TDOT contract CNZ164 bid tabulation
The construction of pedestrian facilities on s.r. 100 from the fairview community center (l.m. 3.08) to bowie lake road (l.m. 5.19), including intersection improvements at cumberland drive. Let by Tennessee DOT on May 9, 2025, Williamson County. 4 bids received; low bid $6,987,981 by Eubank Asphalt Paving & Sealing, LLC.
- Owner
- Tennessee DOT
- Letting
- 09 MAY 2025
- Pay items
- 171
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Eubank Asphalt Paving & Sealing, LLC | $6,987,981 | Low |
| 2 | Parchman Construction Company, Inc. | $7,428,118 | +6.0% |
| 3 | Civil Constructors, LLC | $7,992,414 | +14% |
| 4 | Cleary Construction, Inc. | $9,940,621 | +42% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eubank Asphalt Paving & Sealing, LLC | 2. Parchman Construction Company, Inc. | 3. Civil Constructors, LLC | 4. Cleary Construction, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $130,000 | $137,445 | $79,730 | $145,000 |
| 2 | Trainee (109-10.01) | HR | 1,680 | $0.80 | $0.80 | $0.80 | $0.80 |
| 3 | Clearing and grubbing (201-01) | LS | 1 | $60,000 | $23,000 | $88,250 | $130,000 |
| 4 | Removal of structures and obstructions (202-01) | LS | 1 | $2,500.00 | $37,950 | $57,890 | $110,000 |
| 5 | Road & drainage excavation (unclassified) (203-01) | CY | 12,215 | $32.50 | $20.11 | $43.30 | $47.00 |
| 6 | Borrow excavation (graded solid rock) (203-02.01) | TON | 391 | $42.00 | $38.64 | $40.00 | $53.00 |
| 7 | Borrow excavation (unclassified) (203-03) | CY | 9,597 | $32.50 | $37.70 | $28.50 | $47.00 |
| 8 | Placing and spreading topsoil (203-04) | CY | 1,007 | $27.00 | $26.82 | $24.70 | $35.00 |
| 9 | Water (203-06) | MG | 56 | $50.00 | $12.65 | $41.00 | $135.00 |
| 10 | Furnishing & spreading topsoil (203-07) | CY | 1,680 | $42.00 | $63.24 | $45.00 | $53.00 |
| 11 | Flowable fill (general) (204-06.01) | CY | 530 | $400.00 | $206.91 | $240.00 | $289.00 |
| 12 | Foundation fill material (204-08) | CY | 17 | $125.00 | $143.75 | $191.00 | $207.00 |
| 13 | Protected area marker (white with decal) (209-03.99) | EACH | 2 | $100.00 | $115.00 | $186.00 | $365.00 |
| 14 | Sediment removal (209-05) | CY | 855 | $25.00 | $23.13 | $38.00 | $40.00 |
| 15 | Temporary silt fence (with backing) (209-08.02) | LF | 1,000 | $6.10 | $5.51 | $5.90 | $6.40 |
| 16 | Rock check dam (209-08.07) | EACH | 36 | $700.00 | $690.00 | $676.00 | $1,200.00 |
| 17 | Enhanced rock check dam (209-08.08) | EACH | 31 | $900.00 | $690.00 | $676.00 | $1,340.00 |
| 18 | Filter sock check dam (209-08.09) | EACH | 52 | $420.00 | $194.25 | $208.00 | $365.00 |
| 19 | Sandbags (209-09.01) | BAG | 1,450 | $5.00 | $6.30 | $7.70 | $6.30 |
| 20 | Sediment filter bag(15' X 10') (209-09.04) | EACH | 2 | $500.00 | $184.38 | $754.00 | $183.00 |
| 21 | Curb inlet protection (type 4) (209-09.43) | EACH | 81 | $40.00 | $136.50 | $146.00 | $183.00 |
| 22 | Polyethylene sheeting (6 mil. minimum) (209-20.03) | SY | 72 | $10.00 | $3.45 | $14.50 | $7.00 |
| 23 | Catch basin protection (type D) (209-40.33) | EACH | 24 | $40.00 | $194.25 | $208.00 | $305.00 |
| 24 | Catch basin filter assembly(type 1) (209-40.41) | EACH | 18 | $40.00 | $577.50 | $619.00 | $730.00 |
| 25 | Catch basin filter assembly(type 2) (209-40.42) | EACH | 17 | $40.00 | $577.50 | $619.00 | $1,220.00 |
| 26 | Catch basin filter assembly(type 5) (209-40.45) | EACH | 7 | $40.00 | $1,155.00 | $1,240.00 | $1,220.00 |
| 27 | Catch basin filter assembly(type 7) (209-40.47) | EACH | 3 | $40.00 | $577.50 | $619.00 | $730.00 |
| 28 | Catch basin filter assembly(type 8) (209-40.48) | EACH | 1 | $40.00 | $1,155.00 | $1,240.00 | $2,450.00 |
| 29 | Temporary diversion channel (209-65.03) | LF | 124 | $200.00 | $172.50 | $46.00 | $22.50 |
| 30 | Mineral aggregate, type A base, grading D (303-01) | TON | 6,907 | $35.00 | $34.50 | $43.50 | $41.00 |
| 31 | Granular backfill (roadway) (303-01.01) | TON | 61 | $100.00 | $115.00 | $106.00 | $41.00 |
| 32 | Mineral aggregate (size 57) (303-10.01) | TON | 114 | $50.00 | $56.31 | $67.50 | $61.00 |
| 33 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 155 | $165.00 | $157.50 | $172.00 | $350.00 |
| 34 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 228 | $185.00 | $159.60 | $185.00 | $460.00 |
| 35 | Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21) | TON | 300 | $165.00 | $162.75 | $173.00 | $350.00 |
| 36 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01) | TON | 324 | $165.00 | $163.80 | $171.00 | $350.00 |
| 37 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08) | TON | 212 | $185.00 | $165.90 | $200.00 | $350.00 |
| 38 | Asphalt conc mix (PG76-22)(BPMB-HM) GR CS (307-03.10) | TON | 75 | $200.00 | $225.75 | $219.00 | $460.00 |
| 39 | Bituminous material for prime coat (PC) (402-01) | TON | 5 | $800.00 | $420.00 | $1,390.00 | $1,700.00 |
| 40 | Aggregate for cover material (PC) (402-02) | TON | 16 | $65.00 | $26.25 | $68.00 | $97.50 |
| 41 | Bituminous material for tack coat (TC) (403-01) | TON | 11 | $470.00 | $1,260.00 | $1,080.00 | $1,700.00 |
| 42 | Saw cutting asphalt pavement (407-20.05) | LF | 162 | $10.00 | $5.75 | $5.80 | $12.00 |
| 43 | Acs mix(PG64-22) grading D (411-01.10) | TON | 448 | $250.00 | $143.85 | $213.00 | $465.00 |
| 44 | Acs mix(PG70-22) grading D (411-02.10) | TON | 555 | $195.00 | $145.95 | $204.00 | $365.00 |
| 45 | Cold planing bituminous pavement (415-01.01) | TON | 300 | $40.00 | $75.35 | $72.00 | $85.00 |
| 46 | Class A concrete (roadway) (604-01.01) | CY | 55 | $2,600.00 | $2,860.00 | $1,520.00 | $1,650.00 |
| 47 | Steel bar reinforcement (roadway) (604-01.02) | LB | 9,436 | $2.00 | $2.20 | $2.10 | $2.25 |
| 48 | Box tube safety rail (604-01.20) | LF | 130 | $250.00 | $495.00 | $185.00 | $214.00 |
| 49 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 7,450 | $90.00 | $111.90 | $102.61 | $174.00 |
| 50 | 24" concrete pipe culvert (class III) (607-05.02) | LF | 685 | $100.00 | $123.38 | $158.00 | $192.00 |
| 51 | 30" concrete pipe culvert (class III) (607-06.02) | LF | 287 | $250.00 | $158.31 | $212.00 | $215.00 |
| 52 | 36" concrete pipe culvert (class III) (607-07.02) | LF | 11 | $500.00 | $188.00 | $686.00 | $300.00 |
| 53 | 42" concrete pipe culvert (class III) (607-08.02) | LF | 12 | $500.00 | $241.79 | $819.00 | $368.00 |
| 54 | 30" corrugated metal pipe culvert (607-37.04) | LF | 3 | $500.00 | $366.58 | $1,050.00 | $190.00 |
| 55 | 18" pipe culvert (side drain) (607-39.02) | LF | 92 | $100.00 | $117.65 | $137.00 | $128.00 |
| 56 | 24" pipe culvert (side drain) (607-39.03) | LF | 36 | $110.00 | $138.63 | $184.00 | $140.00 |
| 57 | Manholes, > 4' - 8' depth (611-01.02) | EACH | 4 | $5,000.00 | $6,393.12 | $10,870 | $7,000.00 |
| 58 | Manholes, > 8' - 12' depth (611-01.03) | EACH | 5 | $6,500.00 | $9,078.36 | $13,830 | $8,500.00 |
| 59 | Junction box, type 2 (611-02.11) | EACH | 2 | $5,500.00 | $5,211.12 | $8,540.00 | $6,200.00 |
| 60 | Trench drains (611-05.01) | LF | 68 | $800.00 | $768.24 | $644.00 | $940.00 |
| 61 | Curb cut trench grate (611-05.99) | EACH | 8 | $1,250.00 | $7,529.18 | $6,400.00 | $7,300.00 |
| 62 | 18IN endwall (side drain) (611-07.31) | EACH | 7 | $3,200.00 | $4,510.55 | $4,200.00 | $5,350.00 |
| 63 | 24IN endwall (side drain) (611-07.32) | EACH | 1 | $4,800.00 | $5,823.16 | $5,857.85 | $6,800.00 |
| 64 | 30IN endwall (side drain) (611-07.33) | EACH | 1 | $6,200.00 | $9,296.39 | $8,350.00 | $8,950.00 |
| 65 | 18IN endwall (cross drain) 3:1 (611-07.54) | EACH | 7 | $3,000.00 | $2,068.34 | $2,970.00 | $2,750.00 |
| 66 | 24IN endwall (cross drain) 3:1 (611-07.57) | EACH | 1 | $3,500.00 | $3,027.56 | $3,920.00 | $3,750.00 |
| 67 | 24IN endwall (cross drain) 4:1 (611-07.58) | EACH | 1 | $3,800.00 | $3,336.78 | $4,570.00 | $4,075.00 |
| 68 | 30IN endwall (cross drain) 3:1 (611-07.60) | EACH | 1 | $4,500.00 | $3,799.84 | $5,650.00 | $4,900.00 |
| 69 | 42IN endwall (cross drain) 3:1 (611-07.66) | EACH | 1 | $6,500.00 | $8,674.02 | $8,500.00 | $8,000.00 |
| 70 | Capping existing catchbasin (611-09.03) | EACH | 1 | $2,500.00 | $2,300.00 | $2,790.00 | $1,930.00 |
| 71 | Catch basins, type 12, 0' - 4' depth (611-12.01) | EACH | 21 | $3,000.00 | $4,672.88 | $7,920.00 | $5,380.00 |
| 72 | Catch basins, type 12, > 4' - 8' depth (611-12.02) | EACH | 36 | $3,500.00 | $5,762.03 | $8,950.00 | $6,725.00 |
| 73 | Catch basins, type 12, > 8' - 12' depth (611-12.03) | EACH | 1 | $12,000 | $11,339 | $14,470 | $11,500 |
| 74 | Catch basins, type 14, 0' - 4' depth (611-14.01) | EACH | 1 | $5,500.00 | $7,363.04 | $12,510 | $8,500.00 |
| 75 | Catch basins, type 14, > 4' - 8' depth (611-14.02) | EACH | 16 | $6,000.00 | $8,220.67 | $14,130 | $9,000.00 |
| 76 | Catch basins, type 42, 0' - 4' depth (611-42.01) | EACH | 17 | $4,750.00 | $5,751.59 | $6,990.00 | $6,900.00 |
| 77 | Catch basins, type 42, > 4' - 8' depth (611-42.02) | EACH | 5 | $4,700.00 | $7,050.35 | $9,100.00 | $7,700.00 |
| 78 | Catch basins, type 43, > 8' - 12' depth (611-43.03) | EACH | 1 | $24,000 | $13,021 | $17,620 | $12,200 |
| 79 | Catch basins, type 44, > 4' - 8' depth (611-44.02) | EACH | 1 | $38,000 | $42,174 | $31,540 | $29,700 |
| 80 | 36" temporary drainage pipe (621-03.05) | LF | 266 | $75.00 | $108.35 | $131.00 | $235.00 |
| 81 | Concrete sidewalk (4 ") (701-01.01) | SF | 58,848 | $6.60 | $9.63 | $7.30 | $7.95 |
| 82 | Concrete driveway (701-02) | SF | 6,745 | $9.35 | $13.15 | $13.50 | $14.60 |
| 83 | Concrete curb ramp (701-02.03) | SF | 1,959 | $19.65 | $34.10 | $11.30 | $12.20 |
| 84 | Concrete combined curb & gutter (702-03) | CY | 920 | $465.00 | $540.65 | $487.00 | $527.00 |
| 85 | High-visibility construction fence (707-08.11) | LF | 1,045 | $4.00 | $2.10 | $2.25 | $2.15 |
| 86 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 10 | $200.00 | $401.09 | $675.00 | $600.00 |
| 87 | Machined rip-rap (class A-3) (709-05.05) | TON | 651 | $50.00 | $59.53 | $62.00 | $67.00 |
| 88 | Machined rip-rap (class A-1) (709-05.06) | TON | 384 | $75.00 | $59.53 | $69.00 | $67.00 |
| 89 | Machined rip-rap (class B) (709-05.08) | TON | 61 | $90.00 | $60.79 | $85.50 | $67.00 |
| 90 | Machined rip-rap (class C) (709-05.09) | TON | 94 | $90.00 | $60.79 | $78.50 | $67.00 |
| 91 | Aggregate underdrains (with pipe) (710-02) | LF | 14,580 | $11.10 | $13.48 | $13.80 | $15.50 |
| 92 | Lateral underdrain (710-05) | LF | 675 | $10.60 | $12.65 | $13.00 | $14.50 |
| 93 | Lateral underdrain endwall (4:1) (710-06.13) | EACH | 7 | $1,232.00 | $1,650.00 | $1,690.00 | $1,830.00 |
| 94 | Traffic control (712-01) | LS | 1 | $76,000 | $135,410 | $216,720 | $320,000 |
| 95 | Interconnected portable barrier rail (712-02.02) | LF | 2,490 | $50.00 | $68.59 | $76.50 | $45.00 |
| 96 | Remove and relocate portable barrier rail (712-02.36) | LF | 2,300 | $45.00 | $16.50 | $24.10 | $18.00 |
| 97 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 14 | $4,000.00 | $7,700.00 | $7,550.00 | $11,000 |
| 98 | Flexible drums (channelizing) (712-04.01) | EACH | 1,050 | $35.00 | $44.00 | $40.00 | $48.00 |
| 99 | Barrier rail delineator (712-04.50) | EACH | 68 | $50.00 | $11.00 | $13.00 | $12.00 |
| 100 | Warning lights (type A) (712-05.01) | EACH | 16 | $5.00 | $22.00 | $35.00 | $36.00 |
| 101 | Warning lights (type C) (712-05.03) | EACH | 39 | $5.00 | $22.00 | $36.00 | $36.00 |
| 102 | Signs (construction) (712-06) | SF | 977 | $9.00 | $8.36 | $8.10 | $18.00 |
| 103 | Temporary barricades (type III) (712-07.03) | LF | 24 | $50.00 | $30.80 | $15.80 | $18.00 |
| 104 | Arrow board (type C) (712-08.03) | EACH | 4 | $600.00 | $1,375.00 | $1,750.00 | $1,830.00 |
| 105 | Speed feedback sign assembly (712-08.08) | EACH | 2 | $1,200.00 | $6,490.00 | $6,980.00 | $7,500.00 |
| 106 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 24,500 | $5.00 | $4.46 | $4.80 | $5.50 |
| 107 | Removable pavement marking (stop line) (712-09.04) | LF | 96 | $50.00 | $31.50 | $34.00 | $12.80 |
| 108 | Removable pavement marking (4" line) (712-09.09) | LF | 23,500 | $4.00 | $3.41 | $3.65 | $3.05 |
| 109 | Removable black-out tape (6") (712-09.30) | LF | 35,000 | $4.00 | $3.94 | $4.20 | $3.65 |
| 110 | Perforated/knockout square tube post (713-11.02) | LB | 1,171 | $5.00 | $4.32 | $4.10 | $9.00 |
| 111 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 181 | $17.00 | $15.60 | $14.80 | $19.75 |
| 112 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 85 | $20.00 | $17.45 | $16.50 | $20.75 |
| 113 | Street name sign (rigid 0.100IN thick (713-14.21) | SF | 105 | $20.00 | $42.00 | $68.50 | $34.15 |
| 114 | Removal of signs, posts and footings (713-15) | LS | 1 | $500.00 | $2,444.20 | $2,320.00 | $670.00 |
| 115 | Suspended flat sheet aluminum sign (0.080" thick) (713-15.07) | EACH | 3 | $750.00 | $787.50 | $737.00 | $925.00 |
| 116 | Changeable message sign unit (713-16.01) | EACH | 4 | $5,000.00 | $6,930.00 | $9,460.00 | $9,150.00 |
| 117 | Relocate sign (713-16.41) | LS | 1 | $500.00 | $2,915.00 | $2,760.00 | $975.00 |
| 118 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 108 | $50.00 | $52.50 | $56.50 | $42.00 |
| 119 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 18 | $50.00 | $52.50 | $56.50 | $42.00 |
| 120 | Removal of snowplowable reflective marker (716-01.30) | EACH | 48 | $30.00 | $21.00 | $22.50 | $22.00 |
| 121 | Plastic pavement marking (cross-walk) (716-02.03) | LF | 485 | $12.00 | $15.75 | $16.90 | $37.00 |
| 122 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 537 | $30.00 | $31.50 | $34.00 | $48.00 |
| 123 | Plastic pavement marking (stop line) (716-02.05) | LF | 204 | $25.00 | $26.25 | $28.20 | $24.00 |
| 124 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 5 | $250.00 | $236.25 | $253.00 | $245.00 |
| 125 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 360 | $3.00 | $4.20 | $4.50 | $3.05 |
| 126 | Plastic pavement marking (longitudinal cross-walk) (716-02.09) | LF | 120 | $60.00 | $47.25 | $50.50 | $55.00 |
| 127 | Plastic pavement marking (8IN line) (716-02.12) | LM | 0.06 | $18,000 | $26,250 | $28,160 | $13,400 |
| 128 | Plastic pavement marking (yield line) (716-04.12) | SF | 48 | $40.00 | $42.00 | $45.00 | $60.00 |
| 129 | Painted pavement marking (stop line) (716-05.05) | LF | 12 | $15.00 | $15.75 | $16.90 | $12.20 |
| 130 | Painted pavement marking (6" line) (716-05.20) | LM | 1.60 | $1,600.00 | $2,625.00 | $2,820.00 | $1,585.00 |
| 131 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 4.30 | $8,500.00 | $8,925.00 | $9,570.00 | $10,975 |
| 132 | Mobilization (717-01) | LS | 1 | $425,000 | $193,074 | $237,170 | $475,000 |
| 133 | Signal head assembly (130 with backplate) (730-02.09) | EACH | 4 | $1,450.00 | $1,522.50 | $1,730.00 | $1,785.00 |
| 134 | Signal head assembly (140 A1 with backplate) (730-02.14) | EACH | 2 | $1,625.00 | $1,706.25 | $2,090.00 | $2,000.00 |
| 135 | Signal head assembly (150 A2H with backplate) (730-02.17) | EACH | 2 | $2,100.00 | $2,205.00 | $690.00 | $2,600.00 |
| 136 | Install pull box (type B) (730-03.21) | EACH | 6 | $1,000.00 | $1,050.00 | $1,700.00 | $1,200.00 |
| 137 | Electrical service connection (730-05.01) | EACH | 1 | $8,000.00 | $8,400.00 | $22,190 | $9,850.00 |
| 138 | Signal cable - 5 conductor (730-08.02) | LF | 1,652 | $2.25 | $2.36 | $2.25 | $2.75 |
| 139 | Signal cable - 7 conductor (730-08.03) | LF | 619 | $2.50 | $2.63 | $2.70 | $3.10 |
| 140 | Conduit 2" diameter (PVC schedule 40) (730-12.02) | LF | 114 | $25.00 | $26.25 | $29.30 | $30.80 |
| 141 | Conduit 3" diameter (PVC schedule 40) (730-12.03) | LF | 112 | $28.00 | $29.40 | $31.50 | $34.50 |
| 142 | Conduit 2" diameter (directional bore) (730-12.23) | LF | 164 | $130.00 | $136.50 | $52.00 | $160.00 |
| 143 | Conduit 3" diameter (directional bore) (730-12.24) | LF | 122 | $140.00 | $147.00 | $58.50 | $172.00 |
| 144 | Vehicle detector (radar - stop line) (730-13.12) | EACH | 4 | $12,000 | $12,600 | $10,150 | $14,800 |
| 145 | Vehicle detector (radar - advance) (730-13.13) | EACH | 2 | $12,000 | $12,600 | $12,560 | $14,800 |
| 146 | Cabinet (school zone flasher) (730-15.07) | EACH | 1 | $1,500.00 | $1,575.00 | $3,380.00 | $1,850.00 |
| 147 | Cabinet (atc) (730-15.08) | EACH | 1 | $34,500 | $36,225 | $38,630 | $42,500 |
| 148 | Controller (atc) (730-16.04) | EACH | 1 | $6,000.00 | $6,300.00 | $6,760.00 | $7,400.00 |
| 149 | Controller (school zone flasher) (730-16.14) | EACH | 1 | $1,000.00 | $1,050.00 | $597.00 | $1,230.00 |
| 150 | Pedestal pole (type A) (730-23.28) | EACH | 2 | $2,500.00 | $2,625.00 | $2,690.00 | $3,080.00 |
| 151 | Cantilever signal support (1 arm @ 30 W/ luminaire) (730-24.96) | EACH | 1 | $34,500 | $36,225 | $29,510 | $42,500 |
| 152 | Cantilever signal support (1 arm @ 40' W/ luminaire) (730-24.97) | EACH | 1 | $35,750 | $37,538 | $32,830 | $44,000 |
| 153 | Cantilever signal support (2 @ 45' & 60' W/ luminaire) (730-24.98) | EACH | 1 | $53,000 | $56,560 | $55,810 | $65,275 |
| 154 | Countdown pedestrian signal (730-26.05) | EACH | 3 | $1,000.00 | $1,050.00 | $1,440.00 | $1,230.00 |
| 155 | Pedestrian pushbutton post (730-26.06) | EACH | 3 | $2,200.00 | $2,310.00 | $2,240.00 | $2,710.00 |
| 156 | Pedestrian pushbutton with 15IN sign (730-26.09) | EACH | 3 | $800.00 | $840.00 | $672.00 | $985.00 |
| 157 | Countdown ped SGNL head W/audible pushbutton & 15IN sign (730-26.11) | EACH | 3 | $1,800.00 | $1,890.00 | $2,150.00 | $2,215.00 |
| 158 | Rectangular rapid flashing beacon assembly (solar powered) (730-50.20) | EACH | 4 | $12,000 | $12,600 | $13,290 | $14,800 |
| 159 | School speed limit flashing assembly (solar powered) (730-50.30) | EACH | 1 | $29,000 | $30,450 | $31,420 | $35,700 |
| 160 | Geotextile (type III)(erosion control) (740-10.03) | SY | 2,618 | $3.30 | $3.26 | $3.50 | $3.30 |
| 161 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 174 | $3.65 | $7.32 | $9.70 | $3.00 |
| 162 | Temporary sediment tube 12IN (740-11.02) | LF | 12,490 | $4.40 | $2.89 | $3.10 | $4.25 |
| 163 | Temporary sediment tube 20IN (740-11.04) | LF | 300 | $8.00 | $3.94 | $4.80 | $9.15 |
| 164 | 6IN dia PVC pipe (790-42.11) | LF | 24 | $35.00 | $57.60 | $172.00 | $104.00 |
| 165 | Temporary seeding (with mulch) (801-01.07) | UNIT | 344 | $50.00 | $55.00 | $45.00 | $45.00 |
| 166 | Special wetland seed mixture (801-01.36) | UNIT | 1 | $500.00 | $275.00 | $216.87 | $610.00 |
| 167 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 2 | $400.00 | $165.00 | $67.50 | $305.00 |
| 168 | Seeding (without mulch) (801-02) | UNIT | 6 | $50.00 | $55.00 | $34.00 | $53.00 |
| 169 | Water (seeding & sodding) (801-03) | MG | 196 | $75.00 | $55.00 | $56.50 | $245.00 |
| 170 | Sodding (new sod) (803-01) | SY | 26,680 | $5.50 | $5.50 | $5.60 | $9.20 |
| 171 | Turf reinforcement mat (class I) (805-01.01) | SY | 484 | $6.00 | $6.60 | $3.40 | $7.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of May 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.