TDOT contract CNZ111 bid tabulation
The grading, drainage, construction of a concrete box beam bridge, and paving on a s.i.a. route serving project sim (portobello america, inc.). Let by Tennessee DOT on October 3, 2025, Putnam County. 7 bids received; low bid $3,976,193 by Rogers Group, Inc..
- Owner
- Tennessee DOT
- Letting
- 03 OCT 2025
- Pay items
- 111
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rogers Group, Inc. | $3,976,193 | Low |
| 2 | Mack Construction, LLC | $4,224,135 | +6.0% |
| 3 | Cleary Construction, Inc. | $4,740,588 | +19% |
| 4 | Bell & Associates Construction, LLC | $4,868,439 | +22% |
| 5 | MasTec Civil, LLC | $4,912,852 | +24% |
| 6 | Middle Tennessee Infrastructure, Inc. | $5,594,660 | +41% |
| 7 | Kenneth Rich Construction Company, Inc. | $6,116,836 | +54% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rogers Group, Inc. | 2. Mack Construction, LLC | 3. Cleary Construction, Inc. | 4. Bell & Associates Construction, LLC | 5. MasTec Civil, LLC | 6. Middle Tennessee Infrastructure, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $31,950 | $20,000 | $105,000 | $38,000 | $128,500 | $135,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $79,379 | $25,000 | $128,000 | $225,000 | $100,000 | $175,000 |
| 3 | Removal of pipe (24", ditty 20+45.00) (202-01.13) | LF | 45 | $60.00 | $14.00 | $33.00 | $30.00 | $20.00 | $20.00 |
| 4 | Removal of pipe (24", ditty 22+76.00) (202-01.14) | LF | 46 | $60.00 | $14.00 | $33.00 | $30.00 | $20.00 | $20.00 |
| 5 | Removal of pipe (48", ditty 25+93.00) (202-01.15) | LF | 53 | $76.00 | $20.00 | $33.00 | $75.00 | $20.00 | $20.00 |
| 6 | Removal of pipe (12" ,baxter 101+40) (202-02.01) | LF | 33 | $45.00 | $14.00 | $33.00 | $21.00 | $15.00 | $20.00 |
| 7 | Removal of pipe (12" , baxter 102+00) (202-02.02) | LF | 27 | $55.00 | $14.00 | $33.00 | $21.00 | $15.00 | $20.00 |
| 8 | Removal of pipe (18" , baxter 106+00) (202-02.03) | LF | 30 | $50.00 | $14.00 | $33.00 | $24.00 | $20.00 | $20.00 |
| 9 | Removal of pipe (12" , ditty 26+84) (202-02.04) | LF | 21 | $67.00 | $14.00 | $33.00 | $21.00 | $15.00 | $20.00 |
| 10 | Removal of pipe (18", ditty 30+04) (202-02.05) | LF | 40 | $54.00 | $14.00 | $33.00 | $24.00 | $20.00 | $20.00 |
| 11 | Removal of pipe (12" ,ditty 30+52) (202-02.06) | LF | 20 | $71.00 | $14.00 | $33.00 | $21.00 | $15.00 | $20.00 |
| 12 | Removal of curb (tract 14 driveway) (202-08.10) | LF | 62 | $17.00 | $7.00 | $19.00 | $8.00 | $9.00 | $5.00 |
| 13 | Road & drainage excavation (unclassified) (203-01) | CY | 58,036 | $7.00 | $8.25 | $8.80 | $16.40 | $7.50 | $17.00 |
| 14 | Borrow excavation (graded solid rock) (203-02.01) | TON | 30,600 | $15.00 | $22.00 | $21.10 | $22.00 | $21.50 | $28.00 |
| 15 | Placing and spreading topsoil (203-04) | CY | 3,706 | $17.50 | $8.00 | $19.35 | $9.00 | $11.00 | $17.00 |
| 16 | Undercutting (203-05) | CY | 10,400 | $18.60 | $14.00 | $8.00 | $19.50 | $8.00 | $17.00 |
| 17 | Water (203-06) | MG | 57 | $675.00 | $33.00 | $64.00 | $75.00 | $9.00 | $15.00 |
| 18 | Furnishing & spreading topsoil (203-07) | CY | 486 | $21.00 | $49.00 | $19.35 | $35.00 | $6.29 | $65.00 |
| 19 | Channel substrate (203-20.01) | CY | 165 | $32.75 | $75.00 | $26.00 | $67.00 | $39.00 | $100.00 |
| 20 | Filter sock (12 inch) (209-03.21) | LF | 300 | $4.25 | $4.20 | $4.60 | $4.50 | $8.00 | $4.45 |
| 21 | Sediment removal (209-05) | CY | 304 | $26.40 | $14.00 | $40.25 | $25.00 | $21.00 | $10.00 |
| 22 | Temporary silt fence (with backing) (209-08.02) | LF | 8,243 | $5.55 | $5.75 | $6.25 | $6.00 | $5.50 | $5.40 |
| 23 | Rock check dam (209-08.07) | EACH | 145 | $505.00 | $500.00 | $335.00 | $520.00 | $729.00 | $650.00 |
| 24 | Enhanced rock check dam (209-08.08) | EACH | 41 | $715.00 | $700.00 | $550.00 | $750.00 | $729.00 | $860.00 |
| 25 | Sediment filter bag (15' X 15') (209-09.03) | EACH | 4 | $635.00 | $680.00 | $700.00 | $450.00 | $540.00 | $255.00 |
| 26 | Temporary in stream diversion (209-65.04) | LF | 240 | $105.00 | $72.00 | $82.25 | $70.00 | $135.00 | $50.00 |
| 27 | Mineral aggregate, type A base, grading D (303-01) | TON | 13,878 | $26.00 | $28.00 | $28.20 | $26.00 | $28.50 | $26.00 |
| 28 | Granular backfill (roadway) (303-01.01) | TON | 2,052 | $20.00 | $39.00 | $50.00 | $29.00 | $29.00 | $58.00 |
| 29 | Mineral aggregate (size 57) (303-10.01) | TON | 84 | $48.00 | $51.00 | $41.00 | $44.00 | $70.00 | $50.00 |
| 30 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 1,899 | $95.00 | $105.00 | $109.00 | $100.00 | $105.00 | $110.00 |
| 31 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 1,559 | $112.00 | $125.00 | $132.00 | $121.00 | $127.00 | $133.00 |
| 32 | Bituminous material for prime coat (PC) (402-01) | TON | 26 | $1,075.00 | $1,150.00 | $1,235.00 | $1,126.00 | $1,190.00 | $1,250.00 |
| 33 | Aggregate for cover material (PC) (402-02) | TON | 64 | $120.00 | $135.00 | $138.00 | $126.00 | $132.00 | $135.00 |
| 34 | Bituminous material for tack coat (TC) (403-01) | TON | 10 | $1,000.00 | $1,100.00 | $1,150.00 | $1,047.00 | $1,105.00 | $1,150.00 |
| 35 | Saw cutting asphalt pavement (407-20.05) | LF | 2,800 | $1.50 | $4.00 | $5.75 | $4.00 | $3.00 | $3.00 |
| 36 | Acs mix (PG64-22) grading E shoulder (411-01.07) | TON | 205 | $127.00 | $145.00 | $150.00 | $137.00 | $145.00 | $150.00 |
| 37 | Acs mix(PG64-22) grading D (411-01.10) | TON | 1,479 | $132.00 | $150.00 | $156.00 | $142.00 | $148.00 | $155.00 |
| 38 | Scoring for rumble stripe (non-continuous) (8IN width) (411-12.03) | LM | 2.60 | $739.50 | $730.00 | $810.00 | $733.00 | $2,200.00 | $810.00 |
| 39 | Cold planing bituminous pavement (415-01.01) | TON | 407 | $60.00 | $65.00 | $70.00 | $63.00 | $67.00 | $70.00 |
| 40 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 50 | $90.00 | $86.00 | $115.00 | $115.00 | $75.00 | $170.00 |
| 41 | 30" concrete pipe culvert (class III) (607-06.02) | LF | 54 | $145.00 | $125.00 | $158.00 | $129.00 | $136.00 | $140.00 |
| 42 | 36" concrete pipe culvert (class III) (607-07.02) | LF | 112 | $180.00 | $175.00 | $185.00 | $150.00 | $165.00 | $150.00 |
| 43 | 18" pipe culvert (side drain) (607-39.02) | LF | 287 | $70.00 | $88.00 | $83.00 | $82.00 | $82.00 | $55.00 |
| 44 | 24" pipe culvert (side drain) (607-39.03) | LF | 47 | $93.00 | $125.00 | $114.00 | $111.00 | $110.00 | $85.00 |
| 45 | Adjustment of existing manhole (611-01.20) | EACH | 1 | $2,170.00 | $1,265.00 | $3,400.00 | $2,050.00 | $12,500 | $3,300.00 |
| 46 | 18IN endwall (side drain) (611-07.31) | EACH | 19 | $5,240.00 | $5,000.00 | $4,350.00 | $4,700.00 | $5,000.00 | $4,000.00 |
| 47 | 24IN endwall (side drain) (611-07.32) | EACH | 4 | $7,440.00 | $5,800.00 | $5,600.00 | $6,400.00 | $6,000.00 | $5,600.00 |
| 48 | 18IN endwall (cross drain) 4:1 (611-07.55) | EACH | 2 | $4,170.00 | $3,500.00 | $2,900.00 | $3,000.00 | $3,000.00 | $2,100.00 |
| 49 | 30IN endwall (cross drain) 4:1 (611-07.61) | EACH | 2 | $5,620.00 | $6,800.00 | $4,900.00 | $6,200.00 | $5,500.00 | $5,100.00 |
| 50 | 36IN endwall (cross drain) 4:1 (611-07.64) | EACH | 2 | $9,690.00 | $7,600.00 | $4,800.00 | $9,000.00 | $7,000.00 | $7,800.00 |
| 51 | Junction structure, 48IN round,> 4FT-8FT depth (611-63.01) | EACH | 1 | $5,100.00 | $4,340.00 | $5,400.00 | $5,100.00 | $5,000.00 | $6,500.00 |
| 52 | Metal beam guard fence (705-01.04) | LF | 50 | $103.45 | $112.00 | $124.00 | $115.00 | $115.00 | $125.00 |
| 53 | Earth pad for guard rail end treatment (705-04.10) | EACH | 10 | $2,590.00 | $835.00 | $1,900.00 | $840.00 | $863.00 | $925.00 |
| 54 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 1,444 | $33.62 | $28.00 | $30.00 | $27.50 | $28.00 | $30.00 |
| 55 | GR terminaltrailing end (type 13) MASH TL-3 (705-06.10) | EACH | 2 | $1,371.00 | $2,050.00 | $2,250.00 | $2,050.00 | $2,100.00 | $2,200.00 |
| 56 | GR terminal (in-inline) MASH TL-3 (705-06.11) | EACH | 3 | $1,397.00 | $1,825.00 | $2,000.00 | $1,850.00 | $1,890.00 | $2,000.00 |
| 57 | Short-radius guardrail system (16 FT radius) MASH TL-3 (705-06.15) | EACH | 1 | $8,793.00 | $11,500 | $12,730 | $11,515 | $12,000 | $12,700 |
| 58 | Short-radius guardrail system (48FT radius) MASH TL-3 (705-06.19) | EACH | 2 | $11,637 | $15,650 | $17,350 | $15,750 | $16,000 | $17,000 |
| 59 | GR terminal (energy absorbing) MASH TL-2 (705-06.30) | EACH | 10 | $3,129.00 | $2,800.00 | $3,000.00 | $2,730.00 | $2,700.00 | $3,000.00 |
| 60 | Guardrail removed (706-01) | LF | 225 | $2.07 | $1.00 | $1.00 | $0.60 | $1.00 | $0.50 |
| 61 | High-visibility construction fence (707-08.11) | LF | 2,585 | $3.18 | $3.15 | $4.00 | $3.50 | $4.00 | $2.30 |
| 62 | Machined rip-rap (class A-3) (709-05.05) | TON | 180 | $37.24 | $49.00 | $50.00 | $43.00 | $56.00 | $45.00 |
| 63 | Machined rip-rap (class A-1) (709-05.06) | TON | 315 | $37.24 | $49.00 | $50.00 | $43.00 | $138.00 | $48.00 |
| 64 | Machined rip-rap (class B) (709-05.08) | TON | 1,317 | $35.42 | $51.00 | $50.00 | $44.00 | $55.00 | $50.00 |
| 65 | Traffic control (712-01) | LS | 1 | $103,000 | $50,000 | $95,000 | $16,600 | $30,000 | $166,000 |
| 66 | Interconnected portable barrier rail (712-02.02) | LF | 350 | $11.00 | $40.00 | $45.00 | $35.00 | $67.00 | $50.00 |
| 67 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 4 | $5,377.00 | $5,500.00 | $11,500 | $7,100.00 | $6,993.00 | $7,500.00 |
| 68 | Flexible drums (channelizing) (712-04.01) | EACH | 128 | $20.50 | $35.00 | $35.00 | $33.00 | $34.00 | $35.00 |
| 69 | Barrier rail delineator (712-04.50) | EACH | 6 | $13.05 | $16.00 | $15.00 | $11.00 | $10.00 | $17.00 |
| 70 | Warning lights (type A) (712-05.01) | EACH | 28 | $25.60 | $28.00 | $35.00 | $13.00 | $13.00 | $30.00 |
| 71 | Signs (construction) (712-06) | SF | 867 | $8.20 | $8.00 | $9.50 | $8.00 | $7.50 | $8.40 |
| 72 | Temporary barricades (type III) (712-07.03) | LF | 168 | $22.60 | $16.00 | $23.00 | $23.50 | $21.50 | $17.00 |
| 73 | Removable pavement marking (6" line) (712-09.08) | LF | 185 | $3.85 | $4.00 | $3.00 | $4.00 | $4.50 | $4.35 |
| 74 | Perforated/knockout square tube post (713-11.02) | LB | 501 | $4.45 | $4.50 | $5.00 | $7.00 | $5.40 | $5.00 |
| 75 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 60 | $13.70 | $16.00 | $18.00 | $17.00 | $17.00 | $17.60 |
| 76 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 63 | $15.25 | $17.50 | $20.00 | $18.00 | $15.00 | $20.00 |
| 77 | Removal of signs, posts and footings (713-15) | LS | 1 | $1,004.00 | $210.00 | $230.00 | $930.00 | $2,300.00 | $250.00 |
| 78 | Changeable message sign unit (713-16.01) | EACH | 3 | $6,964.00 | $6,300.00 | $7,500.00 | $6,100.00 | $5,775.00 | $7,900.00 |
| 79 | End of roadway sign and support (713-16.07) | EACH | 3 | $389.20 | $172.00 | $190.00 | $410.00 | $300.00 | $190.00 |
| 80 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 140 | $51.20 | $53.00 | $54.00 | $53.00 | $57.00 | $57.00 |
| 81 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 25 | $51.20 | $53.00 | $54.00 | $53.00 | $57.00 | $57.00 |
| 82 | Removal of snowplowable reflective marker (716-01.30) | EACH | 20 | $31.50 | $32.00 | $29.00 | $33.00 | $36.00 | $35.00 |
| 83 | Plastic pavement marking (stop line) (716-02.05) | LF | 73 | $15.36 | $16.00 | $14.00 | $16.50 | $18.00 | $17.00 |
| 84 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 6 | $256.00 | $260.00 | $201.00 | $274.00 | $300.00 | $290.00 |
| 85 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 327 | $2.05 | $2.10 | $4.00 | $2.20 | $2.40 | $2.30 |
| 86 | Plastic pavement marking (8IN line) (716-02.12) | LM | 0.10 | $10,815 | $11,000 | $13,200 | $11,100 | $11,800 | $12,225 |
| 87 | Painted pavement marking (6" line) (716-05.20) | LM | 3.60 | $973.00 | $1,000.00 | $1,250.00 | $1,000.00 | $1,100.00 | $1,100.00 |
| 88 | Spray thermo PVMT MRKNG (60 mil) (6IN line) (716-13.02) | LM | 4 | $3,892.00 | $4,000.00 | $4,310.00 | $4,000.00 | $4,550.00 | $4,400.00 |
| 89 | Mobilization (717-01) | LS | 1 | $125,970 | $65,000 | $234,000 | $50,000 | $491,000 | $300,000 |
| 90 | Geomembrane (740-06.01) | SY | 50 | $15.25 | $100.00 | $10.00 | $220.00 | $22.00 | $50.00 |
| 91 | Geotextile (type III)(erosion control) (740-10.03) | SY | 1,502 | $3.43 | $3.50 | $6.00 | $2.00 | $4.00 | $3.90 |
| 92 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 22,500 | $2.45 | $3.25 | $4.00 | $2.50 | $5.00 | $2.25 |
| 93 | Temporary sediment tube 18IN (740-11.03) | LF | 2,389 | $5.28 | $5.25 | $6.00 | $5.50 | $4.40 | $3.20 |
| 94 | Seeding (with mulch) (801-01) | UNIT | 8 | $84.52 | $85.00 | $92.00 | $88.00 | $108.00 | $58.00 |
| 95 | Temporary seeding (with mulch) (801-01.07) | UNIT | 88 | $52.82 | $55.00 | $58.00 | $55.00 | $54.00 | $58.00 |
| 96 | Natve seed MX encapsulation & clear zone (801-01.37) | UNIT | 1 | $528.00 | $525.00 | $580.00 | $550.00 | $540.00 | $580.00 |
| 97 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 2 | $528.00 | $525.00 | $580.00 | $550.00 | $540.00 | $580.00 |
| 98 | Water (seeding & sodding) (801-03) | MG | 249 | $69.00 | $80.00 | $75.00 | $70.00 | $54.00 | $58.00 |
| 99 | Cuttings: salix nigra (18IN-24IN length) (802-02.30) | EACH | 7 | $23.50 | $23.00 | $26.00 | $24.00 | $19.00 | $21.00 |
| 100 | Acer negundo (box elder seedlng B.R.) (802-12.01) | EACH | 7 | $23.50 | $23.00 | $26.00 | $24.00 | $27.00 | $29.00 |
| 101 | Acer rubrum (red maple seedlng B.R.) (802-12.02) | EACH | 7 | $23.50 | $23.00 | $26.00 | $24.00 | $27.00 | $29.00 |
| 102 | Platanus occidentalis (sycamore seedlng B.R.) (802-12.26) | EACH | 8 | $23.50 | $23.00 | $26.00 | $24.00 | $27.00 | $29.00 |
| 103 | Quercus palustris (pin oak seedlng B.R.) (802-12.37) | EACH | 7 | $23.50 | $23.00 | $26.00 | $24.00 | $27.00 | $29.00 |
| 104 | Ulmus americana (american elm seedlng B.R.) (802-12.44) | EACH | 7 | $23.50 | $23.00 | $26.00 | $24.00 | $27.00 | $29.00 |
| 105 | Sodding (new sod) (803-01) | SY | 24,203 | $5.81 | $5.75 | $7.00 | $6.00 | $6.00 | $6.65 |
| 106 | Erosion control blanket (type II) (805-12.02) | SY | 50 | $10.56 | $11.00 | $11.50 | $11.00 | $8.00 | $1.40 |
| 107 | Removal of structures and obstructions (202-01.01) | LS | 1 | $19,420 | $18,000 | $40,000 | $13,000 | $15,000 | $10,000 |
| 108 | Foundation fill material (204-08) | CY | 65 | $72.00 | $105.00 | $175.00 | $67.00 | $136.00 | $174.00 |
| 109 | Class A concrete (box bridges) (604-02.01) | CY | 182 | $1,908.00 | $1,925.00 | $1,910.00 | $2,500.00 | $2,822.00 | $1,700.00 |
| 110 | Steel bar reinforcement (box bridges) (604-02.02) | LB | 38,877 | $0.66 | $2.65 | $2.30 | $1.00 | $1.05 | $2.30 |
| 111 | Epoxy coated reinforcing steel (604-02.03) | LB | 1,589 | $0.92 | $3.00 | $2.60 | $1.40 | $2.10 | $2.60 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 3, 2025. Compiled by Mirage Metrics.