TDOT contract CNZ164 bid tabulation

The construction of pedestrian facilities on s.r. 100 from the fairview community center (l.m. 3.08) to bowie lake road (l.m. 5.19), including intersection improvements at cumberland drive. Let by Tennessee DOT on May 9, 2025, Williamson County. 4 bids received; low bid $6,987,981 by Eubank Asphalt Paving & Sealing, LLC.

Owner
Tennessee DOT
Letting
09 MAY 2025
Pay items
171
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Eubank Asphalt Paving & Sealing, LLC$6,987,981Low
2Parchman Construction Company, Inc.$7,428,118+6.0%
3Civil Constructors, LLC$7,992,414+14%
4Cleary Construction, Inc.$9,940,621+42%
TDOT contract CNZ164: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Eubank Asphalt Paving & Sealing, LLC2. Parchman Construction Company, Inc.3. Civil Constructors, LLC4. Cleary Construction, Inc.
1Construction stakes, lines and grades (105-01)LS1$130,000$137,445$79,730$145,000
2Trainee (109-10.01)HR1,680$0.80$0.80$0.80$0.80
3Clearing and grubbing (201-01)LS1$60,000$23,000$88,250$130,000
4Removal of structures and obstructions (202-01)LS1$2,500.00$37,950$57,890$110,000
5Road & drainage excavation (unclassified) (203-01)CY12,215$32.50$20.11$43.30$47.00
6Borrow excavation (graded solid rock) (203-02.01)TON391$42.00$38.64$40.00$53.00
7Borrow excavation (unclassified) (203-03)CY9,597$32.50$37.70$28.50$47.00
8Placing and spreading topsoil (203-04)CY1,007$27.00$26.82$24.70$35.00
9Water (203-06)MG56$50.00$12.65$41.00$135.00
10Furnishing & spreading topsoil (203-07)CY1,680$42.00$63.24$45.00$53.00
11Flowable fill (general) (204-06.01)CY530$400.00$206.91$240.00$289.00
12Foundation fill material (204-08)CY17$125.00$143.75$191.00$207.00
13Protected area marker (white with decal) (209-03.99)EACH2$100.00$115.00$186.00$365.00
14Sediment removal (209-05)CY855$25.00$23.13$38.00$40.00
15Temporary silt fence (with backing) (209-08.02)LF1,000$6.10$5.51$5.90$6.40
16Rock check dam (209-08.07)EACH36$700.00$690.00$676.00$1,200.00
17Enhanced rock check dam (209-08.08)EACH31$900.00$690.00$676.00$1,340.00
18Filter sock check dam (209-08.09)EACH52$420.00$194.25$208.00$365.00
19Sandbags (209-09.01)BAG1,450$5.00$6.30$7.70$6.30
20Sediment filter bag(15' X 10') (209-09.04)EACH2$500.00$184.38$754.00$183.00
21Curb inlet protection (type 4) (209-09.43)EACH81$40.00$136.50$146.00$183.00
22Polyethylene sheeting (6 mil. minimum) (209-20.03)SY72$10.00$3.45$14.50$7.00
23Catch basin protection (type D) (209-40.33)EACH24$40.00$194.25$208.00$305.00
24Catch basin filter assembly(type 1) (209-40.41)EACH18$40.00$577.50$619.00$730.00
25Catch basin filter assembly(type 2) (209-40.42)EACH17$40.00$577.50$619.00$1,220.00
26Catch basin filter assembly(type 5) (209-40.45)EACH7$40.00$1,155.00$1,240.00$1,220.00
27Catch basin filter assembly(type 7) (209-40.47)EACH3$40.00$577.50$619.00$730.00
28Catch basin filter assembly(type 8) (209-40.48)EACH1$40.00$1,155.00$1,240.00$2,450.00
29Temporary diversion channel (209-65.03)LF124$200.00$172.50$46.00$22.50
30Mineral aggregate, type A base, grading D (303-01)TON6,907$35.00$34.50$43.50$41.00
31Granular backfill (roadway) (303-01.01)TON61$100.00$115.00$106.00$41.00
32Mineral aggregate (size 57) (303-10.01)TON114$50.00$56.31$67.50$61.00
33Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON155$165.00$157.50$172.00$350.00
34Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON228$185.00$159.60$185.00$460.00
35Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21)TON300$165.00$162.75$173.00$350.00
36Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01)TON324$165.00$163.80$171.00$350.00
37Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08)TON212$185.00$165.90$200.00$350.00
38Asphalt conc mix (PG76-22)(BPMB-HM) GR CS (307-03.10)TON75$200.00$225.75$219.00$460.00
39Bituminous material for prime coat (PC) (402-01)TON5$800.00$420.00$1,390.00$1,700.00
40Aggregate for cover material (PC) (402-02)TON16$65.00$26.25$68.00$97.50
41Bituminous material for tack coat (TC) (403-01)TON11$470.00$1,260.00$1,080.00$1,700.00
42Saw cutting asphalt pavement (407-20.05)LF162$10.00$5.75$5.80$12.00
43Acs mix(PG64-22) grading D (411-01.10)TON448$250.00$143.85$213.00$465.00
44Acs mix(PG70-22) grading D (411-02.10)TON555$195.00$145.95$204.00$365.00
45Cold planing bituminous pavement (415-01.01)TON300$40.00$75.35$72.00$85.00
46Class A concrete (roadway) (604-01.01)CY55$2,600.00$2,860.00$1,520.00$1,650.00
47Steel bar reinforcement (roadway) (604-01.02)LB9,436$2.00$2.20$2.10$2.25
48Box tube safety rail (604-01.20)LF130$250.00$495.00$185.00$214.00
4918" concrete pipe culvert (class III) (607-03.02)LF7,450$90.00$111.90$102.61$174.00
5024" concrete pipe culvert (class III) (607-05.02)LF685$100.00$123.38$158.00$192.00
5130" concrete pipe culvert (class III) (607-06.02)LF287$250.00$158.31$212.00$215.00
5236" concrete pipe culvert (class III) (607-07.02)LF11$500.00$188.00$686.00$300.00
5342" concrete pipe culvert (class III) (607-08.02)LF12$500.00$241.79$819.00$368.00
5430" corrugated metal pipe culvert (607-37.04)LF3$500.00$366.58$1,050.00$190.00
5518" pipe culvert (side drain) (607-39.02)LF92$100.00$117.65$137.00$128.00
5624" pipe culvert (side drain) (607-39.03)LF36$110.00$138.63$184.00$140.00
57Manholes, > 4' - 8' depth (611-01.02)EACH4$5,000.00$6,393.12$10,870$7,000.00
58Manholes, > 8' - 12' depth (611-01.03)EACH5$6,500.00$9,078.36$13,830$8,500.00
59Junction box, type 2 (611-02.11)EACH2$5,500.00$5,211.12$8,540.00$6,200.00
60Trench drains (611-05.01)LF68$800.00$768.24$644.00$940.00
61Curb cut trench grate (611-05.99)EACH8$1,250.00$7,529.18$6,400.00$7,300.00
6218IN endwall (side drain) (611-07.31)EACH7$3,200.00$4,510.55$4,200.00$5,350.00
6324IN endwall (side drain) (611-07.32)EACH1$4,800.00$5,823.16$5,857.85$6,800.00
6430IN endwall (side drain) (611-07.33)EACH1$6,200.00$9,296.39$8,350.00$8,950.00
6518IN endwall (cross drain) 3:1 (611-07.54)EACH7$3,000.00$2,068.34$2,970.00$2,750.00
