TDOT contract CNZ111 bid tabulation

The grading, drainage, construction of a concrete box beam bridge, and paving on a s.i.a. route serving project sim (portobello america, inc.). Let by Tennessee DOT on October 3, 2025, Putnam County. 7 bids received; low bid $3,976,193 by Rogers Group, Inc..

Owner
Tennessee DOT
Letting
03 OCT 2025
Pay items
111
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Rogers Group, Inc.$3,976,193Low
2Mack Construction, LLC$4,224,135+6.0%
3Cleary Construction, Inc.$4,740,588+19%
4Bell & Associates Construction, LLC$4,868,439+22%
5MasTec Civil, LLC$4,912,852+24%
6Middle Tennessee Infrastructure, Inc.$5,594,660+41%
7Kenneth Rich Construction Company, Inc.$6,116,836+54%
TDOT contract CNZ111: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Rogers Group, Inc.2. Mack Construction, LLC3. Cleary Construction, Inc.4. Bell & Associates Construction, LLC5. MasTec Civil, LLC6. Middle Tennessee Infrastructure, Inc.
1Construction stakes, lines and grades (105-01)LS1$31,950$20,000$105,000$38,000$128,500$135,000
2Clearing and grubbing (201-01)LS1$79,379$25,000$128,000$225,000$100,000$175,000
3Removal of pipe (24", ditty 20+45.00) (202-01.13)LF45$60.00$14.00$33.00$30.00$20.00$20.00
4Removal of pipe (24", ditty 22+76.00) (202-01.14)LF46$60.00$14.00$33.00$30.00$20.00$20.00
5Removal of pipe (48", ditty 25+93.00) (202-01.15)LF53$76.00$20.00$33.00$75.00$20.00$20.00
6Removal of pipe (12" ,baxter 101+40) (202-02.01)LF33$45.00$14.00$33.00$21.00$15.00$20.00
7Removal of pipe (12" , baxter 102+00) (202-02.02)LF27$55.00$14.00$33.00$21.00$15.00$20.00
8Removal of pipe (18" , baxter 106+00) (202-02.03)LF30$50.00$14.00$33.00$24.00$20.00$20.00
9Removal of pipe (12" , ditty 26+84) (202-02.04)LF21$67.00$14.00$33.00$21.00$15.00$20.00
10Removal of pipe (18", ditty 30+04) (202-02.05)LF40$54.00$14.00$33.00$24.00$20.00$20.00
11Removal of pipe (12" ,ditty 30+52) (202-02.06)LF20$71.00$14.00$33.00$21.00$15.00$20.00
12Removal of curb (tract 14 driveway) (202-08.10)LF62$17.00$7.00$19.00$8.00$9.00$5.00
13Road & drainage excavation (unclassified) (203-01)CY58,036$7.00$8.25$8.80$16.40$7.50$17.00
14Borrow excavation (graded solid rock) (203-02.01)TON30,600$15.00$22.00$21.10$22.00$21.50$28.00
15Placing and spreading topsoil (203-04)CY3,706$17.50$8.00$19.35$9.00$11.00$17.00
16Undercutting (203-05)CY10,400$18.60$14.00$8.00$19.50$8.00$17.00
17Water (203-06)MG57$675.00$33.00$64.00$75.00$9.00$15.00
18Furnishing & spreading topsoil (203-07)CY486$21.00$49.00$19.35$35.00$6.29$65.00
19Channel substrate (203-20.01)CY165$32.75$75.00$26.00$67.00$39.00$100.00
20Filter sock (12 inch) (209-03.21)LF300$4.25$4.20$4.60$4.50$8.00$4.45
21Sediment removal (209-05)CY304$26.40$14.00$40.25$25.00$21.00$10.00
22Temporary silt fence (with backing) (209-08.02)LF8,243$5.55$5.75$6.25$6.00$5.50$5.40
