TDOT contract CN261011 bid tabulation

The new construction on the s.r. 449 extension (veteran's boulevard) from u.s. 411 (s.r. 35) to near robert henderson road, and miscellaneous improvements on u.s. 411 (s.r. 35) from s.r. 448 to eastgate road. Let by Tennessee DOT on February 6, 2026, Sevier County. 1 bid received; low bid $25,993,101 by Charles Blalock & Sons, Inc..

Owner
Tennessee DOT
Letting
06 FEB 2026
Pay items
378
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Charles Blalock & Sons, Inc.$25,993,101Low
TDOT contract CN261011: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Charles Blalock & Sons, Inc.
1Construction stakes, lines and grades (105-01)LS1$175,000
2Trainee (109-10.01)HR4,420$0.80
3Clearing and grubbing (201-01)LS1$850,000
4Removal of structures and obstructions (202-01)LS1$10,098
5Removal of structures & obstructions (3,075 SF of concrete paving) (202-01.56)LS1$11,180
6Removal of buildings (tract no. 9) (202-06.01)LS1$4,077.21
7Removal of buildings (tract no. 10) (202-06.02)LS1$3,593.46
8Road & drainage excavation (unclassified) (203-01)CY14,063$15.00
9Road & drainage excavation (stream mitigation) (203-01.13)CY2,142$34.54
10Borrow excavation (graded solid rock) (203-02.01)TON1,400$65.00
11Borrow excavation (unclassified) (203-03)CY92,939$12.00
12Placing and spreading topsoil (203-04)CY7,665$3.00
13Water (203-06)MG318$3.00
14Furnishing & spreading topsoil (203-07)CY228$78.36
15Channel substrate (203-20.01)CY114$175.00
16Foundation fill material (204-08)CY95$98.44
17Backfill material (flowable fill) (204-08.01)CY128$462.17
1812" temporary slope drain (209-02.05)LF307$15.05
19Filter sock (12 inch) (209-03.21)LF172$5.78
20Stream mitigation-log vanes (209-03.34)LF40$475.00
21Stream mitigation cross vane structure (209-03.37)EACH2$8,200.00
22Stream mitigation -J -hook (209-03.38)EACH8$6,100.00
23Stream mitigation - rock vane (209-03.60)EACH4$4,631.32
24Stream mitigation - root wad (209-03.62)EACH4$4,000.00
25Protected area marker (white with decal) (209-03.99)EACH12$265.15
26Sediment removal (209-05)CY946$23.93
27Temporary silt fence (with backing) (209-08.02)LF7,617$5.25
28Temporary silt fence (without backing) (209-08.03)LF426$4.20
29Rock check dam (209-08.07)EACH8$602.76
30Enhanced rock check dam (209-08.08)EACH24$1,005.13
31Filter sock check dam (209-08.09)EACH8$682.50
32Sandbags (209-09.01)BAG100$10.50
33Sediment filter bag (15' X 15') (209-09.03)EACH2$2,562.81
34Curb inlet protection (type 4) (209-09.43)EACH112$312.90
35Temporary dewatering structure (209-10.01)CY298$38.97
36Polyethylene sheeting (6 mil. minimum) (209-20.03)SY71$24.27
37Catch basin protection (type D) (209-40.33)EACH70$393.75
38Catch basin filter assembly(type 2) (209-40.42)EACH21$813.75
39Catch basin filter assembly(type 3) (209-40.43)EACH13$813.75
40Catch basin filter assembly(type 4) (209-40.44)EACH7$934.50
41Catch basin filter assembly(type 5) (209-40.45)EACH7$1,575.00
42Catch basin filter assembly(type 7) (209-40.47)EACH1$1,050.00
43Temporary stream diversion (with pump around) (209-65.01)LS1$30,116
44Temporary in stream diversion (209-65.04)LF147$483.46
45Mineral aggregate, type A base, grading D (303-01)TON21,312$58.34
46Granular backfill (roadway) (303-01.01)TON855$42.66
47Mineral aggregate (size 57) (303-10.01)TON223$53.28
48Mineral aggregate (see standard drawing STD-10-2) (303-10.04)TON1,782$53.28
49Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON2,761$180.66
50Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON3,407$219.24
51Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21)TON2,807$191.56
52Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01)TON1,406$203.96
53Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08)TON596$208.21
54Bituminous material for prime coat (PC) (402-01)TON36$2,469.71
55Aggregate for cover material (PC) (402-02)TON143$50.00
56Bituminous material for tack coat (TC) (403-01)TON156$1,500.00
57Saw cutting asphalt pavement (407-20.05)LF4,935$3.68
58Acs mix (PG64-22) grading E shoulder (411-01.07)TON179$249.53
59Acs mix(PG64-22) grading D (411-01.10)TON2,143$257.09
60Acs mix(PG70-22) grading D (411-02.10)TON1,585$263.09
61Cold planing bituminous pavement (415-01.01)TON1,224$39.00
62Cold planing bituminous pavement (415-01.02)SY9,772$7.95
63Class A concrete (roadway) (604-01.01)CY259$1,509.17
64Steel bar reinforcement (roadway) (604-01.02)LB49,766$1.42
65Applied texture finish (new structures) (604-04.01)SY4,123$16.07
66Retaining wall (retaining wall no. 1) (604-07.01)SF6,765$200.00
6718" concrete pipe culvert (class III) (607-03.02)LF2,854$125.42
6818" concrete pipe culvert (class IV) (607-03.03)LF42$140.76
6924" concrete pipe culvert (class III) (607-05.02)LF512$166.88
7030" concrete pipe culvert (class III) (607-06.02)LF29$232.21
7136" concrete pipe culvert (class III) (607-07.02)LF740$250.86
7236" concrete pipe culvert (class IV) (607-07.03)LF22$335.72
7342" concrete pipe culvert (class III) (607-08.02)LF182$360.83
7418" corrugated metal pipe culvert (607-37.02)LF23$181.95
7518" pipe culvert (side drain) (607-39.02)LF279$111.09
7618" slotted drain pipe (607-45.02)LF30$445.52
77Manholes, > 4' - 8' depth (611-01.02)EACH4$7,685.17
78Manholes, > 8' - 12' depth (611-01.03)EACH1$8,271.21
79Manholes, > 16' - 20' depth (611-01.05)EACH1$15,245
80Class A concrete (pipe endwalls) (611-07.01)CY11.22$2,504.92
81Steel bar reinforcement (pipe endwalls) (611-07.02)LB714$4.51
8218IN endwall (side drain) (611-07.31)EACH7$3,332.81
83Rework catchbasin (611-09.02)EACH30$1,799.55
84Capping existing catchbasin (611-09.03)EACH21$2,875.87
85Catch basins, type 12, 0' - 4' depth (611-12.01)EACH14$4,461.65
86Catch basins, type 12, > 4' - 8' depth (611-12.02)EACH20$5,351.67
87Catch basins, type 12, > 8' - 12' depth (611-12.03)EACH7$11,554
88Catch basins, type 12, > 12' - 16' depth (611-12.04)EACH8$14,119
89Catch basins, type 12, > 20' - 24' depth (611-12.06)EACH2$16,287
90Catch basins, type 12, > 24' - 28' depth (611-12.07)EACH1$16,663
91Catch basins, type 14, > 4' - 8' depth (611-14.02)EACH4$14,017
92Catch basins, type 14, > 12' - 16' depth (611-14.04)EACH1$22,812
93Catch basins, type 25, 0' - 4' depth (611-25.01)EACH1$5,960.82
94Catch basins, type 25, > 4' - 8' depth (611-25.02)EACH3$6,802.26
95Catch basins, type 25, > 12' - 16' depth (611-25.04)EACH1$12,644
96Catch basins, type 26, > 4' - 8' depth (611-26.02)EACH1$13,433
97Catch basins, type 40, > 4' - 8' depth (611-40.02)EACH1$13,755
98Catch basins, type 42, 0' - 4' depth (611-42.01)EACH4$7,082.77
99Catch basins, type 42, > 4' - 8' depth (611-42.02)EACH3$12,068
100Catch basins, type 42, > 8' - 12' depth (611-42.03)EACH1$10,516
101Catch basins, type 43, > 4' - 8' depth (611-43.02)EACH1$19,984
102Junction structure, 72IN round,> (9.98 FT depth) (611-63.21)EACH1$10,227
103Concrete parapet with structural tubing (620-05)LF1,124$292.31
104Concrete sidewalk (4 ") (701-01.01)SF28,854$13.50
