TDOT contract CN263052 bid tabulation
The grading, drainage, and paving on a s.i.a. route (including u.s. 43/s.r. 6) serving project leeward. Let by Tennessee DOT on June 26, 2026, Maury County. 8 bids received; low bid $2,156,542 by Eubank Asphalt Paving & Sealing, LLC.
- Owner
- Tennessee DOT
- Letting
- 26 JUN 2026
- Pay items
- 131
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Eubank Asphalt Paving & Sealing, LLC | $2,156,542 | Low |
| 2 | Capital City Construction Services, LLC | $3,040,565 | +41% |
| 3 | Kenneth Rich Construction Company, Inc. | $3,066,779 | +42% |
| 4 | Civil Constructors, LLC | $3,131,531 | +45% |
| 5 | Rogers Group, Inc. | $3,173,876 | +47% |
| 6 | Dement Construction Group, LLC | $3,243,819 | +50% |
| 7 | Jones Bros. Contractors, LLC | $3,367,776 | +56% |
| 8 | Adams Contracting, LLC | $3,847,672 | +78% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eubank Asphalt Paving & Sealing, LLC | 2. Capital City Construction Services, LLC | 3. Kenneth Rich Construction Company, Inc. | 4. Civil Constructors, LLC | 5. Rogers Group, Inc. | 6. Dement Construction Group, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $25,000 | $15,000 | $60,000 | $28,470 | $20,500 | $42,150 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $28,500 | $20,000 | $104,513 | $32,995 | $32,000 | $396,000 |
| 3 | Road & drainage excavation (unclassified) (203-01) | CY | 16,779 | $12.00 | $25.34 | $20.22 | $30.65 | $27.00 | $15.00 |
| 4 | Borrow excavation (graded solid rock) (203-02.01) | TON | 1,098 | $30.00 | $56.23 | $42.00 | $41.05 | $36.00 | $45.00 |
| 5 | Placing and spreading topsoil (203-04) | CY | 2,937.65 | $12.00 | $37.72 | $14.00 | $24.70 | $50.00 | $21.00 |
| 6 | Undercutting (203-05) | CY | 623 | $16.00 | $45.60 | $33.00 | $37.95 | $32.00 | $25.00 |
| 7 | Water (203-06) | MG | 88 | $20.00 | $14.29 | $20.00 | $10.00 | $19.00 | $5.00 |
| 8 | Backfill material (flowable fill) (204-08.01) | CY | 5 | $400.00 | $357.14 | $194.00 | $457.00 | $700.00 | $500.00 |
| 9 | 18" temporary slope drain (209-02.07) | LF | 22 | $50.00 | $35.71 | $44.00 | $55.00 | $91.00 | $75.00 |
| 10 | Sediment removal (209-05) | CY | 670 | $10.00 | $33.08 | $32.00 | $34.50 | $49.00 | $30.00 |
| 11 | Temporary silt fence (with backing) (209-08.02) | LF | 464 | $6.00 | $5.89 | $7.00 | $6.55 | $4.80 | $5.25 |
| 12 | Temporary silt fence (without backing) (209-08.03) | LF | 3,683 | $3.00 | $2.42 | $3.00 | $2.70 | $1.70 | $2.00 |
| 13 | Rock check dam (209-08.07) | EACH | 9 | $500.00 | $747.37 | $400.00 | $828.00 | $984.00 | $750.00 |
| 14 | Enhanced rock check dam (209-08.08) | EACH | 11 | $900.00 | $747.37 | $600.00 | $828.00 | $1,917.00 | $750.00 |
| 15 | Catch basin protection (type A) (209-40.30) | EACH | 3 | $100.00 | $436.84 | $850.00 | $484.00 | $637.00 | $750.00 |
| 16 | Mineral aggregate, type A base, grading D (303-01) | TON | 5,791 | $30.00 | $45.17 | $41.00 | $36.65 | $30.00 | $30.00 |
