TDOT contract CN261061 bid tabulation
The intersection improvements on s.r. 131 (emory road) at harrell road/carpenter road (l.m. 9.5), including grading, drainage, signals, and paving. Let by Tennessee DOT on August 14, 2026, Knox County. 4 bids received; low bid $7,897,170 by Charles Blalock & Sons, Inc..
- Owner
- Tennessee DOT
- Letting
- 14 AUG 2026
- Pay items
- 203
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Charles Blalock & Sons, Inc. | $7,897,170 | Low |
| 2 | Cleary Construction, Inc. | $9,179,203 | +16% |
| 3 | Southern Constructors, Inc. | $9,401,602 | +19% |
| 4 | Whaley Construction, LLC | $10,499,161 | +33% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Charles Blalock & Sons, Inc. | 2. Cleary Construction, Inc. | 3. Southern Constructors, Inc. | 4. Whaley Construction, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $80,000 | $87,500 | $100,000 | $169,485 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $250,000 | $465,000 | $125,000 | $456,540 |
| 3 | Removal of structures and obstructions (202-01.50) | EACH | 5 | $4,000.00 | $1,925.00 | $12,500 | $7,412.34 |
| 4 | Removal of pipe (24" ,sta.202+67.90) (202-02.01) | LF | 20 | $10.00 | $50.00 | $75.00 | $68.32 |
| 5 | Removal of pipe (15", sta.202+94.70) (202-02.02) | LF | 27 | $10.00 | $37.00 | $60.00 | $52.78 |
| 6 | Removal of pipe (18" ,sta.106+84.34) (202-02.03) | LF | 278 | $10.00 | $21.00 | $60.00 | $61.89 |
| 7 | Removal of pipe (15" ,sta.110+86.87) (202-02.04) | LF | 21 | $10.00 | $47.00 | $60.00 | $53.96 |
| 8 | Removal of pipe (15" ,sta.111+75.08) (202-02.05) | LF | 31 | $10.00 | $32.00 | $60.00 | $52.12 |
| 9 | Removal of pipe (15" ,sta.112+47.21) (202-02.06) | LF | 27 | $10.00 | $37.00 | $60.00 | $51.98 |
| 10 | Removal of pipe (18" ,sta.113+95.82) (202-02.07) | LF | 31 | $10.00 | $32.00 | $60.00 | $58.23 |
| 11 | Removal of pipe (18" ,sta.114+05.43) (202-02.08) | LF | 41 | $10.00 | $24.00 | $60.00 | $57.45 |
| 12 | Removal of pipe (18" ,sta.114+35.71) (202-02.09) | LF | 31 | $10.00 | $32.00 | $60.00 | $56.39 |
| 13 | Removal of pipe (18" ,sta.300+63.87) (202-02.10) | LF | 42 | $10.00 | $23.00 | $60.00 | $58.23 |
| 14 | Removal of pipe (18" ,sta.301+08.93) (202-02.11) | LF | 22 | $10.00 | $45.00 | $60.00 | $59.63 |
| 15 | Removal of pipe (48" ,sta.400+32.52) (202-02.12) | LF | 31 | $10.00 | $81.00 | $175.00 | $186.36 |
| 16 | Removal of pipe (18" ,sta.302+26.48) (202-02.13) | LF | 60 | $10.00 | $41.00 | $60.00 | $58.41 |
| 17 | Removal of pipe (18" ,sta.400+92.87) (202-02.14) | LF | 24 | $10.00 | $41.00 | $60.00 | $56.23 |
| 18 | Removal of pipe (18" ,sta.400+71.37) (202-02.15) | LF | 18 | $10.00 | $55.00 | $60.00 | $61.32 |
| 19 | Removal of pipe (18" ,sta.500+47.58) (202-02.17) | LF | 25 | $10.00 | $40.00 | $60.00 | $62.38 |
| 20 | Removal of pipe (18" ,sta.500+40.92) (202-02.18) | LF | 23 | $10.00 | $43.00 | $60.00 | $63.27 |
| 21 | Removal of curb (sta. 500+00 - sta. 501+25.00) (202-08.10) | LF | 229 | $30.00 | $10.00 | $20.00 | $52.36 |
| 22 | Road & drainage excavation (unclassified) (203-01) | CY | 6,633 | $15.00 | $61.60 | $50.00 | $55.28 |
| 23 | Borrow excavation (unclassified) (203-03) | CY | 5,262 | $35.00 | $27.25 | $60.00 | $65.89 |
| 24 | Placing and spreading topsoil (203-04) | CY | 934 | $5.00 | $40.50 | $35.00 | $35.32 |
| 25 | Water (203-06) | MG | 69 | $10.00 | $130.00 | $260.00 | $115.28 |
| 26 | Furnishing & spreading topsoil (203-07) | CY | 354 | $70.00 | $95.65 | $80.00 | $75.47 |
| 27 | Flowable fill (excavatable) (204-06.02) | CY | 103 | $806.72 | $585.00 | $600.00 | $550.23 |
| 28 | Brooming & degrassing shoulders (208-01.05) | LM | 0.06 | $42,801 | $59,500 | $7,500.00 | $21,147 |
| 29 | Sediment removal (209-05) | CY | 167 | $5.00 | $77.35 | $46.00 | $110.28 |
| 30 | Temporary silt fence (with backing) (209-08.02) | LF | 860 | $4.73 | $6.50 | $7.00 | $5.55 |
| 31 | Rock check dam (209-08.07) | EACH | 6 | $840.00 | $1,000.00 | $1,000.00 | $750.21 |
| 32 | Enhanced rock check dam (209-08.08) | EACH | 3 | $1,260.00 | $1,485.00 | $1,250.00 | $1,258.39 |
| 33 | Curb inlet protection (type 1) (209-09.40) | EACH | 28 | $183.75 | $235.00 | $400.00 | $441.23 |
| 34 | Catch basin protection (type E) (209-40.34) | EACH | 1 | $262.50 | $350.00 | $1,100.00 | $328.96 |
| 35 | Catch basin filter assembly(type 1) (209-40.41) | EACH | 5 | $682.50 | $830.00 | $700.00 | $1,587.36 |
| 36 | Catch basin filter assembly(type 8) (209-40.48) | EACH | 1 | $1,575.00 | $1,850.00 | $1,100.00 | $1,798.39 |
| 37 | Temporary diversion channel (209-65.03) | LF | 430 | $49.68 | $112.00 | $250.00 | $185.47 |
| 38 | Mineral aggregate, type A base, grading D (303-01) | TON | 5,176 | $71.00 | $63.50 | $65.00 | $62.37 |
| 39 | Granular backfill (roadway) (303-01.01) | TON | 1,643 | $71.00 | $76.25 | $70.00 | $65.23 |
| 40 | Mineral aggregate (size 57) (303-10.01) | TON | 86 | $119.91 | $66.50 | $90.00 | $78.36 |
| 41 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 982 | $142.80 | $160.00 | $160.00 | $220.36 |
| 42 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 984 | $162.75 | $185.00 | $170.00 | $242.12 |
| 43 | Bituminous material for prime coat (PC) (402-01) | TON | 8 | $142.00 | $1,550.00 | $1,325.00 | $1,100.46 |
| 44 | Bituminous material for tack coat (TC) (403-01) | TON | 5 | $987.00 | $1,115.00 | $950.00 | $568.32 |
| 45 | Acs mix(PG64-22) grading D (411-01.10) | TON | 741 | $210.00 | $235.00 | $225.00 | $275.63 |
| 46 | Cold planing bituminous pavement (415-01.01) | TON | 192 | $105.00 | $120.00 | $125.00 | $198.85 |
| 47 | Class A concrete (roadway) (604-01.01) | CY | 213 | $1,600.00 | $2,341.00 | $3,250.00 | $1,998.32 |
| 48 | Steel bar reinforcement (roadway) (604-01.02) | LB | 50,498 | $2.00 | $1.90 | $2.25 | $3.15 |
| 49 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 1,282 | $265.39 | $145.00 | $250.00 | $221.84 |
| 50 | 24" concrete pipe culvert (class III) (607-05.02) | LF | 141 | $289.72 | $173.00 | $400.00 | $286.38 |
| 51 | 36" concrete pipe culvert (class III) (607-07.02) | LF | 145 | $397.79 | $279.00 | $350.00 | $387.42 |
| 52 | Class A concrete (pipe endwalls) (611-07.01) | CY | 21 | $4,082.55 | $3,570.00 | $1,750.00 | $2,154.65 |
| 53 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 722 | $18.31 | $4.25 | $2.25 | $5.63 |
| 54 | Catch basins, type 12, 0' - 4' depth (611-12.01) | EACH | 1 | $12,638 | $8,100.00 | $7,000.00 | $9,547.23 |
| 55 | Catch basins, type 12, > 8' - 12' depth (611-12.03) | EACH | 2 | $15,333 | $12,750 | $9,500.00 | $11,548 |
| 56 | Catch basins, type 14, 0' - 4' depth (611-14.01) | EACH | 1 | $16,504 | $13,800 | $9,500.00 | $10,353 |
| 57 | Catch basins, type 14, > 4' - 8' depth (611-14.02) | EACH | 3 | $16,766 | $15,000 | $12,000 | $12,857 |
| 58 | Catch basins, type 25, 0' - 4' depth (611-25.01) | EACH | 1 | $12,710 | $8,115.00 | $7,500.00 | $9,265.87 |
| 59 | Catch basins, type 25, > 4' - 8' depth (611-25.02) | EACH | 3 | $13,440 | $11,750 | $8,000.00 | $10,124 |
| 60 | Catch basins, type 25, > 12' - 16' depth (611-25.04) | EACH | 2 | $21,507 | $28,715 | $18,000 | $23,525 |
| 61 | Catch basins, type 26, > 4' - 8' depth (611-26.02) | EACH | 1 | $19,004 | $21,350 | $12,500 | $13,659 |
| 62 | Catch basins, type 42, 0' - 4' depth (611-42.01) | EACH | 2 | $11,151 | $6,700.00 | $6,500.00 | $9,123.64 |
| 63 | Catch basins, type 42, > 4' - 8' depth (611-42.02) | EACH | 2 | $13,702 | $12,000 | $9,500.00 | $12,590 |
| 64 | Catch basins, type 42, > 8' - 12' depth (611-42.03) | EACH | 1 | $16,483 | $20,000 | $15,000 | $13,854 |
| 65 | Catch basins, type 43, > 4' - 8' depth (611-43.02) | EACH | 1 | $19,987 | $22,650 | $16,000 | $16,834 |
| 66 | 18" temporary drainage pipe (621-03.02) | LF | 153 | $130.09 | $120.00 | $85.00 | $108.58 |
| 67 | 24" temporary drainage pipe (621-03.03) | LF | 100 | $202.01 | $142.00 | $90.00 | $132.45 |
| 68 | 30" temporary drainage pipe (621-03.04) | LF | 1,898 | $88.41 | $125.00 | $100.00 | $109.32 |
| 69 | 54" temporary drainage pipe (621-03.08) | LF | 60 | $419.74 | $465.00 | $250.00 | $387.32 |
| 70 | Temporary shoring (temporary runaround) (621-05.10) | LS | 1 | $197,290 | $760,000 | $450,000 | $185,258 |
| 71 | Concrete driveway (701-02) | SF | 3,187 | $16.80 | $15.50 | $20.00 | $30.98 |
| 72 | Concrete curb (702-01) | CY | 27 | $1,034.25 | $1,125.00 | $900.00 | $1,243.63 |
| 73 | Concrete combined curb & gutter (702-03) | CY | 164 | $792.75 | $715.00 | $650.00 | $852.51 |
| 74 | Metal beam guard fence (705-01.04) | LF | 33 | $79.80 | $90.00 | $80.00 | $128.70 |
| 75 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 384 | $28.35 | $32.00 | $30.00 | $29.70 |
| 76 | GR terminal (in-inline) MASH TL-3 (705-06.11) | EACH | 3 | $1,149.75 | $1,300.00 | $1,200.00 | $1,320.20 |
| 77 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 2 | $3,570.00 | $4,100.00 | $3,600.00 | $3,685.10 |
| 78 | GR terminal (energy absorbing) MASH TL-2 (705-06.30) | EACH | 1 | $2,971.50 | $3,350.00 | $3,000.00 | $3,520.30 |
| 79 | Guardrail removed (706-01) | LF | 281 | $4.73 | $13.25 | $5.00 | $1.10 |
| 80 | Radius rail (706-06.03) | LF | 64 | $36.75 | $41.50 | $38.00 | $48.40 |
| 81 | Rounded end element (706-10.26) | EACH | 3 | $126.00 | $143.00 | $150.00 | $275.20 |
| 82 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 28 | $747.61 | $360.00 | $500.00 | $550.32 |
| 83 | Machined rip-rap (class A-3) (709-05.05) | TON | 100 | $95.00 | $90.00 | $90.00 | $86.39 |
| 84 | Machined rip-rap (class A-1) (709-05.06) | TON | 1,315 | $95.00 | $87.00 | $120.00 | $85.12 |
| 85 | Machined rip-rap (class B) (709-05.08) | TON | 1,241 | $95.00 | $75.00 | $90.00 | $98.36 |
| 86 | Traffic control (712-01) | LS | 1 | $265,205 | $325,000 | $300,000 | $652,128 |
| 87 | Portable barrier rail (MASH TL-3) (712-02.10) | LF | 3,460 | $101.66 | $46.50 | $50.00 | $135.37 |
| 88 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 10 | $5,118.75 | $7,500.00 | $7,500.00 | $12,542 |
| 89 | Flexible drums (channelizing) (712-04.01) | EACH | 50 | $45.00 | $48.00 | $50.00 | $44.55 |
| 90 | Barrier rail delineator (712-04.50) | EACH | 170 | $20.00 | $20.00 | $35.00 | $17.88 |
| 91 | Warning lights (type A) (712-05.01) | EACH | 25 | $2.00 | $33.00 | $50.00 | $30.80 |
| 92 | Signs (construction) (712-06) | SF | 693 | $8.00 | $9.75 | $17.00 | $8.97 |
| 93 | Temporary barricades (type III) (712-07.03) | LF | 40 | $16.00 | $19.00 | $30.00 | $17.60 |
| 94 | Removable pavement marking (stop line) (712-09.04) | LF | 107 | $15.75 | $17.75 | $35.00 | $16.58 |
| 95 | Removable pavement marking (6" line) (712-09.08) | LF | 8,620 | $3.27 | $3.50 | $4.00 | $3.42 |
| 96 | Removable black-out tape (6") (712-09.30) | LF | 9,279 | $3.27 | $3.50 | $4.50 | $3.42 |
| 97 | Class A concrete (foundation for sign supports) (713-01.01) | CY | 1 | $210.00 | $240.00 | $250.00 | $220.30 |
| 98 | Steel bar reinforcement(foundation for sign supports) (713-01.02) | LB | 125 | $1.05 | $1.20 | $1.25 | $1.10 |
| 99 | Perforated/knockout square tube post (713-11.02) | LB | 272 | $4.73 | $5.25 | $5.00 | $4.95 |
| 100 | P post slip base (713-11.21) | EACH | 5 | $556.50 | $630.00 | $600.00 | $583.26 |
| 101 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 54 | $15.07 | $17.00 | $20.00 | $15.79 |
| 102 | Street name sign (rigid 0.100IN thick (713-14.21) | SF | 82 | $121.80 | $138.00 | $40.00 | $127.60 |
| 103 | Removal of signs, posts and footings (713-15) | LS | 1 | $315.00 | $350.00 | $2,000.00 | $330.23 |
| 104 | Suspended flat sheet aluminum sign (0.080" thick) (713-15.07) | EACH | 2 | $345.45 | $390.00 | $750.00 | $361.90 |
| 105 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 58 | $42.00 | $48.00 | $60.00 | $44.23 |
| 106 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 30 | $42.00 | $48.00 | $60.00 | $44.23 |
| 107 | Removal of snowplowable reflective marker (716-01.30) | EACH | 12 | $7.88 | $9.00 | $20.00 | $8.25 |
| 108 | Plastic pavement marking (stop line) (716-02.05) | LF | 230 | $10.50 | $12.00 | $16.00 | $11.23 |
| 109 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 6 | $131.25 | $148.00 | $300.00 | $137.50 |
| 110 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 738 | $1.58 | $1.80 | $3.50 | $1.65 |
| 111 | Plastic pavement marking (8IN line) (716-02.12) | LM | 0.20 | $8,316.00 | $9,500.00 | $12,000 | $8,712.94 |
| 112 | Plastic pavement marking (straight-turn arrow) (716-04.01) | EACH | 2 | $157.50 | $175.00 | $400.00 | $165.00 |
| 113 | Plastic pavement marking (straight arrow) (716-04.05) | EACH | 2 | $131.25 | $150.00 | $200.00 | $137.50 |
| 114 | Painted pavement marking (6" line) (716-05.20) | LM | 0.70 | $1,312.50 | $1,500.00 | $1,850.00 | $1,375.00 |
| 115 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 2 | $6,168.75 | $7,000.00 | $8,500.00 | $6,462.50 |
| 116 | Mobilization (717-01) | LS | 1 | $650,161 | $915,000 | $900,000 | $898,327 |
| 117 | Signal head assembly (130 with backplate) (730-02.09) | EACH | 6 | $1,569.75 | $1,650.00 | $1,500.00 | $1,644.50 |
| 118 | Signal head assembly (150 A2H with backplate) (730-02.17) | EACH | 2 | $2,546.25 | $2,700.00 | $2,500.00 | $2,667.50 |
| 119 | Signal head assembly (140 A4F with backplate) (730-02.59) | EACH | 2 | $1,937.25 | $2,050.00 | $2,000.00 | $2,029.50 |
| 120 | Install pull box (type B) (730-03.21) | EACH | 4 | $1,302.00 | $1,350.00 | $1,250.00 | $1,364.00 |
| 121 | Electrical service connection (730-05.01) | EACH | 1 | $5,748.75 | $6,115.00 | $6,000.00 | $6,022.50 |
| 122 | Signal cable - 7 conductor (730-08.03) | LF | 1,137 | $3.47 | $3.70 | $4.00 | $3.63 |
| 123 | Conduit 2" diameter (directional bore) (730-12.23) | LF | 224 | $56.70 | $60.00 | $55.00 | $59.40 |
| 124 | Conduit 2" diameter (PVC schedule 80) (730-12.26) | LF | 174 | $16.80 | $26.20 | $25.00 | $17.60 |
| 125 | Conduit 3" diameter (PVC schedule 80) (730-12.27) | LF | 17 | $46.20 | $50.00 | $50.00 | $48.40 |
| 126 | Vehicle detector (video) (730-13.02) | EACH | 2 | $5,502.00 | $5,550.00 | $7,500.00 | $5,764.00 |
| 127 | Vehicle detector (360-degree camera) (730-13.14) | EACH | 1 | $38,850 | $40,400 | $40,000 | $40,700 |
| 128 | Cabinet (atc) (730-15.07) | EACH | 1 | $38,063 | $39,275 | $38,000 | $39,875 |
| 129 | Controller (atc) (730-16.04) | EACH | 1 | $11,760 | $12,250 | $12,000 | $12,320 |
| 130 | Cantilever signal support (1 arm @ 55') (730-25.07) | EACH | 2 | $45,728 | $43,920 | $45,000 | $47,905 |
| 131 | Cantilever signal support (1 arm @ 60') (730-25.11) | EACH | 1 | $41,895 | $43,080 | $45,000 | $43,890 |
| 132 | Cantilever signal support (1 arm @ 65') (730-25.13) | EACH | 1 | $56,805 | $51,000 | $50,000 | $59,510 |
| 133 | Geomembrane (740-06.01) | SY | 995 | $21.01 | $11.75 | $20.00 | $25.89 |
| 134 | Geotextile (type III)(erosion control) (740-10.03) | SY | 2,514 | $2.47 | $4.05 | $12.00 | $6.32 |
| 135 | Temporary sediment tube 18IN (740-11.03) | LF | 3,653 | $3.68 | $5.25 | $7.00 | $5.98 |
| 136 | Seeding (with mulch) (801-01) | UNIT | 78 | $42.00 | $47.50 | $50.00 | $60.51 |
| 137 | Temporary seeding (with mulch) (801-01.07) | UNIT | 69 | $31.50 | $35.75 | $40.00 | $38.57 |
| 138 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 17 | $105.00 | $119.00 | $90.00 | $154.52 |
| 139 | Water (seeding & sodding) (801-03) | MG | 60 | $78.75 | $89.25 | $105.00 | $82.51 |
| 140 | Sodding (new sod) (803-01) | SY | 6,142 | $6.30 | $7.15 | $7.50 | $6.11 |
| 141 | Project mowing (806-02.03) | CYCL | 4 | $270.00 | $5,950.00 | $6,000.00 | $2,958.74 |
| 142 | 2IN mdpe gas main (791-02.02) | LF | 530 | $73.77 | $172.00 | $65.00 | $57.20 |
| 143 | 4IN mdpe gas main (791-02.04) | LF | 160 | $91.36 | $172.00 | $70.00 | $61.60 |
| 144 | 8IN mdpe gas main (791-02.06) | LF | 767 | $114.47 | $211.00 | $120.00 | $114.40 |
| 145 | HDD 2IN PE pipe - unconsolidated (791-04.02) | LF | 100 | $73.48 | $300.00 | $80.00 | $74.80 |
| 146 | Connect to 2IN EX. PE main (791-06.02) | EACH | 7 | $3,327.02 | $3,250.00 | $3,500.00 | $2,750.30 |
| 147 | Connect to 8IN EX. PE main (791-06.05) | EACH | 2 | $5,652.14 | $6,000.00 | $8,500.00 | $7,920.20 |
| 148 | 2IN PE gas valve assembly (791-07.01) | EACH | 6 | $755.83 | $1,450.00 | $3,000.00 | $2,420.30 |
| 149 | 4IN PE gas valve assembly (791-07.02) | EACH | 2 | $1,499.93 | $2,000.00 | $4,000.00 | $3,300.80 |
| 150 | 8IN PE gas valve assembly (791-07.04) | EACH | 4 | $3,644.96 | $4,750.00 | $6,500.00 | $5,720.90 |
| 151 | PE gas fittings (791-07.40) | LB | 500 | $38.67 | $0.01 | $22.00 | $16.58 |
| 152 | 1/2IN service assembly (791-08.01) | EACH | 2 | $2,144.70 | $3,000.00 | $3,000.00 | $1,981.30 |
| 153 | 1/2IN PE service pipe (791-08.06) | LF | 250 | $17.97 | $40.00 | $65.00 | $52.80 |
| 154 | Retire gas main (791-10.10) | LS | 1 | $9,998.10 | $5,500.00 | $8,000.00 | $8,581.40 |
| 155 | 6IN dip restrained joint water line (795-01.03) | LF | 60 | $225.51 | $188.00 | $190.00 | $168.27 |
| 156 | 6IN dip slip joint water line (795-01.04) | LF | 49 | $138.69 | $175.00 | $190.00 | $211.12 |
| 157 | 8IN dip restrained joint water line (795-01.05) | LF | 160 | $227.77 | $188.00 | $200.00 | $223.69 |
| 158 | 8IN dip slip joint water line (795-01.06) | LF | 261 | $127.69 | $177.00 | $200.00 | $237.89 |
| 159 | 12IN dip restrained joint water line (795-01.09) | LF | 200 | $250.71 | $215.00 | $260.00 | $288.32 |
| 160 | 12IN dip slip joint water line (795-01.10) | LF | 316 | $199.89 | $210.00 | $260.00 | $308.46 |
| 161 | 16IN dip restrained joint water line (795-01.13) | LF | 200 | $315.00 | $305.00 | $350.00 | $357.41 |
| 162 | 16IN dip slip joint water line (795-01.14) | LF | 309 | $267.38 | $270.00 | $350.00 | $394.51 |
| 163 | Bore/jack 24IN steel casing pipe-uncon. (795-05.68) | LF | 75 | $2,310.00 | $1,130.00 | $1,400.00 | $1,241.87 |
| 164 | Connect to 6IN water line (795-06.04) | EACH | 1 | $5,250.00 | $2,500.00 | $5,000.00 | $6,412.32 |
| 165 | Connect to 8IN water line (795-06.05) | EACH | 3 | $6,300.00 | $2,750.00 | $7,500.00 | $7,887.21 |
| 166 | Connect to 16IN water line (795-06.09) | EACH | 1 | $15,598 | $6,500.00 | $15,000 | $16,522 |
| 167 | Cut and cap 6IN water line (795-06.33) | EACH | 1 | $2,283.79 | $3,000.00 | $3,500.00 | $7,142.36 |
| 168 | Cut and cap 8IN water line (795-06.34) | EACH | 4 | $3,234.86 | $3,250.00 | $3,500.00 | $9,232.08 |
| 169 | Cut and cap 16IN water line (795-06.39) | EACH | 1 | $6,252.53 | $4,000.00 | $6,000.00 | $24,336 |
| 170 | 16IN X 8IN tapping sleeve and valve (795-07.18) | EACH | 1 | $21,000 | $12,000 | $35,000 | $29,874 |
| 171 | 6IN gate valve assembly (795-08.04) | EACH | 2 | $2,310.00 | $3,250.00 | $4,000.00 | $5,512.39 |
| 172 | 12IN gate valve assembly (795-08.09) | EACH | 2 | $5,355.00 | $7,500.00 | $5,500.00 | $6,897.41 |
| 173 | 16IN butterfly valve assembly (795-08.13) | EACH | 2 | $10,500 | $21,500 | $13,000 | $11,872 |
| 174 | TI of 2IN HDPE casing for service pipe-uncon (795-09.24) | LF | 140 | $82.72 | $230.00 | $50.00 | $119.27 |
| 175 | 3/4IN copper service pipe (795-09.28) | LF | 365 | $26.25 | $60.00 | $35.00 | $48.31 |
| 176 | 1IN copper service pipe (795-09.29) | LF | 40 | $57.75 | $65.00 | $50.00 | $68.41 |
| 177 | 1IN auto air release valve assembly (795-10.03) | EACH | 2 | $4,934.39 | $6,100.00 | $8,000.00 | $4,787.39 |
| 178 | Fire hydrant assembly (795-11.02) | EACH | 1 | $10,500 | $13,500 | $17,000 | $8,412.69 |
| 179 | Retire in place existing water main (795-11.12) | LF | 1,163 | $7.58 | $25.00 | $20.00 | $41.26 |
| 180 | DI fittings (795-13.01) | LB | 4,500 | $9.45 | $15.00 | $32.00 | $9.87 |
| 181 | 24IN steel casing pipe open cut method (795-15.07) | LF | 65 | $572.87 | $525.00 | $450.00 | $683.24 |
| 182 | 30IN steel casing pipe open cut method (795-15.10) | LF | 65 | $763.42 | $655.00 | $750.00 | $815.42 |
| 183 | Relocate/reconnect 3/4IN water meter assembly (795-16.16) | EACH | 11 | $2,991.15 | $1,650.00 | $2,500.00 | $2,147.28 |
| 184 | 8IN PVC gravity sewer 0FT-6FT depth (797-05.51) | LF | 95 | $169.78 | $140.00 | $275.00 | $284.37 |
| 185 | 8IN PVC gravity sewer 6FT-12FT depth (797-05.52) | LF | 535 | $230.52 | $150.00 | $315.00 | $314.28 |
| 186 | 8IN PVC gravity sewer 12FT-18FT depth (797-05.53) | LF | 245 | $447.58 | $250.00 | $350.00 | $410.28 |
| 187 | 8IN PVC gravity sewer >18FT depth (797-05.54) | LF | 100 | $593.76 | $250.00 | $450.00 | $417.28 |
| 188 | Bore/jack 16IN steel casing pipe-uncon. (797-06.64) | LF | 430 | $729.63 | $860.00 | $1,100.00 | $1,028.31 |
| 189 | 48IN manhole 4FT-6FT depth (797-07.02) | EACH | 1 | $8,228.36 | $9,000.00 | $9,000.00 | $12,148 |
| 190 | 48IN manhole 6FT-8FT depth (797-07.03) | EACH | 2 | $7,296.20 | $11,000 | $12,000 | $15,436 |
| 191 | 48IN manhole 8FT-10FT depth (797-07.04) | EACH | 2 | $7,810.03 | $12,000 | $14,000 | $17,236 |
| 192 | 48IN manhole 10FT-12FT depth (797-07.05) | EACH | 1 | $12,337 | $13,000 | $17,500 | $19,287 |
| 193 | 48IN manhole 14FT-16FT depth (797-07.07) | EACH | 2 | $13,841 | $17,000 | $20,500 | $24,185 |
| 194 | Manhole drop connection assembly (797-07.56) | EACH | 1 | $10,245 | $6,000.00 | $5,000.00 | $6,217.84 |
| 195 | 6IN PVC pipe for service lateral (797-08.05) | LF | 25 | $393.19 | $155.00 | $250.00 | $101.87 |
| 196 | 6IN clean out assembly (797-08.08) | EACH | 1 | $2,155.85 | $1,800.00 | $3,500.00 | $3,945.28 |
| 197 | Connect 6IN lateral to sewer line (797-10.06) | EACH | 1 | $4,406.58 | $2,500.00 | $3,500.00 | $4,287.39 |
| 198 | Retirein place 48IN manhole (797-11.25) | EACH | 5 | $5,761.01 | $2,500.00 | $3,500.00 | $2,874.69 |
| 199 | Retirein place existing sewer 8IN-14IN (797-11.31) | LF | 900 | $39.56 | $27.00 | $25.00 | $49.26 |
| 200 | Remove existing sewer 8IN-14IN (797-11.35) | LF | 100 | $84.54 | $40.00 | $275.00 | $51.36 |
| 201 | By-pass pumping (797-11.38) | LS | 1 | $74,949 | $45,000 | $25,000 | $257,489 |
| 202 | Concrete encasement (797-40.01) | LF | 30 | $547.28 | $250.00 | $400.00 | $98.23 |
| 203 | Additional work (797-99.01) | LS | 1 | $20,961 | $12,000 | $35,000 | $93,697 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of August 14, 2026. Compiled by Mirage Metrics.