105Concrete driveway (701-02)SF8,112$12.82
106Concrete curb ramp (701-02.03)SF3,656$22.89
107Concrete median pavement (701-03)CY73$603.79
108Concrete curb (702-01)CY224$538.45
109Concrete combined curb & gutter (702-03)CY640$626.53
110GR terminaltrailing end (type 13) MASH TL-3 (705-06.10)EACH1$1,706.25
111GR terminal (in-inline) MASH TL-3 (705-06.11)EACH1$1,653.75
112Tangent energy absorbing term MASH TL-3 (705-06.20)EACH3$3,438.75
113Thrie beam bridge transition MASH TL-3 (705-06.25)EACH3$3,622.50
114Thrie beam 38IN vehicle & pedestrian safety rail MASH TL-3 (705-06.27)LF1,066$55.13
115Portable impact attenuator NCHRP350 TL-2 (705-08.10)EACH4$6,562.50
116Michigan and modified michigan end shoe (706-10.80)EACH1$131.25
117High-visibility construction fence (707-08.11)LF3,071$2.63
118Bike/pedestrian box tube safety rail (707-16.01)LF260$152.25
119Machined rip-rap (class A-3) (709-05.05)TON100$61.00
120Machined rip-rap (class A-1) (709-05.06)TON437$61.00
121Machined rip-rap (class B) (709-05.08)TON2,372$63.37
122Rock riffles (709-05.81)LS1$94,156
123Aggregate underdrains (with pipe) (710-02)LF11,302$13.13
124Traffic control (712-01)LS1$336,520
125Interconnected portable barrier rail (712-02.02)LF458$30.60
126Flexible drums (channelizing) (712-04.01)EACH1,303$42.42
127Warning lights (type A) (712-05.01)EACH48$26.52
128Warning lights (type C) (712-05.03)EACH8$26.52
129Signs (construction) (712-06)SF831$7.42
130Temporary barricades (type III) (712-07.03)LF751$2.12
131Arrow board (type C) (712-08.03)EACH2$1,909.09
132Mobile message sign unit W/attenuator (712-08.10)HR2$127.27
133Class A concrete (foundation for sign supports) (713-01.01)CY2$715.91
134Steel bar reinforcement(foundation for sign supports) (713-01.02)LB501$3.53
135Concrete barrier/parapet delineator (713-02.26)EACH12$12.73
136Steel I-beams & WF-beams(breakaway) sign support (713-06)LB884$9.55
137"U" section steel posts (713-11.01)LB75$5.14
138Perforated/knockout square tube post (713-11.02)LB391$5.25
139P post slip base (713-11.21)EACH11$530.30
140U post slip base (713-11.22)EACH2$546.21
141Square post slip base (713-11.24)EACH10$530.30
142Flat sheet aluminum signs (0.080" thick) (713-13.02)SF38$14.85
143Flat sheet aluminum signs (0.100" thick) (713-13.03)SF137$16.44
144Street name sign (rigid 0.100IN thick (713-14.21)SF60$68.25
145Changeable message sign unit (713-16.01)EACH2$9,333.34
146Dead end sign and support (713-16.06)EACH3$265.15
147End of roadway sign and support (713-16.07)EACH4$265.15
148Signs (protected area sign) (713-16.20)EACH12$265.15
149Signs (removal of left tutrn yield on flashing arrow on mast arm) (713-16.21)EACH1$262.50
150Signs (new street backlit box signage on mast arm middlecreek at SR 35) (713-16.22)EACH2$4,725.00
151Signs (adjust and relocate street backlit box signage on mast arm vet at SR 35) (713-16.23)EACH1$1,050.00
152Remove and replace sign (overhead mounted to mast arm) (713-16.50)EACH1$525.00
153Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH95$42.00
154Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22)EACH300$42.00
155Plastic pavement marking (cross-walk) (716-02.03)LF111$9.19
156Plastic pavement marking(channelization striping) (716-02.04)SY175$26.25
157Plastic pavement marking (stop line) (716-02.05)LF579$10.50
158Plastic pavement marking (turn lane arrow) (716-02.06)EACH49$131.25
159Plastic pavement marking (8" dotted line) (716-02.08)LF2,315$1.31
160Plastic pavement marking (longitudinal cross-walk) (716-02.09)LF138$29.40
161Plastic pavement marking (8IN line) (716-02.12)LM1$8,662.50
162Plastic word pavement marking (only) (716-03.01)EACH3$236.25
163Plastic pavement marking (straight-turn arrow) (716-04.01)EACH3$183.75
164Plastic pavement marking (straight arrow) (716-04.05)EACH7$157.50
165Plastic pavement marking (lane reduction arrow) (716-04.14)EACH1$236.25
166Painted pavement marking (4" line) (716-05.01)LM3.80$1,312.50
167Painted pavement marking (8" barrier line) (716-05.02)LF7,540$0.32
168Painted pavement marking (cross-walk) (716-05.03)LF222$5.25
169Painted pavement marking (channelization striping) (716-05.04)SY290$10.50
170Painted pavement marking (stop line) (716-05.05)LF927$5.25
171Painted pavement marking (turn lane arrow) (716-05.06)EACH120$52.50
172Painted pavement marking(straight-turn arrow) (716-05.09)EACH6$78.75
173Painted pavement marking(straight arrow) (716-05.11)EACH8$52.50
174Painted pavement marking (6" line) (716-05.20)LM6.20$1,312.50
175Painted pavement markings(8" line) (716-05.49)LM1.80$1,575.00
176Enhanced flatline thermo PVMT MRKNG (4IN line) (716-12.01)LM0.90$6,037.50
177Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM3$6,825.00
178Mobilization (717-01)LS1$975,000
179Field office (type 2) (722-01.02)LS1$6,450.00
180Pull box (type D) (725-20.44)EACH4$5,250.00
1812IN conduit (725-22.71)LF250$13.20
1822IN conduit bored (725-22.72)LF1,020$11.06
1834IN conduit (725-22.83)LF2,200$18.89
184Remove & relocate existing traffic signal equipment (730-01.01)EACH2$525.00
185Removal of signal equipment (730-01.02)EACH1$13,125
186Modification of existing traffic signal equipment (730-01.03)EACH1$5,250.00
187Signal head assembly (130 A3 with backplate) (730-02.03)EACH6$1,470.00
188Signal head assembly (130 with backplate) (730-02.09)EACH21$1,365.00
189Signal head assembly (130 A2) (730-02.10)EACH1$1,470.00
190Signal head assembly (140 A1 with backplate) (730-02.14)EACH1$1,680.00
191Signal head assembly (150 A2H with backplate) (730-02.17)EACH2$2,100.00
192Signal head modification (relocation) (730-02.41)EACH1$525.00
193Signal head modification (change black backplate to yellow) (730-02.42)EACH10$525.00
194Signal head assembly (140 A4F with backplate) (730-02.59)EACH4$1,680.00
195Install pull box (type B) (730-03.21)EACH9$2,625.00
196Electrical service connection (730-05.01)EACH2$3,675.00
197Signal cable - 5 conductor (730-08.02)LF3,523$3.12
198Signal cable - 7 conductor (730-08.03)LF2,734$3.62
199Signal cable - 9 conductor (730-08.04)LF1,355$4.34
200Signal cable - 12 conductor (730-08.05)LF945$5.17
201Conduit 2" diameter (PVC schedule 40) (730-12.02)LF261$13.42
202Conduit 2" diameter (directional bore) (730-12.23)LF3,022$5.90
203Vehicle detector (radar - advance) (730-13.13)EACH3$6,825.00
204Vehicle detector (360-degree camera) (730-13.14)EACH3$26,250
205Cabinet (atc) (730-15.07)EACH2$42,000
206Controller (atc) (730-16.04)EACH2$9,712.50
207Pedestal pole (type A) (730-23.28)EACH1$5,250.00
208Pedestal pole (type B) (730-23.29)EACH2$6,825.00
209Pedestal pole (10FT pedestrian type A) (730-23.30)EACH4$5,250.00
210Pedestal pole (relocate existing pushbuttons, ped heads & signs new foundations) (730-23.31)EACH3$4,725.00
211Cantilever signal support (1 arm @ 45') (730-23.88)EACH1$42,382
212Cantilever signal support (1 arm @ 60') (730-25.11)EACH1$50,782
213Cantilever signal support (1 arm @ 65') (730-25.13)EACH1$50,782