| 17 | Mineral aggregate (size 57) (303-10.01) | TON | 17.00 | $50.00 | $53.70 | $48.00 | $68.15 | $74.00 | $50.00 |
| 18 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 620 | $120.00 | $170.43 | $163.17 | $186.00 | $164.00 | $164.00 |
| 19 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 658 | $125.00 | $176.48 | $163.17 | $186.00 | $165.00 | $165.00 |
| 20 | Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21) | TON | 251 | $110.00 | $206.19 | $181.33 | $192.00 | $155.00 | $155.00 |
| 21 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01) | TON | 368 | $122.00 | $215.52 | $181.33 | $204.00 | $174.00 | $174.00 |
| 22 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08) | TON | 413 | $127.00 | $208.31 | $176.29 | $204.00 | $175.00 | $175.00 |
| 23 | Bituminous material for prime coat (PC) (402-01) | TON | 14 | $200.00 | $1,263.16 | $1,517.25 | $1,170.00 | $1,200.00 | $1,200.00 |
| 24 | Aggregate for cover material (PC) (402-02) | TON | 32 | $20.00 | $96.84 | $72.45 | $46.60 | $75.00 | $75.00 |
| 25 | Bituminous material for tack coat (TC) (403-01) | TON | 20 | $200.00 | $1,065.26 | $1,517.25 | $1,170.00 | $835.00 | $835.00 |
| 26 | Acs mix(PG64-22) grading D (411-01.10) | TON | 498 | $150.00 | $227.11 | $212.31 | $186.00 | $175.00 | $175.00 |
| 27 | Acs mix(PG70-22) grading D (411-02.10) | TON | 792 | $150.00 | $190.07 | $212.10 | $196.00 | $178.00 | $178.00 |
| 28 | Scoring shoulders (non-continuous) (16IN width) (411-12.02) | LM | 0.06 | $20,000 | $1,000.00 | $54,863 | $6,990.00 | $7,306.00 | $47,500 |
| 29 | Scoring for rumble stripe (non-continuous) (8IN width) (411-12.03) | LM | 0.17 | $10,000 | $1,000.00 | $54,863 | $6,990.00 | $7,306.00 | $47,500 |
| 30 | Cold planing bituminous pavement (415-01.01) | TON | 839 | $30.00 | $46.45 | $61.56 | $52.45 | $45.00 | $45.00 |
| 31 | 18" pipe culvert (607-03.30) | LF | 25 | $90.00 | $171.43 | $72.00 | $614.00 | $128.00 | $415.00 |
| 32 | 30" pipe culvert (607-06.30) | LF | 44 | $150.00 | $457.14 | $118.00 | $209.00 | $134.00 | $185.00 |
| 33 | 48" pipe culvert (607-09.30) | LF | 15 | $210.00 | $685.71 | $286.91 | $1,150.00 | $330.00 | $600.00 |
| 34 | Class A concrete (pipe endwalls) (611-07.01) | CY | 10 | $2,000.00 | $2,000.00 | $1,200.00 | $2,150.00 | $1,766.00 | $1,250.00 |
| 35 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 372 | $2.00 | $2.50 | $10.00 | $8.65 | $3.10 | $5.00 |
| 36 | 18IN endwall (cross drain) 4:1 (611-07.55) | EACH | 2 | $3,500.00 | $7,142.86 | $3,000.00 | $3,150.00 | $3,200.00 | $2,500.00 |
| 37 | 30IN endwall (cross drain) 4:1 (611-07.61) | EACH | 2 | $5,000.00 | $10,714 | $5,000.00 | $6,050.00 | $7,000.00 | $4,500.00 |
| 38 | Catch basins, type 42, > 4' - 8' depth (611-42.02) | EACH | 1 | $8,500.00 | $16,622 | $16,000 | $16,000 | $14,000 | $20,000 |
| 39 | 18" temporary drainage pipe (621-03.02) | LF | 60 | $50.00 | $71.43 | $50.00 | $67.90 | $62.00 | $100.00 |
| 40 | Extruded sloping curb (702-01.01) | LF | 156 | $30.00 | $35.71 | $38.58 | $29.15 | $26.00 | $28.72 |
| 41 | Earth pad for type 38 GR end treatment (705-04.09) | EACH | 5 | $500.00 | $1,052.63 | $900.00 | $1,170.00 | $831.00 | $800.00 |
| 42 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 300 | $32.91 | $31.58 | $40.43 | $34.95 | $30.60 | $29.50 |
| 43 | GR terminaltrailing end (type 13) MASH TL-3 (705-06.10) | EACH | 2 | $1,625.00 | $1,578.95 | $1,600.00 | $1,750.00 | $2,077.00 | $2,000.00 |
| 44 | GR terminal (in-inline) MASH TL-3 (705-06.11) | EACH | 2 | $1,125.00 | $1,421.05 | $1,500.00 | $1,570.00 | $1,506.00 | $1,750.00 |
| 45 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 2 | $3,488.00 | $3,631.58 | $3,700.00 | $4,020.00 | $3,064.00 | $2,950.00 |
| 46 | Portable impact attenuator NCHRP350 TL-3 (705-08.51) | EACH | 5 | $7,000.00 | $5,500.00 | $11,000 | $6,220.00 | $5,603.00 | $5,340.00 |
| 47 | Guardrail removed (706-01) | LF | 746 | $3.00 | $1.05 | $2.30 | $1.15 | $1.10 | $1.00 |
| 48 | Radius rail (706-06.03) | LF | 214 | $41.84 | $46.32 | $48.00 | $51.30 | $36.30 | $35.00 |
| 49 | High-visibility construction fence (707-08.11) | LF | 442 | $4.00 | $2.84 | $2.89 | $3.15 | $2.30 | $2.20 |
| 50 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 4 | $500.00 | $2,142.86 | $800.00 | $588.00 | $500.00 | $500.00 |
| 51 | Machined rip-rap (class A-3) (709-05.05) | TON | 102 | $70.00 | $82.04 | $60.00 | $82.75 | $57.00 | $50.00 |
| 52 | Machined rip-rap (class A-1) (709-05.06) | TON | 16 | $100.00 | $89.50 | $60.00 | $179.00 | $67.00 | $50.00 |
| 53 | Machined rip-rap (class C) (709-05.09) | TON | 1,038 | $50.00 | $65.55 | $69.00 | $81.15 | $63.00 | $50.00 |
| 54 | Aggregate underdrains (with pipe) (710-02) | LF | 1,580 | $14.00 | $12.11 | $13.00 | $13.40 | $12.30 | $15.00 |
| 55 | Lateral underdrain (710-05) | LF | 64 | $14.00 | $12.63 | $13.00 | $14.00 | $12.90 | $15.00 |
| 56 | Lateral underdrain endwall (6:1) (710-06.15) | EACH | 3 | $1,400.00 | $2,941.43 | $577.00 | $1,080.00 | $992.00 | $2,500.00 |
| 57 | Traffic control (712-01) | LS | 1 | $30,000 | $40,684 | $175,000 | $38,390 | $310,000 | $183,415 |
| 58 | Interconnected portable barrier rail (712-02.02) | LF | 2,100 | $32.00 | $57.50 | $51.00 | $49.75 | $32.00 | $35.00 |
| 59 | Flexible drums (channelizing) (712-04.01) | EACH | 30 | $50.00 | $30.53 | $38.00 | $33.80 | $31.00 | $29.00 |
| 60 | Barrier rail delineator (712-04.50) | EACH | 98 | $8.00 | $15.46 | $16.00 | $17.50 | $16.00 | $15.00 |
| 61 | Warning lights (type A) (712-05.01) | EACH | 2 | $20.00 | $20.00 | $46.00 | $23.30 | $21.00 | $20.00 |
| 62 | Signs (construction) (712-06) | SF | 779 | $9.00 | $6.85 | $9.24 | $8.00 | $7.20 | $6.85 |
| 63 | Temporary barricades (type III) (712-07.03) | LF | 12 | $20.00 | $24.00 | $23.00 | $27.95 | $25.20 | $24.00 |
| 64 | Arrow board (type C) (712-08.03) | EACH | 2 | $1,250.00 | $1,122.45 | $2,500.00 | $1,280.00 | $1,155.00 | $1,100.00 |
| 65 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 2,215 | $1.00 | $4.74 | $5.20 | $4.65 | $4.70 | $4.50 |
| 66 | Removable pavement marking (6" line) (712-09.08) | LF | 15,262 | $0.25 | $3.68 | $4.00 | $3.50 | $3.60 | $3.50 |
| 67 | Flexible delineator (white) (713-02.14) | EACH | 10 | $76.00 | $58.76 | $63.00 | $66.45 | $59.00 | $57.00 |
| 68 | Perforated/knockout square tube post (713-11.02) | LB | 854 | $10.36 | $4.16 | $4.80 | $4.70 | $4.30 | $4.04 |
| 69 | P post slip base (713-11.21) | EACH | 23 | $694.00 | $260.52 | $600.00 | $295.00 | $265.00 | $252.70 |
| 70 | Street name sign (rigid 0.100IN thick (713-14.21) | SF | 56 | $10.00 | $35.71 | $135.00 | $28.65 | $95.60 | $50.18 |
| 71 | Removal of signs, posts and footings (713-15) | LS | 1 | $626.00 | $128.87 | $1,155.00 | $146.00 | $132.00 | $125.00 |
| 72 | Changeable message sign unit (713-16.01) | EACH | 4 | $4,000.00 | $5,051.55 | $9,600.00 | $5,710.00 | $5,145.00 | $4,900.00 |
| 73 | Signs (R10-12A) (713-16.20) | EACH | 2 | $300.00 | $180.41 | $130.00 | $204.00 | $183.00 | $175.00 |
| 74 | Signs (W3-4, 48"X48") (713-16.21) | EACH | 2 | $389.00 | $314.43 | $320.00 | $659.00 | $593.00 | $553.54 |
| 75 | Signs (W16-13P, 24"X18") (713-16.22) | EACH | 2 | $232.00 | $57.73 | $59.00 | $370.00 | $333.00 | $323.86 |
| 76 | Signs (R2-1, 24"X30") (713-16.23) | EACH | 1 | $289.00 | $130.93 | $133.00 | $148.00 | $133.00 | $127.00 |
| 77 | Signs (W1-8R, 18"X24") (713-16.24) | EACH | 4 | $232.00 | $118.56 | $99.00 | $134.00 | $120.00 | $115.00 |
| 78 | Signs (R5-1, 36"X36") (713-16.25) | EACH | 2 | $326.00 | $212.37 | $200.00 | $240.00 | $216.00 | $206.00 |
| 79 | Signs (R5-1A, 42"X30") (713-16.26) | EACH | 2 | $339.00 | $212.37 | $196.00 | $240.00 | $216.00 | $206.00 |
| 80 | Signs (W13-13, 36"X60") (713-16.27) | EACH | 1 | $389.00 | $455.67 | $326.00 | $515.00 | $464.00 | $442.00 |
| 81 | Signs (W13-1P, 24"X24") (713-16.28) | EACH | 1 | $289.00 | $114.43 | $75.00 | $129.00 | $116.00 | $111.00 |
| 82 | Signs (W13-10, 36"X60") (713-16.29) | EACH | 1 | $389.00 | $374.23 | $252.00 | $423.00 | $381.00 | $363.00 |
| 83 | Signs (W13-11, 36"X60") (713-16.30) | EACH | 1 | $389.00 | $374.23 | $252.00 | $423.00 | $381.00 | $363.00 |
| 84 | Signs (W1-2R, 36"X36") (713-16.31) | EACH | 1 | $326.00 | $248.45 | $152.00 | $281.00 | $253.00 | $241.00 |
| 85 | Signs (W3-8A, 48"X30") (713-16.32) | EACH | 1 | $389.00 | $212.37 | $168.00 | $240.00 | $216.00 | $206.00 |
| 86 | Signs (W1-2R, 30"X30") (713-16.33) | EACH | 1 | $295.00 | $189.69 | $154.00 | $214.00 | $193.00 | $184.00 |
| 87 | Signs (W3-3, 36"X36") (713-16.34) | EACH | 4 | $326.00 | $248.45 | $200.00 | $281.00 | $253.00 | $241.00 |
