$45.00$50.00$63.30
114Removal of snowplowable reflective marker (716-01.30)EACH228$20.00$10.00$13.80
115Plastic pavement marking (24" barrier line) (716-02.07)LF343$20.00$25.00$12.90
116Painted pavement marking (6" line) (716-05.20)LM8$1,500.00$2,800.00$1,840.00
117Painted pavement markings(8" line) (716-05.50)LF1,366$1.50$2.80$2.80
118Removal of pavement marking (line) (716-08.20)LM8$7,000.00$5,810.00$2,875.00
119Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM7$9,000.00$8,300.00$6,325.00
120Enhanced flatline thermo PVMT MRKNG (8IN barrier line) (716-12.03)LF1,902$2.75$4.00$4.90
121Enhanced flatline thermo PVMT MRKNG (6IN dotted line) (716-12.05)LF1,300$2.00$4.00$3.70
122Mobilization (717-01)LS1$432,000$350,316$373,750
123Geotextile (type III)(erosion control) (740-10.03)SY632$3.00$1.52$3.70
124Geotextile (type IV)(stabilization) (740-10.04)SY4,050$4.50$3.01$3.60
125Temporary sediment tube 12IN (740-11.02)LF812$6.00$5.25$7.80
126Seeding (with mulch) (801-01)UNIT302$55.00$35.00$89.70
127Temporary seeding (with mulch) (801-01.07)UNIT441$50.00$25.00$48.30
128Grass seed mix (ripzn/FLPL) W/mulch (801-01.35)UNIT8$150.00$100.00$105.80
129Seeding (without mulch) (801-02)UNIT139$40.00$20.00$50.60
130Fertilizer (801-02.15)TON9$400.00$1,250.00$977.50
131Water (seeding & sodding) (801-03)MG88$20.00$40.00$34.50
132Cuttings: cornus amomum (18IN-24IN) (802-02.32)EACH62$10.00$10.00$16.10
133Cuttings: cephalanthus occidentalis (18IN-24IN) (802-02.35)EACH62$10.00$10.00$16.10
134Cuttings: platanus occidentalis (18IN-24IN) (802-02.38)EACH63$10.00$10.00$16.10
135Cuttings: populus deltoides (18IN-24IN) (802-02.39)EACH63$10.00$10.00$16.10
136Fagus grandifolia (beech seedlng B.R.) (802-12.15)EACH10$10.00$20.00$32.20
137Liquidamber styraciflua (sweetgum seedlng B.R.) (802-12.18)EACH10$10.00$20.00$27.60
138Liriodendron tulipifera (tulip poplar seedlng B.R.) (802-12.19)EACH10$10.00$20.00$27.60
139Platanus occidentalis (sycamore seedlng B.R.) (802-12.26)EACH10$10.00$20.00$27.60
140Sodding (new sod) (803-01)SY30,574.67$4.50$3.35$6.60
141Turf reinforcement mat (class I) (805-01.01)SY400.77$6.50$6.50$7.20
142Erosion control blanket (type I) (805-12.01)SY244.71$2.00$1.50$2.70
143Erosion control blanket (type II) (805-12.02)SY15,851.84$1.75$1.50$3.60
144Erosion control blanket (type III) (805-12.03)SY230.67$2.00$2.00$4.90
145Trackless tack coat (403-02.01)TON38$850.00$250.00$550.00
TDOT contract CN264039: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of May 8, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way