6624IN endwall (cross drain) 3:1 (611-07.57)EACH1$3,500.00$3,027.56$3,920.00$3,750.00
6724IN endwall (cross drain) 4:1 (611-07.58)EACH1$3,800.00$3,336.78$4,570.00$4,075.00
6830IN endwall (cross drain) 3:1 (611-07.60)EACH1$4,500.00$3,799.84$5,650.00$4,900.00
6942IN endwall (cross drain) 3:1 (611-07.66)EACH1$6,500.00$8,674.02$8,500.00$8,000.00
70Capping existing catchbasin (611-09.03)EACH1$2,500.00$2,300.00$2,790.00$1,930.00
71Catch basins, type 12, 0' - 4' depth (611-12.01)EACH21$3,000.00$4,672.88$7,920.00$5,380.00
72Catch basins, type 12, > 4' - 8' depth (611-12.02)EACH36$3,500.00$5,762.03$8,950.00$6,725.00
73Catch basins, type 12, > 8' - 12' depth (611-12.03)EACH1$12,000$11,339$14,470$11,500
74Catch basins, type 14, 0' - 4' depth (611-14.01)EACH1$5,500.00$7,363.04$12,510$8,500.00
75Catch basins, type 14, > 4' - 8' depth (611-14.02)EACH16$6,000.00$8,220.67$14,130$9,000.00
76Catch basins, type 42, 0' - 4' depth (611-42.01)EACH17$4,750.00$5,751.59$6,990.00$6,900.00
77Catch basins, type 42, > 4' - 8' depth (611-42.02)EACH5$4,700.00$7,050.35$9,100.00$7,700.00
78Catch basins, type 43, > 8' - 12' depth (611-43.03)EACH1$24,000$13,021$17,620$12,200
79Catch basins, type 44, > 4' - 8' depth (611-44.02)EACH1$38,000$42,174$31,540$29,700
8036" temporary drainage pipe (621-03.05)LF266$75.00$108.35$131.00$235.00
81Concrete sidewalk (4 ") (701-01.01)SF58,848$6.60$9.63$7.30$7.95
82Concrete driveway (701-02)SF6,745$9.35$13.15$13.50$14.60
83Concrete curb ramp (701-02.03)SF1,959$19.65$34.10$11.30$12.20
84Concrete combined curb & gutter (702-03)CY920$465.00$540.65$487.00$527.00
85High-visibility construction fence (707-08.11)LF1,045$4.00$2.10$2.25$2.15
86Markers (concrete R.O.W. posts) (708-02.01)EACH10$200.00$401.09$675.00$600.00
87Machined rip-rap (class A-3) (709-05.05)TON651$50.00$59.53$62.00$67.00
88Machined rip-rap (class A-1) (709-05.06)TON384$75.00$59.53$69.00$67.00
89Machined rip-rap (class B) (709-05.08)TON61$90.00$60.79$85.50$67.00
90Machined rip-rap (class C) (709-05.09)TON94$90.00$60.79$78.50$67.00
91Aggregate underdrains (with pipe) (710-02)LF14,580$11.10$13.48$13.80$15.50
92Lateral underdrain (710-05)LF675$10.60$12.65$13.00$14.50
93Lateral underdrain endwall (4:1) (710-06.13)EACH7$1,232.00$1,650.00$1,690.00$1,830.00
94Traffic control (712-01)LS1$76,000$135,410$216,720$320,000
95Interconnected portable barrier rail (712-02.02)LF2,490$50.00$68.59$76.50$45.00
96Remove and relocate portable barrier rail (712-02.36)LF2,300$45.00$16.50$24.10$18.00
97Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH14$4,000.00$7,700.00$7,550.00$11,000
98Flexible drums (channelizing) (712-04.01)EACH1,050$35.00$44.00$40.00$48.00
99Barrier rail delineator (712-04.50)EACH68$50.00$11.00$13.00$12.00
100Warning lights (type A) (712-05.01)EACH16$5.00$22.00$35.00$36.00
101Warning lights (type C) (712-05.03)EACH39$5.00$22.00$36.00$36.00
102Signs (construction) (712-06)SF977$9.00$8.36$8.10$18.00
103Temporary barricades (type III) (712-07.03)LF24$50.00$30.80$15.80$18.00
104Arrow board (type C) (712-08.03)EACH4$600.00$1,375.00$1,750.00$1,830.00
105Speed feedback sign assembly (712-08.08)EACH2$1,200.00$6,490.00$6,980.00$7,500.00
106Removable pavement marking (8" barrier line) (712-09.02)LF24,500$5.00$4.46$4.80$5.50
107Removable pavement marking (stop line) (712-09.04)LF96$50.00$31.50$34.00$12.80
108Removable pavement marking (4" line) (712-09.09)LF23,500$4.00$3.41$3.65$3.05
109Removable black-out tape (6") (712-09.30)LF35,000$4.00$3.94$4.20$3.65
110Perforated/knockout square tube post (713-11.02)LB1,171$5.00$4.32$4.10$9.00
111Flat sheet aluminum signs (0.080" thick) (713-13.02)SF181$17.00$15.60$14.80$19.75
112Flat sheet aluminum signs (0.100" thick) (713-13.03)SF85$20.00$17.45$16.50$20.75
113Street name sign (rigid 0.100IN thick (713-14.21)SF105$20.00$42.00$68.50$34.15
114Removal of signs, posts and footings (713-15)LS1$500.00$2,444.20$2,320.00$670.00
115Suspended flat sheet aluminum sign (0.080" thick) (713-15.07)EACH3$750.00$787.50$737.00$925.00
116Changeable message sign unit (713-16.01)EACH4$5,000.00$6,930.00$9,460.00$9,150.00
117Relocate sign (713-16.41)LS1$500.00$2,915.00$2,760.00$975.00
118Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH108$50.00$52.50$56.50$42.00
119Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22)EACH18$50.00$52.50$56.50$42.00
120Removal of snowplowable reflective marker (716-01.30)EACH48$30.00$21.00$22.50$22.00
121Plastic pavement marking (cross-walk) (716-02.03)LF485$12.00$15.75$16.90$37.00
122Plastic pavement marking(channelization striping) (716-02.04)SY537$30.00$31.50$34.00$48.00
123Plastic pavement marking (stop line) (716-02.05)LF204$25.00$26.25$28.20$24.00
124Plastic pavement marking (turn lane arrow) (716-02.06)EACH5$250.00$236.25$253.00$245.00
125Plastic pavement marking (8" dotted line) (716-02.08)LF360$3.00$4.20$4.50$3.05
126Plastic pavement marking (longitudinal cross-walk) (716-02.09)LF120$60.00$47.25$50.50$55.00
127Plastic pavement marking (8IN line) (716-02.12)LM0.06$18,000$26,250$28,160$13,400
128Plastic pavement marking (yield line) (716-04.12)SF48$40.00$42.00$45.00$60.00
129Painted pavement marking (stop line) (716-05.05)LF12$15.00$15.75$16.90$12.20
130Painted pavement marking (6" line) (716-05.20)LM1.60$1,600.00$2,625.00$2,820.00$1,585.00
131Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM4.30$8,500.00$8,925.00$9,570.00$10,975
132Mobilization (717-01)LS1$425,000$193,074$237,170$475,000
133Signal head assembly (130 with backplate) (730-02.09)EACH4$1,450.00$1,522.50$1,730.00$1,785.00
134Signal head assembly (140 A1 with backplate) (730-02.14)EACH2$1,625.00$1,706.25$2,090.00$2,000.00
135Signal head assembly (150 A2H with backplate) (730-02.17)EACH2$2,100.00$2,205.00$690.00$2,600.00
136Install pull box (type B) (730-03.21)EACH6$1,000.00$1,050.00$1,700.00$1,200.00
137Electrical service connection (730-05.01)EACH1$8,000.00$8,400.00$22,190$9,850.00
138Signal cable - 5 conductor (730-08.02)LF1,652$2.25$2.36$2.25$2.75
139Signal cable - 7 conductor (730-08.03)LF619$2.50$2.63$2.70$3.10
140Conduit 2" diameter (PVC schedule 40) (730-12.02)LF114$25.00$26.25$29.30$30.80
141Conduit 3" diameter (PVC schedule 40) (730-12.03)LF112$28.00$29.40$31.50$34.50
142Conduit 2" diameter (directional bore) (730-12.23)LF164$130.00$136.50$52.00$160.00
143Conduit 3" diameter (directional bore) (730-12.24)LF122$140.00$147.00$58.50$172.00
144Vehicle detector (radar - stop line) (730-13.12)EACH4$12,000$12,600$10,150$14,800
145Vehicle detector (radar - advance) (730-13.13)EACH2$12,000$12,600$12,560$14,800
146Cabinet (school zone flasher) (730-15.07)EACH1$1,500.00$1,575.00$3,380.00$1,850.00
147Cabinet (atc) (730-15.08)EACH1$34,500$36,225$38,630$42,500
148Controller (atc) (730-16.04)EACH1$6,000.00$6,300.00$6,760.00$7,400.00
149Controller (school zone flasher) (730-16.14)EACH1$1,000.00$1,050.00$597.00$1,230.00
150Pedestal pole (type A) (730-23.28)EACH2$2,500.00$2,625.00$2,690.00$3,080.00
151Cantilever signal support (1 arm @ 30 W/ luminaire) (730-24.96)EACH1$34,500$36,225$29,510$42,500
152Cantilever signal support (1 arm @ 40' W/ luminaire) (730-24.97)EACH1$35,750$37,538$32,830$44,000
153Cantilever signal support (2 @ 45' & 60' W/ luminaire) (730-24.98)EACH1$53,000$56,560$55,810$65,275
154Countdown pedestrian signal (730-26.05)EACH3$1,000.00$1,050.00$1,440.00$1,230.00
155Pedestrian pushbutton post (730-26.06)EACH3$2,200.00$2,310.00$2,240.00$2,710.00
156Pedestrian pushbutton with 15IN sign (730-26.09)EACH3$800.00$840.00$672.00$985.00
157Countdown ped SGNL head W/audible pushbutton & 15IN sign (730-26.11)EACH3$1,800.00$1,890.00$2,150.00$2,215.00
158Rectangular rapid flashing beacon assembly (solar powered) (730-50.20)EACH4$12,000$12,600$13,290$14,800
159School speed limit flashing assembly (solar powered) (730-50.30)EACH1$29,000$30,450$31,420$35,700
160Geotextile (type III)(erosion control) (740-10.03)SY2,618$3.30$3.26$3.50$3.30
161Geotextile (type IV)(stabilization) (740-10.04)SY174$3.65$7.32$9.70$3.00
162Temporary sediment tube 12IN (740-11.02)LF12,490$4.40$2.89$3.10$4.25
163Temporary sediment tube 20IN (740-11.04)LF300$8.00$3.94$4.80$9.15
1646IN dia PVC pipe (790-42.11)LF24$35.00$57.60$172.00$104.00
165Temporary seeding (with mulch) (801-01.07)UNIT344$50.00$55.00$45.00$45.00
166Special wetland seed mixture (801-01.36)UNIT1$500.00$275.00$216.87$610.00
167Natve seed MX final stablizatn of slopes (801-01.38)UNIT2$400.00$165.00$67.50$305.00
168Seeding (without mulch) (801-02)UNIT6$50.00$55.00$34.00$53.00
169Water (seeding & sodding) (801-03)MG196$75.00$55.00$56.50$245.00
170Sodding (new sod) (803-01)SY26,680$5.50$5.50$5.60$9.20
171Turf reinforcement mat (class I) (805-01.01)SY484$6.00$6.60$3.40$7.00
TDOT contract CNZ164: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of May 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy