TDOT contract CNZ276 bid tabulation
The grading, drainage, retaining walls, signals, and paving on s.r. 126 from near east center street (l.m. 3.67) in kingsport to east of briarwood road (l.m. 5.75). Let by Tennessee DOT on December 5, 2025, Sullivan County. 2 bids received; low bid $82,304,525 by Nicholas Overbay DBA East Tennessee Turf and Landscape.
- Owner
- Tennessee DOT
- Letting
- 05 DEC 2025
- Pay items
- 498
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Nicholas Overbay DBA East Tennessee Turf and Landscape | $82,304,525 | Low |
| 2 | Summers-Taylor, Inc. | $88,509,364 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Nicholas Overbay DBA East Tennessee Turf and Landscape | 2. Summers-Taylor, Inc. |
|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $1,500,000 | $648,856 |
| 2 | CPM project schedule (108-03) | LS | 1 | $180,000 | $142,815 |
| 3 | Trainee (109-10.01) | HR | 5,680 | $0.80 | $0.80 |
| 4 | Clearing and grubbing (201-01) | LS | 1 | $1,500,000 | $1,200,000 |
| 5 | Removal of structures and obstructions (202-01) | LS | 1 | $250,000 | $649,617 |
| 6 | Removal of asphalt pavement (202-03.01) | SY | 2,028 | $10.00 | $33.77 |
| 7 | Road & drainage excavation (unclassified) (203-01) | CY | 144,651 | $28.00 | $44.41 |
| 8 | Borrow excavation (graded solid rock) (203-02.01) | TON | 37,043 | $76.00 | $64.38 |
| 9 | Borrow excavation (unclassified) (203-03.51) | CY | 153,001 | $31.00 | $38.21 |
| 10 | Placing and spreading topsoil (203-04) | CY | 8,843 | $22.00 | $41.21 |
| 11 | Undercutting (203-05) | CY | 18,360 | $21.00 | $36.96 |
| 12 | Water (203-06) | MG | 3,072 | $5.00 | $16.80 |
| 13 | Graded solid rock (in-place) (203-10.16) | CY | 1,826 | $50.00 | $108.03 |
| 14 | Backfill material (flowable fill) (204-08.01) | CY | 35 | $700.00 | $477.15 |
| 15 | Ditch (riprap, sand & plastic sheeting) (208-02.01) | LF | 15,846 | $70.00 | $21.58 |
| 16 | 12" temporary slope drain (209-02.05) | LF | 11,000 | $35.00 | $38.22 |
| 17 | Filter sock (12 inch) (209-03.21) | LF | 775 | $7.00 | $5.80 |
| 18 | Sediment removal (209-05) | CY | 1,636 | $20.00 | $40.81 |
| 19 | Temporary silt fence (with backing) (209-08.02) | LF | 4,483 | $7.00 | $8.96 |
| 20 | Temporary silt fence (without backing) (209-08.03) | LF | 10,893 | $5.00 | $2.11 |
| 21 | Rock check dam (209-08.07) | EACH | 517 | $650.00 | $567.30 |
| 22 | Enhanced rock check dam (209-08.08) | EACH | 58 | $1,050.00 | $1,040.03 |
| 23 | Sandbags (209-09.01) | BAG | 7,450 | $14.00 | $10.20 |
| 24 | Sediment filter bag (15' X 15') (209-09.03) | EACH | 2 | $1,500.00 | $1,070.34 |
| 25 | Curb inlet protection (type 2) (209-09.41) | EACH | 1 | $1,000.00 | $342.60 |
| 26 | Curb inlet protection (type 4) (209-09.43) | EACH | 231 | $550.00 | $342.60 |
| 27 | Temporary dewatering structure (209-10.01) | CY | 382 | $40.00 | $36.50 |
| 28 | Polyethylene sheeting (6 mil. minimum) (209-20.03) | SY | 250 | $4.00 | $7.58 |
| 29 | Catch basin protection (type D) (209-40.33) | EACH | 20 | $500.00 | $342.60 |
| 30 | Catch basin protection (type E) (209-40.34) | EACH | 3 | $550.00 | $263.53 |
| 31 | Catch basin filter assembly(type 1) (209-40.41) | EACH | 20 | $800.00 | $790.61 |
| 32 | Catch basin filter assembly(type 4) (209-40.44) | EACH | 1 | $1,100.00 | $790.60 |
| 33 | Catch basin filter assembly(type 8) (209-40.48) | EACH | 5 | $1,000.00 | $790.60 |
| 34 | Mineral aggregate, type A base, grading D (303-01) | TON | 61,378 | $52.00 | $57.41 |
| 35 | Mineral aggregate (size 57) (303-10.01) | TON | 3,627 | $70.00 | $84.53 |
| 36 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 201 | $285.00 | $214.95 |
| 37 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 3,156 | $211.00 | $233.27 |
| 38 | Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21) | TON | 10,419 | $158.00 | $140.34 |
| 39 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01) | TON | 13,519 | $160.00 | $140.94 |
| 40 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08) | TON | 8,856 | $162.00 | $151.12 |
| 41 | Treated permeable base (313-03) | SY | 1,671 | $45.00 | $63.91 |
| 42 | Bituminous material for prime coat (PC) (402-01) | TON | 136 | $1,000.00 | $1,578.83 |
| 43 | Aggregate for cover material (PC) (402-02) | TON | 456 | $168.00 | $108.23 |
| 44 | Bituminous material for tack coat (TC) (403-01) | TON | 20 | $2,000.00 | $1,187.62 |
| 45 | Acs mix(PG64-22) grading D (411-01.10) | TON | 1,868 | $273.00 | $272.01 |
| 46 | Acs mix(PG70-22) grading D (411-02.10) | TON | 5,192 | $201.00 | $166.13 |
| 47 | Portland cement concrete pavement (plain) 10" (501-01.03) | SY | 1,671 | $175.00 | $180.39 |
| 48 | Structural steel (602-01) | LB | 64.45 | $40.00 | $6.79 |
| 49 | Class A concrete (roadway) (604-01.01) | CY | 0.62 | $1,500.00 | $3,397.69 |
| 50 | Box tube safety rail (604-01.20) | LF | 353 | $258.00 | $389.20 |
| 51 | Energy dissipater (usbr TY VI - 24", W = 5') (604-02.41) | EACH | 2 | $10,000 | $36,324 |
| 52 | Energy dissipater (usbr TY VI - 30", W =5') (604-02.42) | EACH | 1 | $10,000 | $36,324 |
| 53 | Energy dissipater (usbr TY VI - 30", W = 7') (604-02.44) | EACH | 2 | $10,000 | $41,109 |
| 54 | Retaining wall (sta. 253+00 - sta. 255+00 LT) (604-07.01) | SF | 1,427 | $160.00 | $292.84 |
| 55 | Retaining wall (glenwood sta. 48+00 - sta. 48+85 LT) (604-07.02) | SF | 982 | $150.00 | $192.92 |
| 56 | Retaining wall (sta 287+50 to sta 291+50 RT) (604-07.03) | SF | 4,601 | $150.00 | $244.81 |
| 57 | Retaining wall (sta 291+50 to sta 292+00 RT) (604-07.04) | SF | 512 | $150.00 | $193.50 |
| 58 | Retaining wall (harbor chapel 50+75 to 278+75 RT) (604-07.05) | SF | 5,377 | $160.00 | $130.23 |
| 59 | Retaining wall (sta. 282+25 to sta. 286+75 LT) (604-07.06) | SF | 2,945 | $180.00 | $564.65 |
| 60 | Retaining wall (sta 291+00 to sta 297+00 LT) (604-07.07) | SF | 10,382 | $111.00 | $147.68 |
| 61 | Retaining wall (ramp C) (604-07.08) | SF | 1,360 | $265.00 | $235.86 |
| 62 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 7,388 | $150.00 | $281.73 |
| 63 | 18" concrete pipe culvert (class V) (607-03.04) | LF | 27 | $200.00 | $285.65 |
| 64 | 24" concrete pipe culvert (class III) (607-05.02) | LF | 2,640 | $175.00 | $339.90 |
| 65 | 30" concrete pipe culvert (class III) (607-06.02) | LF | 1,396 | $200.00 | $362.38 |
| 66 | 30" concrete pipe culvert (class V) (607-06.04) | LF | 154 | $225.00 | $387.30 |
| 67 | 36" concrete pipe culvert (class III) (607-07.02) | LF | 912 | $260.00 | $379.71 |
| 68 | 42" concrete pipe culvert (class III) (607-08.02) | LF | 429 | $300.00 | $450.02 |
| 69 | 48" concrete pipe culvert (class III) (607-09.02) | LF | 626 | $380.00 | $534.56 |
| 70 | 60" concrete pipe culvert (class III) (607-11.03) | LF | 466 | $700.00 | $927.25 |
| 71 | 18" corrugated metal pipe culvert (607-37.02) | LF | 16 | $100.00 | $253.66 |
| 72 | 18" pipe culvert (side drain) (607-39.02) | LF | 523 | $85.00 | $146.77 |
| 73 | 24" pipe culvert (side drain) (607-39.03) | LF | 202 | $100.00 | $153.75 |
| 74 | 60" pipe culvert (side drain) (607-39.09) | LF | 81 | $280.00 | $322.46 |
| 75 | 18" slotted drain pipe (607-45.02) | LF | 40 | $250.00 | $195.14 |
| 76 | Manholes, > 4' - 8' depth (611-01.02) | EACH | 2 | $6,000.00 | $9,370.21 |
| 77 | Manholes, > 8' - 12' depth (611-01.03) | EACH | 3 | $12,000 | $10,548 |
| 78 | Manholes, > 12' - 16' depth (611-01.04) | EACH | 1 | $15,000 | $14,528 |
| 79 | Manholes, > 16' - 20' depth (611-01.05) | EACH | 1 | $20,000 | $21,116 |
| 80 | Manholes, > 20' - 24' depth (611-01.06) | EACH | 1 | $30,000 | $22,234 |
| 81 | Manholes, > 24' - 28' depth (611-01.07) | EACH | 2 | $40,000 | $25,250 |
| 82 | Junction box, type 2 (611-02.11) | EACH | 1 | $8,000.00 | $5,120.00 |
| 83 | Class A concrete (pipe endwalls) (611-07.01) | CY | 139 | $2,200.00 | $1,986.39 |
| 84 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 6,353 | $5.50 | $2.87 |
| 85 | Structural steel (pipe endwalls) (611-07.03) | LB | 728 | $10.00 | $9.35 |
| 86 | 18IN endwall (side drain) (611-07.31) | EACH | 2 | $3,000.00 | $5,723.73 |
| 87 | 18IN endwall (cross drain) 3:1 (611-07.54) | EACH | 16 | $3,000.00 | $2,904.07 |
| 88 | 24IN endwall (cross drain) 3:1 (611-07.57) | EACH | 1 | $3,800.00 | $3,587.93 |
| 89 | 30IN endwall (cross drain) 3:1 (611-07.60) | EACH | 1 | $5,000.00 | $5,592.38 |
| 90 | 36IN endwall (cross drain) 3:1 (611-07.63) | EACH | 1 | $6,500.00 | $6,907.00 |
| 91 | 36IN endwall (cross drain) 4:1 (611-07.64) | EACH | 2 | $6,500.00 | $8,354.82 |
| 92 | 42IN endwall (cross drain) 3:1 (611-07.66) | EACH | 1 | $7,500.00 | $13,614 |
| 93 | 48IN endwall (cross drain) 3:1 (611-07.69) | EACH | 2 | $9,000.00 | $6,990.75 |
| 94 | Catch basins, type 12, 0' - 4' depth (611-12.01) | EACH | 16 | $5,500.00 | $7,643.85 |
| 95 | Catch basins, type 12, > 4' - 8' depth (611-12.02) | EACH | 55 | $6,500.00 | $8,811.99 |
| 96 | Catch basins, type 12, > 8' - 12' depth (611-12.03) | EACH | 18 | $10,000 | $12,153 |
| 97 | Catch basins, type 12, > 12' - 16' depth (611-12.04) | EACH | 8 | $17,000 | $18,281 |
| 98 | Catch basins, type 12, > 16' - 20' depth (611-12.05) | EACH | 1 | $22,000 | $20,842 |
| 99 | Catch basins, type 12, > 20' - 24' depth (611-12.06) | EACH | 1 | $29,000 | $23,749 |
| 100 | Catch basins, type 13, > 4' - 8' depth (611-13.02) | EACH | 1 | $7,500.00 | $7,002.06 |
| 101 | Catch basins, type 13, > 12' - 16' depth (611-13.04) | EACH | 1 | $15,000 | $9,336.05 |
| 102 | Catch basins, type 14, 0' - 4' depth (611-14.01) | EACH | 2 | $7,000.00 | $11,184 |
| 103 | Catch basins, type 14, > 4' - 8' depth (611-14.02) | EACH | 20 | $13,500 | $12,117 |
| 104 | Catch basins, type 14, > 8' - 12' depth (611-14.03) | EACH | 6 | $17,000 | $23,620 |
| 105 | Catch basins, type 14, > 12' - 16' depth (611-14.04) | EACH | 3 | $22,000 | $42,208 |
| 106 | Catch basins, type 16, > 4' - 8' depth (611-16.02) | EACH | 3 | $12,000 | $13,480 |
| 107 | Catch basins, type 25, > 4' - 8' depth (611-25.02) | EACH | 2 | $6,000.00 | $8,258.38 |
| 108 | Catch basins, type 26, > 4' - 8' depth (611-26.02) | EACH | 5 | $7,500.00 | $11,870 |
| 109 | Catch basins, type 27, > 4' - 8' depth (611-27.02) | EACH | 1 | $13,000 | $16,806 |
| 110 | Catch basins, type 27, > 12' - 16' depth (611-27.04) | EACH | 1 | $17,000 | $27,694 |
| 111 | Catch basins, type 28, > 4' - 8' depth (611-28.02) | EACH | 6 | $13,000 | $6,922.50 |
| 112 | Catch basins, type 28, > 12' - 16' depth (611-28.04) | EACH | 1 | $18,000 | $14,889 |
| 113 | Catch basins, type 28, > 20' - 24' depth (611-28.06) | EACH | 1 | $30,000 | $15,071 |
| 114 | Catch basins, type 28, >( ' - ' depth) (611-28.08) | EACH | 1 | $25,000 | $25,326 |
| 115 | Catch basins, type 29, > 4' - 8' depth (611-29.02) | EACH | 1 | $16,000 | $13,444 |
| 116 | Catch basins, type 39, > 4' - 8' depth (611-39.02) | EACH | 1 | $25,000 | $24,518 |
| 117 | Catch basins, type 41, 0' - 4' depth (611-41.01) | EACH | 1 | $5,500.00 | $7,333.94 |
| 118 | Catch basins, type 41, > 4' - 8' depth (611-41.02) | EACH | 1 | $7,500.00 | $7,595.78 |
| 119 | Catch basins, type 42, 0' - 4' depth (611-42.01) | EACH | 18 | $7,500.00 | $7,035.38 |
| 120 | Catch basins, type 42, > 4' - 8' depth (611-42.02) | EACH | 17 | $10,000 | $8,173.59 |
| 121 | Catch basins, type 42, > 8' - 12' depth (611-42.03) | EACH | 2 | $18,000 | $17,071 |
| 122 | Catch basins, type 42, > 12' - 16' depth (611-42.04) | EACH | 1 | $23,000 | $22,184 |
| 123 | Catch basins, type 43, 0' - 4' depth (611-43.01) | EACH | 2 | $12,000 | $12,686 |
| 124 | Catch basins, type 43, > 4' - 8' depth (611-43.02) | EACH | 7 | $16,000 | $13,506 |
| 125 | Catch basins, type 43, > 8' - 12' depth (611-43.03) | EACH | 1 | $20,000 | $19,903 |
| 126 | Catch basins, type 44, > 4' - 8' depth (611-44.02) | EACH | 2 | $35,000 | $35,483 |
| 127 | Catch basins, type 44, > 8' - 12' depth (611-44.03) | EACH | 1 | $48,000 | $46,201 |
| 128 | Catch basins, type 45, > 4' - 8' depth (611-45.02) | EACH | 1 | $15,000 | $16,213 |
| 129 | Catch basins, (type >4'-8'depth) (611-90.01) | EACH | 1 | $18,000 | $13,885 |
| 130 | Conc parapet single slope (STD-1-1SS) (620-05.01) | LF | 450 | $155.00 | $148.73 |
| 131 | 24" temporary drainage pipe (621-03.03) | LF | 70 | $65.00 | $141.24 |
| 132 | 36" temporary drainage pipe (621-03.05) | LF | 72 | $150.00 | $189.34 |
| 133 | Steel mesh & plates (622-02.01) | SF | 124 | $65.00 | $298.64 |
| 134 | Concrete sidewalk (4 ") (701-01.01) | SF | 77,943 | $10.25 | $12.33 |
| 135 | Concrete driveway (701-02) | SF | 16,028 | $16.00 | $17.63 |
| 136 | Concrete curb ramp (701-02.03) | SF | 3,769 | $30.00 | $56.33 |
| 137 | Concrete curb (702-01.02) | LF | 10,350 | $38.00 | $34.74 |
| 138 | Concrete combined curb & gutter (702-03) | CY | 1,700 | $600.00 | $609.40 |
| 139 | Portland cement concrete ditch paving (703-01) | CY | 32.20 | $900.00 | $802.13 |
| 140 | Single guardrail (type 2) (705-02.02) | LF | 5,300 | $29.25 | $27.29 |
| 141 | Earth pad for guard rail end treatment (705-04.10) | EACH | 6 | $2,400.00 | $2,086.88 |
| 142 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 175 | $30.00 | $26.22 |
| 143 | GR terminaltrailing end (type 13) MASH TL-3 (705-06.10) | EACH | 11 | $2,000.00 | $1,658.80 |
| 144 | GR terminal (in-inline) MASH TL-3 (705-06.11) | EACH | 4 | $1,800.00 | $1,284.23 |
| 145 | GR terminal (energy absorbing) MASH TL-2 (705-06.30) | EACH | 6 | $4,000.00 | $3,424.62 |
| 146 | Permanent impact attenuator NCHRP350 TL-3 (705-08.13) | EACH | 2 | $34,800 | $33,176 |
| 147 | Guardrail removed (706-01) | LF | 4,119 | $3.73 | $2.68 |
| 148 | Radius rail (706-06.03) | LF | 4 | $50.00 | $33.18 |
| 149 | Rounded end element (706-10.26) | EACH | 4 | $300.00 | $240.80 |
| 150 | High-visibility construction fence (707-08.11) | LF | 750 | $5.00 | $4.74 |
| 151 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 227 | $525.00 | $615.97 |
| 152 | Machined rip-rap (class A-3) (709-05.05) | TON | 10 | $90.00 | $96.77 |
| 153 | Machined rip-rap (class A-1) (709-05.06) | TON | 1,402 | $68.00 | $86.74 |
| 154 | Machined rip-rap (class A-2) (709-05.07) | TON | 579 | $68.00 | $85.96 |
| 155 | Machined rip-rap (class B) (709-05.08) | TON | 3,758 | $60.00 | $84.13 |
| 156 | Machined rip-rap (class C) (709-05.09) | TON | 8,010 | $82.00 | $85.11 |
| 157 | Aggregate underdrains (with pipe) (710-02) | LF | 19,353 | $15.50 | $15.49 |
| 158 | Lateral underdrain (710-05) | LF | 354 | $15.00 | $29.22 |
| 159 | Lateral underdrain endwall (2:1) (710-06.11) | EACH | 2 | $2,000.00 | $1,318.91 |
| 160 | Lateral underdrain endwall (3:1) (710-06.12) | EACH | 8 | $2,000.00 | $1,318.90 |
| 161 | Lateral underdrain endwall (4:1) (710-06.13) | EACH | 2 | $2,000.00 | $1,318.91 |
| 162 | Lateral underdrain endwall (6:1) (710-06.15) | EACH | 1 | $2,000.00 | $1,318.90 |
| 163 | Traffic control (712-01) | LS | 1 | $2,600,000 | $1,750,000 |
| 164 | Flexible drums (channelizing) (712-04.01) | EACH | 273 | $65.00 | $64.30 |
| 165 | Signs (construction) (712-06) | SF | 944 | $11.00 | $6.85 |
| 166 | Temporary barricades (type II) (712-07.02) | LF | 75 | $25.00 | $23.19 |
| 167 | Temporary barricades (type III) (712-07.03) | LF | 994 | $22.00 | $21.08 |
| 168 | Arrow board (type C) (712-08.03) | EACH | 4 | $2,000.00 | $2,319.11 |
| 169 | Removable pavement marking (arrow) (712-09.05) | EACH | 131 | $480.00 | $421.66 |
| 170 | Sign post delineation enhancement (713-02.21) | LF | 10 | $15.00 | $6.33 |
| 171 | "U" section steel posts (713-11.01) | LB | 270 | $6.25 | $5.27 |
| 172 | Perforated/knockout square tube post (713-11.02) | LB | 2,745 | $7.50 | $6.17 |
| 173 | U post slip base (713-11.22) | EACH | 2 | $550.00 | $606.13 |
| 174 | Flat sheet aluminum signs (0.064" thick) (713-13.01) | SF | 1,270.50 | $12.00 | $9.49 |
| 175 | Street name sign (rigid 0.100IN thick (713-14.21) | SF | 271 | $28.00 | $24.25 |
| 176 | Removal of signs, posts and footings (713-15) | LS | 1 | $30,000 | $1,054.14 |
| 177 | Changeable message sign unit (713-16.01) | EACH | 2 | $12,000 | $11,596 |
| 178 | LED luminaires (275 watt) (714-09.46) | EACH | 4 | $1,800.00 | $1,581.21 |
| 179 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 6,641 | $28.00 | $29.52 |
| 180 | Plastic pavement marking (6" dotted line) (716-02.11) | LF | 957 | $3.00 | $3.43 |
| 181 | Plastic word pavement marking (only) (716-03.01) | EACH | 4 | $350.00 | $263.54 |
| 182 | Plastic pavement marking-bike symbol/arrow shared (716-04.15) | EACH | 34 | $470.00 | $500.72 |
| 183 | Painted pavement marking (4" line) (716-05.01) | LM | 16.70 | $1,400.00 | $1,844.74 |
| 184 | Painted pavement marking (cross-walk) (716-05.03) | LF | 638 | $8.00 | $7.91 |
| 185 | Painted pavement marking (stop line) (716-05.05) | LF | 700 | $7.00 | $7.91 |
| 186 | Painted pavement marking (turn lane arrow) (716-05.06) | EACH | 50 | $175.00 | $158.12 |
| 187 | Painted pavement marking(straight-turn arrow) (716-05.09) | EACH | 5 | $200.00 | $184.48 |
| 188 | Painted pavement marking(straight arrow) (716-05.11) | EACH | 2 | $165.00 | $158.12 |
| 189 | Painted pavement marking(4"dotted line) (716-05.21) | LF | 429 | $1.35 | $0.53 |
| 190 | Removal of pavement marking (line) (716-08.01) | LF | 6,363 | $1.20 | $1.32 |
| 191 | Removal of pavement marking (channelization striping) (716-08.04) | SY | 593 | $18.00 | $23.19 |
| 192 | Removal of pavement marking (stop line) (716-08.05) | LF | 34 | $6.35 | $8.17 |
| 193 | Removal of pavement marking (turn lane arrow) (716-08.06) | EACH | 4 | $200.00 | $105.42 |
| 194 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 11.20 | $7,750.00 | $7,906.05 |
| 195 | Mobilization (717-01) | LS | 1 | $5,800,000 | $3,900,000 |
| 196 | Video detection cable (725-03.99) | LF | 4,550 | $3.50 | $1.05 |
| 197 | Removal of signal equipment (730-01.02) | EACH | 4 | $10,000 | $5,270.70 |
| 198 | Signal head assembly (130 pole mounted) (730-02.08) | EACH | 1 | $1,500.00 | $1,528.50 |
| 199 | Signal head assembly (130 with backplate) (730-02.09) | EACH | 30 | $1,750.00 | $1,528.50 |
| 200 | Signal head assembly (140 A4F with backplate) (730-02.30) | EACH | 8 | $2,000.00 | $1,686.62 |
| 201 | Install pull box (type B) (730-03.21) | EACH | 43 | $1,200.00 | $2,635.35 |
| 202 | Install pull box (fiber optic-type B) (730-03.24) | EACH | 16 | $5,500.00 | $5,270.70 |
| 203 | Fiber optic splice fusion (730-03.33) | EACH | 165 | $450.00 | $26.35 |
| 204 | Electrical service connection (730-05.01) | EACH | 6 | $6,500.00 | $3,689.49 |
| 205 | Signal cable - 3 conductor (730-08.01) | LF | 4,600 | $3.50 | $2.68 |
| 206 | Signal cable - 5 conductor (730-08.02) | LF | 6,500 | $3.80 | $2.95 |
| 207 | Signal cable - 7 conductor (730-08.03) | LF | 5,700 | $3.80 | $3.45 |
| 208 | Signal cable - 9 conductor (730-08.04) | LF | 150 | $5.35 | $4.15 |
| 209 | Interconnect cable - fiber optic (12 fiber single-mode) (730-08.40) | LF | 7,692 | $4.50 | $4.74 |
| 210 | Interconnect cable - fiber optic (6 fiber drop) (730-08.41) | LF | 1,126 | $6.00 | $26.35 |
| 211 | Conduit 2" diameter (PVC schedule 40) (730-12.02) | LF | 9,938 | $17.00 | $9.03 |
| 212 | Conduit 3" diameter (PVC schedule 40) (730-12.03) | LF | 420 | $19.00 | $10.51 |
| 213 | Conduit 2" diameter (jack and bore) (730-12.13) | LF | 526 | $33.00 | $20.82 |
| 214 | Conduit 2" diameter (directional bore) (730-12.23) | LF | 440 | $35.00 | $20.82 |
| 215 | Conduit 3" diameter (directional bore) (730-12.24) | LF | 970 | $40.00 | $22.30 |
| 216 | Vehicle detector (video) (730-13.02) | EACH | 22 | $15,000 | $10,541 |
| 217 | Cabinet (pedestrian hybrid beacon) (730-15.07) | EACH | 2 | $29,000 | $36,895 |
| 218 | Cabinet (eight phase base mounted) (730-15.32) | EACH | 4 | $29,000 | $36,895 |
| 219 | Controller (atc) (730-16.04) | EACH | 4 | $8,800.00 | $8,433.12 |
| 220 | Controller (pedestrian hybrid beacon) (730-16.14) | EACH | 2 | $8,800.00 | $8,433.12 |
| 221 | Pedestal pole (description) (730-23.31) | EACH | 18 | $3,300.00 | $5,270.70 |
| 222 | Cantilever signal support (1 arm @ 40') (730-23.80) | EACH | 1 | $42,000 | $42,561 |
| 223 | Cantilever signal support (2 @ 45' & 50') (730-24.90) | EACH | 5 | $48,000 | $50,203 |
| 224 | Cantilever signal support (2 @ 45' & 55') (730-24.91) | EACH | 1 | $60,000 | $58,373 |
| 225 | Cantilever signal support (1 arm @ 50') (730-25.01) | EACH | 1 | $40,000 | $43,615 |
| 226 | Cantilever signal support (1 arm @ 55') (730-25.07) | EACH | 1 | $48,000 | $49,940 |
| 227 | Cantilever signal support (1 arm @ 60') (730-25.11) | EACH | 1 | $50,000 | $51,521 |
| 228 | Cantilever signal support (1 arm @ 65') (730-25.13) | EACH | 3 | $50,000 | $52,048 |
| 229 | Cantilever signal support (1 arm @ 70') (730-25.14) | EACH | 3 | $52,000 | $52,312 |
| 230 | Pedestrian pushbutton with 12" sign (730-26.02) | EACH | 22 | $2,500.00 | $1,317.67 |
| 231 | Countdown pedestrian signal (730-26.05) | EACH | 22 | $2,500.00 | $1,317.67 |
| 232 | Countdown ped SGNL head W/audible pushbutton & 15IN sign (730-26.11) | EACH | 22 | $3,100.00 | $2,635.35 |
| 233 | Battery back-UP system (730-35.06) | EACH | 4 | $15,000 | $12,650 |
| 234 | Temporary traffic signal system (730-40) | EACH | 2 | $35,000 | $84,152 |
| 235 | Pedestrian hybrid beacon assembly (730-50.25) | EACH | 4 | $42,000 | $2,635.35 |
| 236 | Geotextile (type III)(erosion control) (740-10.03) | SY | 13,994 | $4.00 | $2.86 |
| 237 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 40,626 | $5.00 | $8.17 |
| 238 | Temporary sediment tube 12IN (740-11.02) | LF | 775 | $5.50 | $4.48 |
| 239 | 8IN dip gravity sewer 0FT-6FT depth (797-05.01) | LF | 225 | $150.00 | $325.95 |
| 240 | 8IN dip gravity sewer 6FT-12FT depth (797-05.02) | LF | 293 | $225.00 | $383.72 |
| 241 | 48IN manhole 4FT-6FT depth (797-07.02) | EACH | 2 | $10,000 | $8,517.20 |
| 242 | 48IN manhole 6FT-8FT depth (797-07.03) | EACH | 2 | $14,000 | $9,551.56 |
| 243 | 48IN manhole 10FT-12FT depth (797-07.05) | EACH | 1 | $18,000 | $14,441 |
| 244 | Seeding (with mulch) (801-01) | UNIT | 945 | $60.00 | $47.44 |
| 245 | Temporary seeding (with mulch) (801-01.07) | UNIT | 500 | $50.00 | $42.17 |
| 246 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 48 | $200.00 | $105.41 |
| 247 | Seeding (without mulch) (801-02) | UNIT | 1,421 | $55.00 | $27.41 |
| 248 | Water (seeding & sodding) (801-03) | MG | 242 | $100.00 | $68.52 |
| 249 | Seed (supplemental application) (801-07) | LB | 2,931 | $5.00 | $3.43 |
| 250 | Sodding (new sod) (803-01) | SY | 2,424 | $9.00 | $9.49 |
| 251 | Turf reinforcement mat (class II) (805-01.02) | SY | 5,675 | $5.00 | $6.85 |
| 252 | Erosion control blanket (type II) (805-12.02) | SY | 70,322 | $1.75 | $1.21 |
| 253 | Project mowing (806-02.03) | CYCL | 4 | $5,000.00 | $2,082.22 |
| 254 | Pole 35FT class 4 wood (790-02.03) | EACH | 14 | $1,200.00 | $954.81 |
| 255 | Pole 40FT class 4 wood (790-03.03) | EACH | 8 | $1,500.00 | $1,049.70 |
| 256 | Pole 45FT class 2 wood (790-04.02) | EACH | 2 | $1,645.00 | $1,369.77 |
| 257 | Pole 45FT class 3 wood (790-04.03) | EACH | 11 | $1,525.00 | $1,250.85 |
| 258 | Pole 50FT class 1 wood (790-05.01) | EACH | 6 | $2,100.00 | $1,742.97 |
| 259 | Pole 50FT class 2 wood (790-05.02) | EACH | 71 | $2,100.00 | $1,620.26 |
| 260 | Pole 55FT class 1 wood (790-06.01) | EACH | 31 | $2,500.00 | $1,948.51 |
| 261 | Pole 55FT class 2 wood (790-06.02) | EACH | 3 | $2,400.00 | $1,880.78 |
| 262 | Pole 55FT class H1 wood (790-06.19) | EACH | 2 | $2,800.00 | $2,241.35 |
| 263 | Pole 60FT class 1 wood (790-07.01) | EACH | 6 | $3,000.00 | $2,433.54 |
| 264 | Pole 65FT class 1 wood (790-08.30) | EACH | 4 | $3,350.00 | $2,901.63 |
| 265 | Pole 70FT class 1 wood (790-09.01) | EACH | 4 | $3,665.00 | $3,220.36 |
| 266 | Top existing pole (790-20.30) | EACH | 3 | $300.00 | $125.16 |
| 267 | Field pole modifiction (790-20.31) | EACH | 10 | $400.00 | $250.31 |
| 268 | 1PH SGL primary support 15KV (790-21.01) | EACH | 2 | $450.00 | $459.98 |
| 269 | 1PH DBL primary support 15KV (790-21.05) | EACH | 1 | $650.00 | $644.46 |
| 270 | 1PH primary LG angle 15KV (790-21.07) | EACH | 8 | $600.00 | $532.21 |
| 271 | 1PH deadend 15KV (790-21.08) | EACH | 12 | $525.00 | $498.24 |
| 272 | 1PH primary tap 15KV (790-21.09) | EACH | 39 | $520.00 | $449.53 |
| 273 | 3PH crossarm SGL 15KV (790-25.01) | EACH | 6 | $1,400.00 | $965.78 |
| 274 | 3PH narrow profile SGL LG cond 15KV (790-25.03) | EACH | 2 | $1,600.00 | $1,297.84 |
| 275 | 3PH crossarm DBL prim support 15KV (790-25.10) | EACH | 36 | $1,900.00 | $1,570.49 |
| 276 | 3PH crossarm DBL prim sup LRG cond 15KV (790-25.11) | EACH | 38 | $1,900.00 | $1,558.86 |
| 277 | 3PH narrow profile LG cond SM angle 15KV (790-25.14) | EACH | 3 | $1,200.00 | $1,071.68 |
| 278 | 3PH vertical deadend LRG ang LG cond 15KV (790-25.18) | EACH | 5 | $1,900.00 | $1,571.35 |
| 279 | 3PH vertical deadend LG cond 15KV (790-25.20) | EACH | 3 | $1,300.00 | $903.80 |
| 280 | 3PH crossarm deadend SGL 15KV (790-25.21) | EACH | 27 | $1,550.00 | $1,286.53 |
| 281 | 3PH crossarm dde 15KV (790-25.23) | EACH | 19 | $2,600.00 | $2,005.90 |
| 282 | Service assembly-pole type (790-31.02) | EACH | 131 | $200.00 | $172.74 |
| 283 | Service conductor 6 AL duplex (790-31.04) | LF | 8,620 | $3.75 | $2.97 |
| 284 | Service conductor 2 AL triplex (790-31.11) | LF | 3,692 | $5.40 | $4.54 |
| 285 | Service conductor 1/0 AL qplex (790-31.20) | LF | 211 | $10.00 | $6.84 |
| 286 | Down guy - through bolt type (790-32.01) | EACH | 84 | $480.00 | $328.21 |
| 287 | Down guy - insulated (790-32.06) | EACH | 147 | $465.00 | $356.12 |
| 288 | Guy guard (790-32.23) | EACH | 248 | $30.00 | $22.46 |
| 289 | Overhead guy light construction - preform (790-32.27) | EACH | 34 | $400.00 | $258.18 |
| 290 | Screw type anchor 23,000LB (F1-5D-P) (790-33.31) | EACH | 121 | $685.00 | $543.72 |
| 291 | Screw type anchor 36,000LB (F1-6T-P) (790-33.32) | EACH | 17 | $1,500.00 | $1,279.44 |
| 292 | Transfer service (790-36.04) | EACH | 11 | $340.00 | $333.05 |
| 293 | Transfer - light assembly (790-36.10) | EACH | 7 | $340.00 | $343.27 |
| 294 | Transfer existing 3PH transformer/recloser (790-36.12) | EACH | 3 | $6,000.00 | $4,819.58 |
| 295 | Switch-900A-underslung (three phase) (790-36.21) | EACH | 9 | $4,600.00 | $3,853.20 |
| 296 | OH cond 4 7/1 acsr swanate (790-40.01) | LF | 333 | $2.95 | $2.08 |
| 297 | OH cond 2 7/1 acsr sparate (790-40.02) | LF | 7,954 | $2.88 | $2.65 |
| 298 | OH cond 1/0 6/1 acsr raven (790-40.03) | LF | 137 | $3.00 | $2.42 |
| 299 | OH cond 4/0 6/1 acsr penguin (790-40.06) | LF | 137 | $3.00 | $3.29 |
| 300 | OH cond 2 7 aac iris (790-40.35) | LF | 5,492 | $2.22 | $1.40 |
| 301 | OH cond 1/0 7 aac poppy (790-40.36) | LF | 160 | $5.00 | $6.12 |
| 302 | OH cond 4/0 7 aac oxlip (790-40.39) | LF | 18,854 | $4.35 | $3.54 |
| 303 | OH cond 556.5 19 aac dahlia (790-40.46) | LF | 61,664 | $7.44 | $6.57 |
| 304 | UG pri cond 2 AL 15KV (790-41.01) | LF | 8 | $100.00 | $69.68 |
| 305 | UG pri cond 1/0 AL 15KV (790-41.03) | LF | 11 | $100.00 | $67.81 |
| 306 | UG sec cond 4/0 AL QPLX (790-41.58) | LF | 86 | $19.50 | $19.97 |
| 307 | 2IN dia PVC pipe (790-42.08) | LF | 35 | $30.00 | $10.49 |
| 308 | 4IN dia PVC pipe (790-42.10) | LF | 86 | $50.00 | $17.89 |
| 309 | __ duct bank @ __in-__in depth (790-42.26) | LF | 105 | $30.00 | $12.89 |
| 310 | Loadbreak elbow 200A 15KV (790-43.01) | EACH | 7 | $600.00 | $397.39 |
| 311 | Loadbreak junction 3 PT 200A 15KV (790-43.05) | EACH | 4 | $800.00 | $550.56 |
| 312 | Secondary pullbox large (790-43.46) | EACH | 1 | $2,700.00 | $2,266.37 |
| 313 | Secondary riser W/ 3IN conduit (790-43.51) | EACH | 1 | $1,300.00 | $815.73 |
| 314 | 1PH primary riser W/ 3IN conduit (790-43.53) | EACH | 1 | $3,200.00 | $2,092.96 |
| 315 | 1PH transformer (790-46.01) | EACH | 3 | $1,200.00 | $1,108.30 |
| 316 | 1PH transformer conv W/pole MTD fuse & LA (790-46.02) | EACH | 6 | $1,600.00 | $1,179.93 |
| 317 | 1PH fuse cutout xarm mount 15KV (790-60.01) | EACH | 20 | $650.00 | $446.55 |
| 318 | Lightning arrester arm MTD 9 KV (790-65.03) | EACH | 12 | $550.00 | $296.90 |
| 319 | Pole ground rod type (790-68.01) | EACH | 155 | $625.00 | $512.32 |
| 320 | SGL phase mounting bracket - fiberglass (790-68.13) | EACH | 2 | $400.00 | $387.81 |
| 321 | Pole top pin (790-69.22) | EACH | 1 | $350.00 | $299.55 |
| 322 | Stick pin (790-69.31) | EACH | 12 | $165.00 | $83.63 |
| 323 | Arm pin (790-69.32) | EACH | 151 | $140.00 | $81.81 |
| 324 | Street light on wood pole (790-70.01) | EACH | 61 | $1,620.00 | $1,648.60 |
| 325 | Remove wire (790-98.01) | LF | 99,975 | $1.45 | $1.32 |
| 326 | Remove poles (790-98.02) | EACH | 183 | $475.00 | $375.47 |
| 327 | Remove framing/associated apparatus (790-98.03) | EACH | 1,091 | $490.00 | $500.62 |
| 328 | Tree and brush removal off row (790-98.20) | LS | 1 | $65,000 | $10,012 |
| 329 | 2IN steel gas main (791-01.02) | LF | 20 | $400.00 | $637.12 |
| 330 | 6IN steel gas main (791-01.05) | LF | 20 | $1,200.00 | $1,392.03 |
| 331 | 2IN HDPE gas main (791-03.02) | LF | 1,660 | $130.00 | $218.44 |
| 332 | 4IN HDPE gas main (791-03.04) | LF | 1,835 | $160.00 | $229.15 |
| 333 | 6IN HDPE gas main (791-03.05) | LF | 9,654 | $200.00 | $277.34 |
| 334 | HDD <2IN PE pipe - unconsolidated (791-04.01) | LF | 2,003 | $140.00 | $182.04 |
| 335 | HDD 2IN PE pipe - unconsolidated (791-04.02) | LF | 540 | $160.00 | $203.45 |
| 336 | HDD 4IN PE pipe - unconsolidated (791-04.04) | LF | 115 | $200.00 | $364.07 |
| 337 | HDD 6IN PE pipe - unconsolidated (791-04.05) | LF | 2,764 | $225.00 | $380.13 |
| 338 | Connect to 2IN EX. PE main (791-06.02) | EACH | 11 | $3,500.00 | $8,298.66 |
| 339 | Connect to 4IN EX. PE main (791-06.03) | EACH | 3 | $5,000.00 | $8,566.36 |
| 340 | Connect to 2IN EX. STL main (791-06.10) | EACH | 1 | $6,500.00 | $21,416 |
| 341 | Connect to 6IN EX. STL main (791-06.12) | EACH | 1 | $18,000 | $44,973 |
| 342 | 2IN PE gas valve assembly (791-07.01) | EACH | 8 | $1,000.00 | $3,747.78 |
| 343 | 4IN PE gas valve assembly (791-07.02) | EACH | 5 | $1,500.00 | $4,550.88 |
| 344 | 6IN PE gas valve assembly (791-07.03) | EACH | 7 | $3,200.00 | $6,157.07 |
| 345 | 3/4IN service assembly (791-08.02) | EACH | 32 | $4,200.00 | $1,980.97 |
| 346 | 3/4IN PE service pipe (791-08.07) | LF | 3,097 | $55.00 | $74.96 |
| 347 | Retire gas main (791-10.10) | LS | 1 | $30,000 | $10,708 |
| 348 | Pole 35FT class 5 wood (793-01.08) | EACH | 17 | $1,465.00 | $2,429.59 |
| 349 | Anchor 3/4IN (793-01.40) | EACH | 152 | $777.00 | $640.75 |
| 350 | Guy wire 10M or 3/8IN (793-02.08) | EACH | 152 | $380.00 | $201.13 |
| 351 | Overhead guy wire (10M) (793-02.92) | EACH | 28 | $450.00 | $626.05 |
| 352 | Install guy guard (793-02.99) | EACH | 152 | $35.00 | $34.58 |
| 353 | 25 pair group aerial splice (793-03.01) | EACH | 20 | $200.00 | $218.49 |
| 354 | 10M strand (793-03.03) | LF | 48,095 | $3.33 | $3.87 |
| 355 | Relash/delash cable (793-04.01) | LF | 12,020 | $2.60 | $4.39 |
| 356 | Ready access closure (793-04.06) | EACH | 2 | $1,000.00 | $864.84 |
| 357 | Aerial splice closure (793-04.07) | EACH | 19 | $8,000.00 | $1,636.77 |
| 358 | Transfer aerial cable (793-04.08) | EACH | 86 | $288.00 | $400.51 |
| 359 | Underground splice closure (793-04.12) | EACH | 9 | $1,000.00 | $1,473.53 |
| 360 | 288 fiber(material only) (793-07.10) | LF | 14,535 | $3.33 | $2.60 |
| 361 | 12-96 fiber(installation only) (793-07.16) | LF | 22,665 | $2.88 | $3.14 |
| 362 | 108-144 fiber(installation only) (793-07.17) | LF | 24,335 | $2.88 | $3.14 |
| 363 | 288-432 fiber(installation only) (793-07.19) | LF | 14,535 | $2.88 | $4.21 |
| 364 | Fiber optic maintenance loop (793-07.23) | EACH | 69 | $288.00 | $292.11 |
| 365 | Single fiber optic cable splice (793-07.25) | EACH | 4,134 | $58.00 | $58.36 |
| 366 | Single fiber aerial drop (793-07.31) | LF | 45,320 | $2.00 | $3.36 |
| 367 | 72 fiber (material only) (793-07.51) | LF | 22,665 | $1.00 | $0.76 |
| 368 | Fiber distribution tap (793-07.80) | EACH | 7 | $522.00 | $1,151.14 |
| 369 | Fiber terminal (793-07.81) | EACH | 21 | $322.00 | $1,523.80 |
| 370 | Rearrange fiber jumper (793-07.82) | LF | 43,805 | $2.00 | $3.00 |
| 371 | Rearrange fiber drop (793-07.83) | LF | 24,285 | $2.00 | $3.00 |
| 372 | Test bare fiber (793-07.99) | EACH | 3,384 | $38.44 | $16.80 |
| 373 | Buried riser guard (793-11.13) | EACH | 8 | $222.00 | $324.24 |
| 374 | Rearrange existing splice case (793-11.50) | EACH | 12 | $600.00 | $471.09 |
| 375 | Rearrangement existing cable (793-12.02) | EACH | 2 | $500.00 | $1,580.97 |
| 376 | 25 pair group UG splice (793-13.06) | EACH | 181 | $144.00 | $252.75 |
| 377 | 1 duct formation @ 36IN depth (793-13.12) | LF | 1,260 | $65.00 | $52.74 |
| 378 | 2 duct formation @ 36IN depth (793-13.17) | LF | 8,090 | $65.00 | $54.55 |
| 379 | Concrete encasement per duct (793-14.02) | LF | 17,440 | $19.00 | $56.73 |
| 380 | MH precast (description) (793-14.07) | EACH | 19 | $18,000 | $11,238 |
| 381 | 4IN core drill into manhole (793-14.10) | EACH | 3 | $2,000.00 | $1,171.09 |
| 382 | 1 1/4IN innerduct (793-14.12) | LF | 29,520 | $5.55 | $2.56 |
| 383 | MH(retire/remove/gravel backfill) (793-16.01) | EACH | 7 | $5,555.00 | $3,009.19 |
| 384 | Relocate cable/inner duct from inside manhole (793-80.02) | LF | 490 | $16.00 | $5.85 |
| 385 | Remove aerial cable and wire (793-98.01) | LF | 153,296 | $1.70 | $1.99 |
| 386 | Remove crossconnect cabinet (793-98.02) | EACH | 1 | $1,500.00 | $2,049.39 |
| 387 | Remove carrier cabinet (793-98.03) | EACH | 1 | $1,500.00 | $2,049.39 |
| 388 | Remove poles all sizes (793-98.04) | EACH | 140 | $250.00 | $585.54 |
| 389 | Retire buried facilities in place (793-98.05) | LF | 5,170 | $10.00 | $1.76 |
| 390 | Remove pedestals (793-98.06) | EACH | 4 | $100.00 | $117.10 |
| 391 | Remove underground to overhead riser (793-98.07) | EACH | 23 | $100.00 | $175.66 |
| 392 | Remove anchor (any size) (793-98.08) | EACH | 190 | $100.00 | $105.39 |
| 393 | Remove down guy (793-98.09) | EACH | 196 | $100.00 | $58.56 |
| 394 | 6IN dip restrained joint water line (795-01.03) | LF | 1,850 | $125.00 | $167.53 |
| 395 | 6IN dip slip joint water line (795-01.04) | LF | 3,450 | $140.00 | $157.73 |
| 396 | 8IN dip restrained joint water line (795-01.05) | LF | 1,300 | $155.00 | $187.56 |
| 397 | 8IN dip slip joint water line (795-01.06) | LF | 4,000 | $155.00 | $174.91 |
| 398 | 12IN dip restrained joint water line (795-01.09) | LF | 1,650 | $190.00 | $224.01 |
| 399 | 12IN dip slip joint water line (795-01.10) | LF | 8,950 | $200.00 | $206.12 |
| 400 | 20IN dip restrained joint water line (795-01.17) | LF | 330 | $420.00 | $439.97 |
| 401 | 2IN PVC water line (795-03.02) | LF | 2,100 | $65.00 | $78.23 |
| 402 | Connect to 2IN water line (795-06.01) | EACH | 7 | $5,000.00 | $3,854.59 |
| 403 | Connect to 6IN water line (795-06.04) | EACH | 12 | $6,000.00 | $6,163.55 |
| 404 | Connect to 8IN water line (795-06.05) | EACH | 7 | $7,000.00 | $7,647.10 |
| 405 | Connect to 12IN water line (795-06.07) | EACH | 5 | $10,000 | $11,454 |
| 406 | Connect to 20IN water line (795-06.11) | EACH | 2 | $18,000 | $37,308 |
| 407 | Cut and cap 2IN water line (795-06.31) | EACH | 7 | $2,500.00 | $2,357.43 |
| 408 | Cut and cap 6IN water line (795-06.33) | EACH | 13 | $5,000.00 | $3,302.03 |
| 409 | Cut and cap 8IN water line (795-06.34) | EACH | 7 | $6,000.00 | $4,005.69 |
| 410 | Cut and cap 12IN water line (795-06.37) | EACH | 4 | $10,000 | $4,941.56 |
| 411 | Cut and cap 20IN water line (795-06.42) | EACH | 1 | $10,000 | $9,454.25 |
| 412 | 2IN gate valve assembly (795-08.01) | EACH | 13 | $4,500.00 | $2,811.81 |
| 413 | 6IN gate valve assembly (795-08.04) | EACH | 28 | $6,000.00 | $5,130.06 |
| 414 | 8IN gate valve assembly (795-08.05) | EACH | 24 | $7,500.00 | $6,224.60 |
| 415 | 12IN gate valve assembly (795-08.09) | EACH | 24 | $10,000 | $13,354 |
| 416 | 20IN butterfly valve assembly (795-08.17) | EACH | 1 | $19,000 | $38,908 |
| 417 | 1IN water service meter assembly (795-09.02) | EACH | 5 | $2,000.00 | $5,914.54 |
| 418 | 2IN water service meter assembly (795-09.04) | EACH | 2 | $6,000.00 | $9,848.54 |
| 419 | 3/4IN HDPE service pipe (795-09.14) | LF | 1,060 | $60.00 | $79.60 |
| 420 | 1IN HDPE service pipe (795-09.15) | LF | 160 | $100.00 | $79.94 |
| 421 | 2IN HDPE service pipe (795-09.17) | LF | 185 | $80.00 | $94.80 |
| 422 | Reconnect service assembly (795-09.51) | EACH | 41 | $2,000.00 | $4,430.73 |
| 423 | 5/8IN water service meter assembly (795-09.70) | EACH | 21 | $1,800.00 | $4,758.57 |
| 424 | 1IN auto air release valve assembly (795-10.03) | EACH | 1 | $6,500.00 | $5,861.46 |
| 425 | 2IN auto air release valve assembly (795-10.05) | EACH | 3 | $8,000.00 | $9,973.29 |
| 426 | Blow-off assembly (795-11.01) | EACH | 3 | $4,000.00 | $10,476 |
| 427 | Fire hydrant assembly (795-11.02) | EACH | 21 | $11,000 | $15,223 |
| 428 | Remove fire hydrant (795-12.01) | EACH | 15 | $2,000.00 | $3,153.44 |
| 429 | Removal of existing line (795-12.02) | LS | 1 | $120,000 | $74,440 |
| 430 | Pipe grouting (795-12.03) | LS | 1 | $250,000 | $131,695 |
| 431 | Remove blow-off assembly (795-12.05) | EACH | 3 | $2,000.00 | $2,685.65 |
| 432 | Concrete encasement (795-14.05) | LF | 800 | $500.00 | $236.49 |
| 433 | Flowable fill excavatable encasement (795-14.16) | LF | 6,360 | $300.00 | $49.93 |
| 434 | 12IN steel casing pipe open cut method (795-15.02) | LF | 280 | $180.00 | $291.95 |
| 435 | 24IN steel casing pipe open cut method (795-15.07) | LF | 230 | $250.00 | $524.72 |
| 436 | 16IN steel casing pipe open cut method (795-15.25) | LF | 85 | $240.00 | $369.08 |
| 437 | 8IN dip gravity sewer 0FT-6FT depth (797-05.01) | LF | 3,712 | $155.00 | $359.10 |
| 438 | 8IN dip gravity sewer 6FT-12FT depth (797-05.02) | LF | 2,852 | $200.00 | $416.87 |
| 439 | 8IN dip gravity sewer 12FT-18FT depth (797-05.03) | LF | 147 | $265.00 | $567.31 |
| 440 | 8IN dip gravity sewer >18FT depth (797-05.04) | LF | 37 | $400.00 | $950.09 |
| 441 | 8IN PVC gravity sewer 0FT-6FT depth (797-05.51) | LF | 2,520 | $125.00 | $275.48 |
| 442 | 8IN PVC gravity sewer 6FT-12FT depth (797-05.52) | LF | 3,792 | $165.00 | $345.55 |
| 443 | 8IN PVC gravity sewer 12FT-18FT depth (797-05.53) | LF | 609 | $245.00 | $928.97 |
| 444 | 48IN manhole 4FT-6FT depth (797-07.02) | EACH | 23 | $10,000 | $8,517.20 |
| 445 | 48IN manhole 6FT-8FT depth (797-07.03) | EACH | 27 | $14,000 | $9,551.56 |
| 446 | 48IN manhole 8FT-10FT depth (797-07.04) | EACH | 17 | $16,000 | $9,885.95 |
| 447 | 48IN manhole 10FT-12FT depth (797-07.05) | EACH | 9 | $18,000 | $14,441 |
| 448 | 48IN manhole 12FT-14FT depth (797-07.06) | EACH | 6 | $20,000 | $18,153 |
| 449 | 48IN manhole 14FT-16FT depth (797-07.07) | EACH | 3 | $24,000 | $25,583 |
| 450 | 48IN manhole 16FT-20FT depth (797-07.08) | EACH | 5 | $30,000 | $32,412 |
| 451 | Manhole drop connection assembly (797-07.56) | EACH | 22 | $5,000.00 | $10,121 |
| 452 | Adjust existing manhole (797-07.60) | EACH | 1 | $5,000.00 | $5,273.34 |
| 453 | Traffic rated frames and covers (797-07.75) | EACH | 53 | $1,500.00 | $1,793.27 |
| 454 | Remove sewer manhole (797-07.80) | EACH | 44 | $2,500.00 | $1,960.55 |
| 455 | 6IN PVC pipe for service lateral (797-08.05) | LF | 1,350 | $95.00 | $172.81 |
| 456 | 6IN clean out assembly (797-08.08) | EACH | 55 | $1,500.00 | $2,617.41 |
| 457 | Connect 6IN lateral to sewer line (797-10.06) | EACH | 55 | $1,500.00 | $3,825.96 |
| 458 | Connect EX. 8IN sewer to new manhole (797-10.09) | EACH | 27 | $10,000 | $3,398.34 |
| 459 | Pump station retire in place (797-10.36) | LS | 1 | $20,000 | $11,557 |
| 460 | Retirein place 48IN manhole (797-11.25) | EACH | 7 | $2,500.00 | $3,501.84 |
| 461 | Retirein place existing sewer 8IN-14IN (797-11.31) | LF | 11,420 | $25.00 | $20.82 |
| 462 | By-pass pumping (797-11.38) | LS | 1 | $150,000 | $328,828 |
| 463 | Fiber optic cable enclosure (798-05.02) | EACH | 3 | $2,400.00 | $1,241.84 |
| 464 | Fiber optic cable splice (798-05.03) | EACH | 46 | $450.00 | $241.29 |
| 465 | 3/8IN ehs steel strand (798-05.06) | LF | 24,316 | $8.15 | $4.70 |
| 466 | Trunk/feeder cable .565 (798-05.08) | LF | 34,199 | $7.65 | $4.33 |
| 467 | Trunk/feeder cable .750 (798-05.13) | LF | 2,603 | $7.65 | $4.33 |
| 468 | Trunk/feeder cable 1.00 (798-05.17) | LF | 13,902 | $7.65 | $4.33 |
| 469 | Drop cable 22 AWG (798-05.22) | LF | 2,608 | $8.15 | $4.62 |
| 470 | Communication assembly (tap) (798-05.26) | EACH | 50 | $1,111.00 | $601.43 |
| 471 | Communication assembly (bond) (798-05.27) | EACH | 52 | $750.00 | $338.11 |
| 472 | Communication assembly (CSC) (798-05.29) | EACH | 61 | $750.00 | $340.47 |
| 473 | Communication assembly (DC) (798-05.30) | EACH | 18 | $1,111.00 | $601.42 |
| 474 | Communication assembly (dde) (798-05.32) | EACH | 38 | $1,220.00 | $665.67 |
| 475 | Communication assembly (DE) (798-05.33) | EACH | 56 | $750.00 | $340.06 |
| 476 | Communication assembly (E1-2) (798-05.34) | EACH | 111 | $450.00 | $202.14 |
| 477 | Communication assembly (E2-2) (798-05.35) | EACH | 25 | $1,300.00 | $629.40 |
| 478 | Communication assembly (F2&F3) (798-05.37) | EACH | 111 | $1,300.00 | $642.85 |
| 479 | Communication assembly (split) (798-05.48) | EACH | 12 | $1,500.00 | $601.42 |
| 480 | Communication assembly (lxtap) (798-05.50) | EACH | 2 | $1,700.00 | $895.14 |
| 481 | Communication assy(amptap) (798-05.51) | EACH | 16 | $1,700.00 | $895.14 |
| 482 | Communication assembly (loop) (798-05.52) | EACH | 42 | $800.00 | $293.07 |
| 483 | Communication assembly (splice) (798-05.53) | EACH | 15 | $1,400.00 | $601.42 |
| 484 | Fiber optic cable (4F) (798-06.02) | LF | 561 | $8.88 | $4.86 |
| 485 | Fiber optic cable (6F) (798-06.03) | LF | 2,017 | $8.88 | $4.86 |
| 486 | Fiber optic cable (12F) (798-06.04) | LF | 2,895 | $8.88 | $4.86 |
| 487 | Fiber optic cable (20F) (798-06.05) | LF | 2,167 | $9.40 | $5.03 |
| 488 | Fiber optic cable (44 F) (798-06.07) | LF | 14,841 | $9.40 | $5.03 |
| 489 | Fiber optic cable (72F) (798-06.08) | LF | 1,683 | $9.80 | $5.22 |
| 490 | Fiber optic cable (96F) (798-06.11) | LF | 14,841 | $9.80 | $5.50 |
| 491 | Fiber optic cable (8F) (798-06.15) | LF | 361 | $8.88 | $4.86 |
| 492 | Fiber optic cable (36F) (798-06.16) | LF | 1,122 | $9.40 | $5.03 |
| 493 | Remove steel strand (798-09.01) | LF | 24,838 | $4.00 | $2.00 |
| 494 | Remove aerial cable/terminals (798-09.02) | LF | 82,295 | $3.55 | $2.00 |
| 495 | Remove poles, guys, anchors (798-09.03) | EACH | 319 | $400.00 | $164.49 |
| 496 | Remove strand pole framing (798-09.08) | EACH | 223 | $250.00 | $105.74 |
| 497 | Power supply (798-10.10) | EACH | 1 | $25,000 | $12,761 |
| 498 | Amplifier assembly (798-10.15) | EACH | 13 | $5,000.00 | $895.14 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of December 5, 2025. Compiled by Mirage Metrics.