| 88 | Luminaires (signal pole mounted) (714-09.09) | EACH | 4 | $1,420.00 | $1,463.92 | $1,491.00 | $2,000.00 | $1,806.00 | $1,420.00 |
| 89 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 10.64 | $50.00 | $47.37 | $47.25 | $46.60 | $46.00 | $45.00 |
| 90 | Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23) | EACH | 98.75 | $50.00 | $47.37 | $47.25 | $46.60 | $46.00 | $45.00 |
| 91 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 964 | $35.00 | $5.26 | $5.25 | $40.80 | $5.20 | $5.00 |
| 92 | Plastic pavement marking (stop line) (716-02.05) | LF | 334.46 | $25.00 | $21.05 | $21.00 | $23.30 | $20.80 | $20.00 |
| 93 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 26 | $250.00 | $263.16 | $262.00 | $192.00 | $259.00 | $250.00 |
| 94 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 83 | $4.00 | $3.16 | $3.15 | $2.35 | $3.10 | $3.00 |
| 95 | Plastic word pavement marking (only) (716-03.01) | EACH | 4 | $650.00 | $473.68 | $472.00 | $478.00 | $467.00 | $450.00 |
| 96 | Plastic pavement marking (straight-turn arrow) (716-04.01) | EACH | 3 | $500.00 | $368.42 | $367.00 | $350.00 | $363.00 | $350.00 |
| 97 | Plastic pavement marking (wrong way arrow) (716-04.06) | EACH | 1 | $1,200.00 | $421.05 | $420.00 | $699.00 | $415.00 | $4.00 |
| 98 | Painted pavement marking (4" line) (716-05.01) | LM | 1.01 | $2,500.00 | $2,105.26 | $2,100.00 | $1,160.00 | $2,067.00 | $2,000.00 |
| 99 | Painted pavement marking (8" barrier line) (716-05.02) | LF | 2,215 | $1.00 | $0.53 | $0.55 | $1.35 | $0.55 | $0.50 |
| 100 | Painted pavement marking (6" line) (716-05.20) | LM | 0.81 | $3,500.00 | $2,631.58 | $2,625.00 | $1,520.00 | $2,597.00 | $2,500.00 |
| 101 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 0.81 | $10,000 | $8,947.37 | $8,925.00 | $8,970.00 | $8,830.00 | $8,500.00 |
| 102 | Enhanced flat line thermo (8IN line) (716-12.06) | LF | 1,299.99 | $4.00 | $2.11 | $2.10 | $2.35 | $2.10 | $2.00 |
| 103 | Mobilization (717-01) | LS | 1 | $110,000 | $132,477 | $175,000 | $158,500 | $260,000 | $342,944 |
| 104 | CCTV camera system (pan tilt & zoom) (725-20.91) | EACH | 1 | $8,260.00 | $8,428.57 | $8,673.00 | $14,280 | $12,864 | $8,260.00 |
| 105 | Removal of signal equipment (730-01.02) | EACH | 1 | $2,500.00 | $2,551.02 | $2,625.00 | $5,620.00 | $5,061.00 | $2,500.00 |
| 106 | Signal head assembly (130 A3 with backplate) (730-02.03) | EACH | 3 | $1,514.00 | $1,544.90 | $1,589.00 | $1,680.00 | $1,517.00 | $1,514.00 |
| 107 | Signal head assembly (130 with backplate) (730-02.09) | EACH | 7 | $1,514.00 | $1,544.90 | $1,589.00 | $1,640.00 | $1,475.00 | $1,514.00 |
| 108 | Signal head assembly (150 A2H with backplate) (730-02.17) | EACH | 1 | $2,642.00 | $2,695.92 | $2,774.00 | $2,700.00 | $2,431.00 | $2,642.00 |
| 109 | Signal head assembly (130 A3F with backplate) (730-02.51) | EACH | 2 | $1,517.00 | $1,547.96 | $1,592.00 | $1,690.00 | $1,522.00 | $1,517.00 |
| 110 | Install pull box (type B) (730-03.21) | EACH | 10 | $1,200.00 | $1,224.49 | $1,260.00 | $1,390.00 | $1,249.00 | $1,200.00 |
| 111 | Electrical service connection (730-05.01) | EACH | 1 | $8,000.00 | $8,163.27 | $8,400.00 | $5,150.00 | $4,636.00 | $8,000.00 |
| 112 | Signal cable - 5 conductor (730-08.02) | LF | 1,815 | $2.50 | $2.55 | $2.25 | $2.35 | $2.10 | $2.50 |
| 113 | Signal cable - 7 conductor (730-08.03) | LF | 1,370 | $2.75 | $2.81 | $2.88 | $2.90 | $2.60 | $2.75 |
| 114 | Conduit 2" diameter (PVC schedule 40) (730-12.02) | LF | 1,375 | $22.00 | $22.45 | $23.00 | $19.80 | $17.80 | $22.00 |
| 115 | Conduit 2" diameter (directional bore) (730-12.23) | LF | 790 | $80.00 | $81.63 | $84.00 | $33.80 | $30.50 | $80.00 |
| 116 | Vehicle detector (radar - stop line) (730-13.12) | EACH | 4 | $11,160 | $11,388 | $11,718 | $12,240 | $11,026 | $11,160 |
| 117 | Vehicle detector (radar - advance) (730-13.13) | EACH | 2 | $11,656 | $11,894 | $12,238 | $13,350 | $12,024 | $11,656 |
| 118 | Cabinet (eight phase base mounted) (730-15.32) | EACH | 1 | $28,828 | $29,416 | $30,269 | $31,000 | $27,934 | $28,828 |
| 119 | Controller (atc) (730-16.04) | EACH | 1 | $6,455.00 | $6,586.73 | $6,777.00 | $7,460.00 | $6,721.00 | $6,455.00 |
| 120 | Pedestal pole (advanced flashing beacon) (730-23.30) | EACH | 2 | $4,391.00 | $4,480.61 | $4,610.00 | $5,030.00 | $4,531.00 | $4,391.00 |
| 121 | Cantilever signal support (1 arm @ 65') (730-25.13) | EACH | 2 | $46,136 | $47,072 | $4,844.00 | $54,840 | $49,411 | $46,136 |
| 122 | Cantilever signal support (1 arm @ 70') (730-25.14) | EACH | 2 | $46,036 | $46,976 | $48,337 | $56,950 | $51,312 | $46,036 |
| 123 | Flashing warning beacon (advanced warning to stop) (730-26.07) | EACH | 2 | $1,832.00 | $1,869.39 | $1,923.00 | $1,960.00 | $1,769.00 | $1,832.00 |
| 124 | Geotextile (type III)(erosion control) (740-10.03) | SY | 825 | $3.50 | $3.27 | $4.85 | $3.75 | $2.30 | $5.00 |
| 125 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 1,369 | $4.00 | $3.57 | $7.31 | $9.50 | $2.30 | $4.74 |
| 126 | Temporary sediment tube 18IN (740-11.03) | LF | 59 | $40.00 | $4.69 | $4.42 | $5.35 | $3.40 | $4.50 |
| 127 | Temporary seeding (with mulch) (801-01.07) | UNIT | 170 | $50.00 | $48.98 | $47.25 | $55.95 | $46.70 | $45.00 |
| 128 | Water (seeding & sodding) (801-03) | MG | 17 | $50.00 | $163.27 | $42.00 | $186.00 | $41.50 | $40.00 |
| 129 | Seed (supplemental application) (801-07) | LB | 56 | $10.00 | $4.69 | $5.25 | $5.35 | $5.20 | $5.00 |
| 130 | Fertilizer (supplemental application) (801-08) | TON | 1 | $2,000.00 | $2,653.06 | $1,050.00 | $3,030.00 | $1,038.00 | $1,000.00 |
| 131 | Sodding (new sod) (803-01) | SY | 6,240 | $5.00 | $5.82 | $5.00 | $6.65 | $5.00 | $4.80 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of June 26, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.