23Rock check dam (209-08.07)EACH145$505.00$500.00$335.00$520.00$729.00$650.00
24Enhanced rock check dam (209-08.08)EACH41$715.00$700.00$550.00$750.00$729.00$860.00
25Sediment filter bag (15' X 15') (209-09.03)EACH4$635.00$680.00$700.00$450.00$540.00$255.00
26Temporary in stream diversion (209-65.04)LF240$105.00$72.00$82.25$70.00$135.00$50.00
27Mineral aggregate, type A base, grading D (303-01)TON13,878$26.00$28.00$28.20$26.00$28.50$26.00
28Granular backfill (roadway) (303-01.01)TON2,052$20.00$39.00$50.00$29.00$29.00$58.00
29Mineral aggregate (size 57) (303-10.01)TON84$48.00$51.00$41.00$44.00$70.00$50.00
30Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON1,899$95.00$105.00$109.00$100.00$105.00$110.00
31Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON1,559$112.00$125.00$132.00$121.00$127.00$133.00
32Bituminous material for prime coat (PC) (402-01)TON26$1,075.00$1,150.00$1,235.00$1,126.00$1,190.00$1,250.00
33Aggregate for cover material (PC) (402-02)TON64$120.00$135.00$138.00$126.00$132.00$135.00
34Bituminous material for tack coat (TC) (403-01)TON10$1,000.00$1,100.00$1,150.00$1,047.00$1,105.00$1,150.00
35Saw cutting asphalt pavement (407-20.05)LF2,800$1.50$4.00$5.75$4.00$3.00$3.00
36Acs mix (PG64-22) grading E shoulder (411-01.07)TON205$127.00$145.00$150.00$137.00$145.00$150.00
37Acs mix(PG64-22) grading D (411-01.10)TON1,479$132.00$150.00$156.00$142.00$148.00$155.00
38Scoring for rumble stripe (non-continuous) (8IN width) (411-12.03)LM2.60$739.50$730.00$810.00$733.00$2,200.00$810.00
39Cold planing bituminous pavement (415-01.01)TON407$60.00$65.00$70.00$63.00$67.00$70.00
4018" concrete pipe culvert (class III) (607-03.02)LF50$90.00$86.00$115.00$115.00$75.00$170.00
4130" concrete pipe culvert (class III) (607-06.02)LF54$145.00$125.00$158.00$129.00$136.00$140.00
4236" concrete pipe culvert (class III) (607-07.02)LF112$180.00$175.00$185.00$150.00$165.00$150.00
4318" pipe culvert (side drain) (607-39.02)LF287$70.00$88.00$83.00$82.00$82.00$55.00
4424" pipe culvert (side drain) (607-39.03)LF47$93.00$125.00$114.00$111.00$110.00$85.00
45Adjustment of existing manhole (611-01.20)EACH1$2,170.00$1,265.00$3,400.00$2,050.00$12,500$3,300.00
4618IN endwall (side drain) (611-07.31)EACH19$5,240.00$5,000.00$4,350.00$4,700.00$5,000.00$4,000.00
4724IN endwall (side drain) (611-07.32)EACH4$7,440.00$5,800.00$5,600.00$6,400.00$6,000.00$5,600.00
4818IN endwall (cross drain) 4:1 (611-07.55)EACH2$4,170.00$3,500.00$2,900.00$3,000.00$3,000.00$2,100.00
4930IN endwall (cross drain) 4:1 (611-07.61)EACH2$5,620.00$6,800.00$4,900.00$6,200.00$5,500.00$5,100.00
5036IN endwall (cross drain) 4:1 (611-07.64)EACH2$9,690.00$7,600.00$4,800.00$9,000.00$7,000.00$7,800.00
51Junction structure, 48IN round,> 4FT-8FT depth (611-63.01)EACH1$5,100.00$4,340.00$5,400.00$5,100.00$5,000.00$6,500.00
52Metal beam guard fence (705-01.04)LF50$103.45$112.00$124.00$115.00$115.00$125.00
53Earth pad for guard rail end treatment (705-04.10)EACH10$2,590.00$835.00$1,900.00$840.00$863.00$925.00
54W beam GR (type 2) MASH TL-3 (705-06.01)LF1,444$33.62$28.00$30.00$27.50$28.00$30.00
55GR terminaltrailing end (type 13) MASH TL-3 (705-06.10)EACH2$1,371.00$2,050.00$2,250.00$2,050.00$2,100.00$2,200.00
56GR terminal (in-inline) MASH TL-3 (705-06.11)EACH3$1,397.00$1,825.00$2,000.00$1,850.00$1,890.00$2,000.00
57Short-radius guardrail system (16 FT radius) MASH TL-3 (705-06.15)EACH1$8,793.00$11,500$12,730$11,515$12,000$12,700
58Short-radius guardrail system (48FT radius) MASH TL-3 (705-06.19)EACH2$11,637$15,650$17,350$15,750$16,000$17,000
59GR terminal (energy absorbing) MASH TL-2 (705-06.30)EACH10$3,129.00$2,800.00$3,000.00$2,730.00$2,700.00$3,000.00
60Guardrail removed (706-01)LF225$2.07$1.00$1.00$0.60$1.00$0.50
61High-visibility construction fence (707-08.11)LF2,585$3.18$3.15$4.00$3.50$4.00$2.30
62Machined rip-rap (class A-3) (709-05.05)TON180$37.24$49.00$50.00$43.00$56.00$45.00
63Machined rip-rap (class A-1) (709-05.06)TON315$37.24$49.00$50.00$43.00$138.00$48.00
64Machined rip-rap (class B) (709-05.08)TON1,317$35.42$51.00$50.00$44.00$55.00$50.00
65Traffic control (712-01)LS1$103,000$50,000$95,000$16,600$30,000$166,000
66Interconnected portable barrier rail (712-02.02)LF350$11.00$40.00$45.00$35.00$67.00$50.00
67Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH4$5,377.00$5,500.00$11,500$7,100.00$6,993.00$7,500.00
68Flexible drums (channelizing) (712-04.01)EACH128$20.50$35.00$35.00$33.00$34.00$35.00
69Barrier rail delineator (712-04.50)EACH6$13.05$16.00$15.00$11.00$10.00$17.00
70Warning lights (type A) (712-05.01)EACH28$25.60$28.00$35.00$13.00$13.00$30.00
71Signs (construction) (712-06)SF867$8.20$8.00$9.50$8.00$7.50$8.40
72Temporary barricades (type III) (712-07.03)LF168$22.60$16.00$23.00$23.50$21.50$17.00
73Removable pavement marking (6" line) (712-09.08)LF185$3.85$4.00$3.00$4.00$4.50$4.35
74Perforated/knockout square tube post (713-11.02)LB501$4.45$4.50$5.00$7.00$5.40$5.00
75Flat sheet aluminum signs (0.080" thick) (713-13.02)SF60$13.70$16.00$18.00$17.00$17.00$17.60
76Flat sheet aluminum signs (0.100" thick) (713-13.03)SF63$15.25$17.50$20.00$18.00$15.00$20.00
77Removal of signs, posts and footings (713-15)LS1$1,004.00$210.00$230.00$930.00$2,300.00$250.00
78Changeable message sign unit (713-16.01)EACH3$6,964.00$6,300.00$7,500.00$6,100.00$5,775.00$7,900.00
79End of roadway sign and support (713-16.07)EACH3$389.20$172.00$190.00$410.00$300.00$190.00
80Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH140$51.20$53.00$54.00$53.00$57.00$57.00
81Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22)EACH25$51.20$53.00$54.00$53.00$57.00$57.00
82Removal of snowplowable reflective marker (716-01.30)EACH20$31.50$32.00$29.00$33.00$36.00$35.00
83Plastic pavement marking (stop line) (716-02.05)LF73$15.36$16.00$14.00$16.50$18.00$17.00
84Plastic pavement marking (turn lane arrow) (716-02.06)EACH6$256.00$260.00$201.00$274.00$300.00$290.00
85Plastic pavement marking (8" dotted line) (716-02.08)LF327$2.05$2.10$4.00$2.20$2.40$2.30
86Plastic pavement marking (8IN line) (716-02.12)LM0.10$10,815$11,000$13,200$11,100$11,800$12,225
87Painted pavement marking (6" line) (716-05.20)LM3.60$973.00$1,000.00$1,250.00$1,000.00$1,100.00$1,100.00
88Spray thermo PVMT MRKNG (60 mil) (6IN line) (716-13.02)LM4$3,892.00$4,000.00$4,310.00$4,000.00$4,550.00$4,400.00
89Mobilization (717-01)LS1$125,970$65,000$234,000$50,000$491,000$300,000
90Geomembrane (740-06.01)SY50$15.25$100.00$10.00$220.00$22.00$50.00
91Geotextile (type III)(erosion control) (740-10.03)SY1,502$3.43$3.50$6.00$2.00$4.00$3.90
92Geotextile (type IV)(stabilization) (740-10.04)SY22,500$2.45$3.25$4.00$2.50$5.00$2.25
93Temporary sediment tube 18IN (740-11.03)LF2,389$5.28$5.25$6.00$5.50$4.40$3.20
94Seeding (with mulch) (801-01)UNIT8$84.52$85.00$92.00$88.00$108.00$58.00
95Temporary seeding (with mulch) (801-01.07)UNIT88$52.82$55.00$58.00$55.00$54.00$58.00
96Natve seed MX encapsulation & clear zone (801-01.37)UNIT1$528.00$525.00$580.00$550.00$540.00$580.00
97Natve seed MX final stablizatn of slopes (801-01.38)UNIT2$528.00$525.00$580.00$550.00$540.00$580.00
98Water (seeding & sodding) (801-03)MG249$69.00$80.00$75.00$70.00$54.00$58.00
99Cuttings: salix nigra (18IN-24IN length) (802-02.30)EACH7$23.50$23.00$26.00$24.00$19.00$21.00
100Acer negundo (box elder seedlng B.R.) (802-12.01)EACH7$23.50$23.00$26.00$24.00$27.00$29.00
101Acer rubrum (red maple seedlng B.R.) (802-12.02)EACH7$23.50$23.00$26.00$24.00$27.00$29.00
102Platanus occidentalis (sycamore seedlng B.R.) (802-12.26)EACH8$23.50$23.00$26.00$24.00$27.00$29.00
103Quercus palustris (pin oak seedlng B.R.) (802-12.37)EACH7$23.50$23.00$26.00$24.00$27.00$29.00
104Ulmus americana (american elm seedlng B.R.) (802-12.44)EACH7$23.50$23.00$26.00$24.00$27.00$29.00
105Sodding (new sod) (803-01)SY24,203$5.81$5.75$7.00$6.00$6.00$6.65
106Erosion control blanket (type II) (805-12.02)SY50$10.56$11.00$11.50$11.00$8.00$1.40
107Removal of structures and obstructions (202-01.01)LS1$19,420$18,000$40,000$13,000$15,000$10,000
108Foundation fill material (204-08)CY65$72.00$105.00$175.00$67.00$136.00$174.00
109Class A concrete (box bridges) (604-02.01)CY182$1,908.00$1,925.00$1,910.00$2,500.00$2,822.00$1,700.00
110Steel bar reinforcement (box bridges) (604-02.02)LB38,877$0.66$2.65$2.30$1.00$1.05$2.30
111Epoxy coated reinforcing steel (604-02.03)LB1,589$0.92$3.00$2.60$1.40$2.10$2.60
TDOT contract CNZ111: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of October 3, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy