TDOT contract CNZ042 bid tabulation
The construction of concrete bulb-tee beam bridges on s.r. 68 over u.s. 64 (u.s. 74, s.r. 40) (l.m. 18.39), including grading, drainage, and paving. Let by Tennessee DOT on February 7, 2025, Polk County. 4 bids received; low bid $10,963,940 by Wright Brothers Civil Construction, LLC.
- Owner
- Tennessee DOT
- Letting
- 07 FEB 2025
- Pay items
- 132
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Wright Brothers Civil Construction, LLC | $10,963,940 | Low |
| 2 | APAC-Atlantic, Inc. | $11,099,222 | +1.0% |
| 3 | Jones Bros. Contractors, LLC | $12,523,104 | +14% |
| 4 | Summers-Taylor, Inc. | $12,566,613 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Wright Brothers Civil Construction, LLC | 2. APAC-Atlantic, Inc. | 3. Jones Bros. Contractors, LLC | 4. Summers-Taylor, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $80,000 | $80,211 | $150,000 | $85,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $95,000 | $63,438 | $53,000 | $53,000 |
| 3 | Removal of pipe (18" ,sta. 100+70.00) (202-01.13) | LF | 69 | $49.70 | $159.91 | $125.00 | $125.00 |
| 4 | Removal of pipe (15" ,sta. 103+00.00) (202-01.14) | LF | 97 | $48.40 | $159.92 | $120.00 | $120.00 |
| 5 | Removal of asphalt pavement (202-03.01) | SY | 9,072 | $8.10 | $17.18 | $14.50 | $14.50 |
| 6 | Removal of structures (drop inlet, sta. 103+46.00) (202-04.01) | LS | 1 | $1,800.00 | $4,377.28 | $4,600.00 | $4,600.00 |
| 7 | Road & drainage excavation (unclassified) (203-01) | CY | 13,866 | $27.20 | $34.18 | $54.00 | $54.00 |
| 8 | Borrow excavation (borrow material) (203-02.05) | CY | 1,911 | $27.20 | $46.23 | $63.50 | $63.50 |
| 9 | Placing and spreading topsoil (203-04) | CY | 944 | $13.90 | $34.53 | $56.50 | $56.50 |
| 10 | Water (203-06) | MG | 190 | $19.60 | $36.42 | $70.00 | $70.00 |
| 11 | Furnishing & spreading topsoil (203-07) | CY | 238.02 | $50.75 | $89.59 | $77.00 | $77.00 |
| 12 | Backfill material (flowable fill) (204-08.01) | CY | 10 | $520.00 | $2,112.03 | $600.00 | $550.00 |
| 13 | Temporary silt fence (with backing) (209-08.02) | LF | 1,570 | $5.50 | $5.47 | $4.85 | $5.50 |
| 14 | Temporary silt fence (without backing) (209-08.03) | LF | 3,150 | $3.40 | $3.40 | $3.00 | $3.50 |
| 15 | Enhanced rock check dam (209-08.08) | EACH | 13 | $1,000.00 | $1,374.65 | $900.00 | $2,350.00 |
| 16 | Catch basin protection (type A) (209-40.30) | EACH | 6 | $1,100.00 | $1,120.00 | $1,000.00 | $1,200.00 |
| 17 | Mineral aggregate, type A base, grading D (303-01) | TON | 11,715.51 | $66.00 | $57.09 | $66.50 | $66.50 |
| 18 | Mineral aggregate (size 57) (303-10.01) | TON | 2,786 | $62.00 | $59.48 | $60.00 | $74.50 |
| 19 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 1,611.44 | $179.00 | $157.84 | $157.85 | $189.00 |
| 20 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 2,268.15 | $177.00 | $156.50 | $156.50 | $187.50 |
| 21 | Bituminous material for prime coat (PC) (402-01) | TON | 28.91 | $1,100.00 | $1,014.76 | $1,014.80 | $1,216.00 |
| 22 | Aggregate for cover material (PC) (402-02) | TON | 100.74 | $355.00 | $323.62 | $323.75 | $388.00 |
| 23 | Bituminous material for tack coat (TC) (403-01) | TON | 21 | $830.00 | $734.16 | $734.15 | $880.00 |
| 24 | Acs mix(PG64-22) grading D (411-01.10) | TON | 2,387.17 | $197.00 | $173.91 | $174.00 | $177.00 |
| 25 | Cold planing bituminous pavement (415-01.01) | TON | 1,047.62 | $49.30 | $43.44 | $43.50 | $45.00 |
| 26 | Class A concrete (roadway) (604-01.01) | CY | 392.04 | $900.00 | $724.69 | $1,000.00 | $765.00 |
| 27 | Epoxy coated reinforcing steel (604-02.03) | LB | 2,196 | $1.60 | $2.23 | $2.00 | $2.00 |
| 28 | Retaining wall (retaining wall 1) (604-07.01) | SF | 1,137 | $199.00 | $330.53 | $300.00 | $278.25 |
| 29 | 24" concrete pipe culvert (class III) (607-05.02) | LF | 197 | $154.00 | $194.60 | $213.00 | $213.00 |
| 30 | 24IN endwall (cross drain) 6:1 (611-07.59) | EACH | 3 | $4,800.00 | $3,926.37 | $8,150.00 | $8,150.00 |
| 31 | Catch basins, type 42, 0' - 4' depth (611-42.01) | EACH | 1 | $10,500 | $10,009 | $12,250 | $12,250 |
| 32 | 18" temporary drainage pipe (621-03.02) | LF | 236.50 | $75.25 | $75.99 | $102.00 | $102.00 |
| 33 | 24" temporary drainage pipe (621-03.03) | LF | 55.50 | $87.75 | $86.98 | $122.00 | $122.00 |
| 34 | Concrete curb (702-01.02) | LF | 1,086 | $39.00 | $35.62 | $30.00 | $36.00 |
| 35 | Guardrail transition 27IN to 31IN (705-02.10) | EACH | 4 | $223.00 | $224.00 | $100.00 | $230.00 |
| 36 | Earth pad for type 38 GR end treatment (705-04.09) | EACH | 5 | $2,200.00 | $2,308.30 | $1,250.00 | $2,300.00 |
| 37 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 512.50 | $38.00 | $47.04 | $39.50 | $39.50 |
| 38 | GR terminaltrailing end (type 13) MASH TL-3 (705-06.10) | EACH | 1 | $1,800.00 | $1,904.00 | $1,850.00 | $1,900.00 |
| 39 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 5 | $4,100.00 | $3,920.00 | $4,000.00 | $4,200.00 |
| 40 | Thrie beam bridge transition MASH TL-3 (705-06.25) | EACH | 6 | $2,500.00 | $3,640.00 | $3,950.00 | $2,630.00 |
| 41 | Guardrail removed (706-01) | LF | 1,263 | $4.00 | $1.12 | $1.00 | $4.00 |
| 42 | High-visibility construction fence (707-08.11) | LF | 910 | $3.15 | $3.12 | $2.75 | $3.25 |
| 43 | Historical marker - move and reset (708-02.03) | EACH | 1 | $2,300.00 | $713.33 | $1,250.00 | $1,255.00 |
| 44 | Machined rip-rap (class A-3) (709-05.05) | TON | 1,115 | $69.25 | $97.67 | $81.50 | $81.50 |
| 45 | Machined rip-rap (class A-1) (709-05.06) | TON | 136.20 | $67.25 | $97.67 | $96.00 | $96.00 |
| 46 | Traffic control (712-01) | LS | 1 | $245,000 | $134,624 | $170,000 | $162,000 |
| 47 | Interconnected portable barrier rail (712-02.02) | LF | 620 | $39.00 | $70.00 | $75.00 | $75.00 |
| 48 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 3 | $8,400.00 | $12,880 | $7,800.00 | $6,300.00 |
| 49 | Flexible drums (channelizing) (712-04.01) | EACH | 450 | $43.30 | $42.56 | $38.00 | $45.00 |
| 50 | Signs (construction) (712-06) | SF | 2,500.13 | $9.05 | $8.90 | $7.95 | $9.50 |
| 51 | Temporary barricades (type III) (712-07.03) | LF | 37 | $23.30 | $22.96 | $20.50 | $24.50 |
| 52 | Arrow board (type C) (712-08.03) | EACH | 4 | $2,300.00 | $2,240.00 | $2,000.00 | $2,400.00 |
| 53 | Queue protection truck (712-08.11) | HR | 80 | $120.00 | $117.60 | $105.00 | $125.00 |
| 54 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 8,000 | $4.75 | $5.32 | $3.65 | $4.50 |
| 55 | Removable pavement marking (stop line) (712-09.04) | LF | 427 | $28.00 | $28.00 | $26.00 | $31.00 |
| 56 | Removable pavement marking (6" line) (712-09.08) | LF | 1,250 | $3.90 | $4.76 | $3.50 | $4.25 |
| 57 | Removable black-out tape (8IN) (712-09.31) | LF | 1,000 | $5.30 | $5.32 | $3.85 | $4.50 |
| 58 | Sign post delineation enhancement (713-02.21) | LF | 10 | $6.00 | $6.94 | $6.20 | $7.50 |
| 59 | Perforated/knockout square tube post (713-11.02) | LB | 1,589 | $4.50 | $6.16 | $5.50 | $6.50 |
| 60 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 124 | $14.80 | $18.48 | $16.50 | $19.50 |
| 61 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 307 | $15.80 | $19.32 | $17.25 | $20.50 |
| 62 | Removal of signs, posts and footings (713-15) | LS | 1 | $740.00 | $560.00 | $500.00 | $600.00 |
| 63 | Removal & relocation of sign & support (713-15.02) | EACH | 3 | $342.00 | $168.00 | $150.00 | $178.00 |
| 64 | Changeable message sign unit (713-16.01) | EACH | 9 | $9,450.00 | $9,296.00 | $8,300.00 | $9,850.00 |
| 65 | Barrier mounted sign support (see plans) (713-30.09) | EACH | 4 | $484.00 | $1,344.00 | $1,200.00 | $1,425.00 |
| 66 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 41 | $56.00 | $56.00 | $41.50 | $49.00 |
| 67 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 22 | $56.00 | $56.00 | $41.50 | $49.00 |
| 68 | Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23) | EACH | 183 | $56.00 | $56.00 | $41.50 | $49.00 |
| 69 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 909 | $23.60 | $28.00 | $21.50 | $25.50 |
| 70 | Plastic pavement marking (stop line) (716-02.05) | LF | 190 | $16.80 | $14.00 | $12.00 | $14.25 |
| 71 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 3 | $280.00 | $252.00 | $175.00 | $210.00 |
| 72 | Plastic pavement marking (24" barrier line) (716-02.07) | LF | 330 | $10.10 | $8.68 | $11.00 | $13.00 |
| 73 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 836.67 | $3.35 | $2.80 | $2.50 | $3.00 |
| 74 | Plastic pavement marking (8IN line) (716-02.12) | LM | 0.28 | $11,400 | $16,921 | $10,000 | $12,000 |
| 75 | Plastic pavement marking(double turning arrow) (716-04.02) | EACH | 1 | $393.00 | $252.00 | $200.00 | $237.00 |
| 76 | Plastic pavement marking (yield line) (716-04.12) | SF | 18 | $16.80 | $28.00 | $20.00 | $24.00 |
| 77 | Plastic pavement marking (lane reduction arrow) (716-04.14) | EACH | 1 | $393.00 | $252.00 | $275.00 | $325.00 |
| 78 | Painted pavement marking (turn lane arrow) (716-05.06) | EACH | 7 | $168.00 | $56.00 | $90.00 | $107.00 |
| 79 | Painted pavement marking (6" line) (716-05.20) | LM | 3.23 | $1,790.00 | $2,802.60 | $1,350.00 | $1,600.00 |
| 80 | Painted pavement marking(4"dotted line) (716-05.21) | LF | 150 | $1.10 | $1.40 | $0.75 | $1.00 |
| 81 | Removal of pavement marking (line) (716-08.01) | LF | 25,383.26 | $1.10 | $0.56 | $0.42 | $0.50 |
| 82 | Removal of pavement marking (turn lane arrow) (716-08.06) | EACH | 5 | $140.00 | $56.00 | $85.00 | $100.00 |
| 83 | Removal of pavement marking (double turning arrow) (716-08.08) | EACH | 1 | $280.00 | $84.00 | $100.00 | $119.00 |
| 84 | Removal of pavement marking (dotted line) (716-08.09) | LF | 150 | $1.10 | $0.84 | $0.50 | $1.00 |
| 85 | Removal of pavement marking (yield line) (716-08.19) | SF | 18 | $8.95 | $14.28 | $3.25 | $4.00 |
| 86 | Contrast pavement marking 6" dotted (716-09.90) | LF | 167 | $8.95 | $16.80 | $9.75 | $11.50 |
| 87 | Contrast pavement shadow marking 6" (716-09.94) | LM | 0.21 | $44,000 | $84,001 | $24,500 | $29,000 |
| 88 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 4.32 | $9,500.00 | $8,400.89 | $6,875.00 | $8,150.00 |
| 89 | Enhanced flatline thermo PVMT MRKNG (6IN dotted line) (716-12.05) | LF | 470.83 | $2.25 | $2.53 | $2.00 | $2.40 |
| 90 | Mobilization (717-01) | LS | 1 | $912,000 | $587,960 | $1,240,000 | $900,000 |
| 91 | Geogrid reinforcement type 2 (740-07.04) | SY | 4,000 | $4.40 | $1.16 | $12.00 | $9.90 |
| 92 | Geotextile (type III)(erosion control) (740-10.03) | SY | 837.60 | $4.40 | $4.20 | $4.25 | $4.15 |
| 93 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 1,000 | $4.45 | $4.52 | $4.25 | $5.75 |
| 94 | Temporary sediment tube 18IN (740-11.03) | LF | 2,681 | $5.80 | $5.75 | $5.10 | $6.00 |
| 95 | Temporary seeding (with mulch) (801-01.07) | UNIT | 127.66 | $45.50 | $44.80 | $40.00 | $47.50 |
| 96 | Water (seeding & sodding) (801-03) | MG | 6.38 | $114.00 | $113.07 | $100.00 | $120.00 |
| 97 | Sodding (new sod) (803-01) | SY | 7,092.11 | $7.65 | $7.50 | $6.70 | $8.00 |
| 98 | Removal of structures (BR. no. 70-SR68-18.39LT) (202-04.01) | LS | 1 | $242,000 | $248,667 | $350,000 | $265,000 |
| 99 | Removal of structures (BR. no. 70-SR68-18.39RT) (202-04.02) | LS | 1 | $242,000 | $248,667 | $600,000 | $265,000 |
| 100 | Dry excavation (bridges) (204-02.01) | CY | 654 | $65.00 | $56.95 | $35.00 | $56.00 |
| 101 | Granular backfill (bridges) (303-01.02) | TON | 118 | $82.00 | $105.01 | $60.00 | $101.00 |
| 102 | Epoxy coated reinforcing steel (604-02.03) | LB | 166,930 | $1.55 | $1.57 | $1.75 | $1.45 |
| 103 | Class A concrete (bridges) (604-03.01) | CY | 468 | $1,420.00 | $1,225.75 | $1,500.00 | $1,895.00 |
| 104 | Steel bar reinforcement (bridges) (604-03.02) | LB | 86,619 | $1.30 | $1.86 | $1.50 | $1.70 |
| 105 | Pavement @ bridge ends (604-03.04) | SY | 485 | $322.00 | $485.74 | $375.00 | $411.00 |
| 106 | Class D concrete (bridge deck) (604-03.09) | CY | 702 | $1,420.00 | $1,197.11 | $1,500.00 | $1,279.00 |
| 107 | Applied texture finish (new structures) (604-04.01) | SY | 6,331 | $18.50 | $12.32 | $8.25 | $9.80 |
| 108 | Three star state emblem (604-04.41) | EACH | 12 | $3,700.00 | $2,785.37 | $4,000.00 | $2,300.00 |
| 109 | Bridge deck grooving (mechanical) (604-05.31) | SY | 2,849 | $4.35 | $12.60 | $3.83 | $5.20 |
| 110 | Steel piles (12 inch) (606-03.03) | LF | 8,151 | $79.00 | $74.54 | $75.00 | $85.00 |
| 111 | Pile tips (steel piles, 12 inch) (606-03.06) | EACH | 128 | $140.00 | $189.66 | $130.00 | $149.00 |
| 112 | Prestressed concrete bulb tee beam (6" web)(BT-63) (615-01.11) | LF | 2,539 | $375.00 | $549.33 | $475.00 | $575.00 |
| 113 | Conc parapet single slope (STD-1-1SS) (620-05.01) | LF | 1,082 | $113.00 | $156.40 | $120.00 | $145.00 |
| 114 | 6" perforated pipe with vertical drain system (710-09.01) | LF | 303 | $49.70 | $79.21 | $50.00 | $37.00 |
| 115 | 6" pipe underdrain (710-09.02) | LF | 160 | $17.95 | $42.42 | $10.00 | $30.00 |
| 116 | Pole 35FT class 5 wood (793-01.08) | EACH | 8 | $2,400.00 | $1,730.40 | $2,125.00 | $2,520.00 |
| 117 | Anchor 1IN (793-01.41) | EACH | 4 | $960.00 | $1,338.40 | $857.00 | $1,015.00 |
| 118 | Concrete handhole 4FT X 4FT X 4FT (793-11.25) | EACH | 2 | $14,000 | $15,051 | $12,500 | $14,800 |
| 119 | Dig splice pit (50 LF) (793-12.21) | EACH | 2 | $4,700.00 | $4,768.96 | $4,190.00 | $4,970.00 |
| 120 | 2 duct formation @ 36IN depth (793-13.17) | LF | 35 | $93.00 | $85.12 | $83.00 | $98.00 |
| 121 | 4 duct formation @ 36IN depth (793-13.27) | LF | 1,302 | $97.50 | $106.40 | $87.00 | $103.00 |
| 122 | 6 duct formation @ 36IN depth (793-13.32) | LF | 130 | $129.00 | $196.00 | $115.00 | $136.00 |
| 123 | Concrete encasement per duct (793-14.02) | LF | 6,058 | $14.60 | $8.80 | $13.00 | $15.40 |
| 124 | MH precast 4-FT W X 8-FT L X 6-FT H (793-14.05) | EACH | 1 | $36,100 | $26,009 | $32,150 | $38,100 |
| 125 | Bridge conduit hanger system (793-14.09) | LS | 1 | $101,500 | $103,965 | $90,500 | $110,000 |
| 126 | Multi duct (793-14.14) | LF | 2,030 | $3.50 | $5.88 | $3.10 | $3.60 |
| 127 | Rod ducts (793-14.21) | LF | 4,060 | $1.35 | $1.29 | $1.20 | $1.40 |
| 128 | Underground to overhead riser (793-14.26) | EACH | 5 | $660.00 | $1,613.92 | $588.00 | $697.00 |
| 129 | Directional bore 4IN/flex sleeve (793-16.04) | LF | 420 | $89.25 | $122.08 | $79.50 | $94.00 |
| 130 | Bore/jack 16IN casing - unconsolidated (793-16.09) | LF | 280 | $990.00 | $1,246.56 | $885.00 | $1,760.00 |
| 131 | Adjust manhole lid (793-16.21) | EACH | 1 | $1,600.00 | $2,128.00 | $1,465.00 | $1,737.00 |
| 132 | MH(retire/remove/sand backfill) (793-16.25) | EACH | 1 | $1,600.00 | $11,480 | $1,455.00 | $1,725.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of February 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.