214Cantilever signal support (1 arm @ 70') (730-25.14)EACH1$56,557
215Cantilever signal support (1 arm @ 75') (730-25.15)EACH1$61,282
216Cantilever signal support (1 arm @ 80') (730-25.16)EACH2$60,232
217Cantilever signal support (1 arm @ 85') (730-25.17)EACH1$63,382
218Countdown ped SGNL head W/audible pushbutton & 15IN sign (730-26.11)EACH10$2,625.00
219Battery back-UP system (730-35.06)EACH2$10,500
220Geogrid reinforcement type 2 (740-07.04)SY4,227$9.25
221Geotextile (type III)(erosion control) (740-10.03)SY2,306$2.70
222Geotextile (type IV)(stabilization) (740-10.04)SY1,520$3.86
223Temporary sediment tube 8IN (740-11.01)LF10,167$3.41
224Seeding (with mulch) (801-01)UNIT191$47.93
225Temporary seeding (with mulch) (801-01.07)UNIT124$38.01
226Grass seed mix (ripzn/FLPL) (801-01.34)UNIT51$68.99
227Natve seed MX final stablizatn of slopes (801-01.38)UNIT7$84.00
228Seeding (without mulch) (801-02)UNIT31$39.90
229Water (seeding & sodding) (801-03)MG97$131.25
230Seed (supplemental application) (801-07)LB7$26.25
231Fertilizer (supplemental application) (801-08)TON1$2,100.00
232Cuttings: salix sericea (18IN-24IN) (802-02.31)EACH75$4.46
233Cuttings: sambucus canadensis (18IN-24IN) (802-02.33)EACH75$7.26
234Cuttings: cephalanthus occidentalis (18IN-24IN) (802-02.35)EACH75$5.64
235Cuttings: cornus amomum (24-48IN) (802-02.42)EACH75$5.57
236Acer rubrum (red maple seedlng B.R.) (802-12.02)EACH62$10.50
237Carya ovata (shagbark hickory seedlng B.R.) (802-12.09)EACH63$10.50
238Cornus florida (flowering dogwood seedlng B.R.) (802-12.12)EACH62$10.50
239Diospyros virginiana (persimmon seedlng B.R.) (802-12.14)EACH63$10.50
240Liriodendron tulipifera (tulip poplar seedlng B.R.) (802-12.19)EACH62$10.50
241Quercus falcata (southern red oak seedlng B.R.) (802-12.31)EACH62$10.50
242Quercus phellos (willow oak seedlng B.R.) (802-12.38)EACH62$10.50
243Hamamelis virginiana (american witchhazel seedling B.R.) (802-12.63)EACH57$10.50
244Calycanthus floridus (sweetshrub SDLNG bare root) (802-13.52)EACH58$10.50
245Lindera benzoin (spicebush SDLNG bare root) (802-13.59)EACH58$10.50
246Aronia melanocarpa (BLCK chokeberry SDLNG B.R.) (802-13.61)EACH58$10.50
247Ilex verticillata (CMMN winterberry SDLNG B.R.) (802-13.62)EACH58$10.50
248Amorpha fruticosa (indigobush sdling B.R.) (802-13.65)EACH57$10.50
249Sodding (new sod) (803-01)SY8,469$6.83
250Turf reinforcement mat (class I) (805-01.01)SY708$4.73
251Erosion control blanket (type I) (805-12.01)SY7,006$1.89
252700 gram coir fiber erosion blanket (805-12.08)SY337$4.20
253Project mowing (806-02.03)CYCL9$2,393.45
254Removal of structures (bridge location no. 78-nfa 2488-00.21) (202-04.01)LS1$169,697
255Dry excavation (bridges) (204-02.01)CY172$126.54
256Wet excavation (bridges) (204-03.01)CY339$133.42
257Rock excavation (bridges) (204-04.01)CY50$342.14
258Rock drilling (bridges) (204-05)LF24$200.00
259Foundation preparation(see plans) (204-10.01)LS1$269,000
260Foundation preparation(see plans) (204-10.02)LS1$269,000
261Core drilling for piles(rock) (204-14)LF210$273.00
262Core drilling for piles(soil) (204-15)LF674$52.50
263Granular backfill (bridges) (303-01.02)TON54$55.05
264Epoxy coated reinforcing steel (604-02.03)LB209,144$1.60
265Class A concrete (bridges) (604-03.01)CY684$1,450.13
266Steel bar reinforcement (bridges) (604-03.02)LB147,321$1.38
267Pavement @ bridge ends (604-03.04)SY426$346.85
268Class DS concrete (604-03.32)CY975$1,219.77
269Three star state emblem (604-04.41)EACH3$935.01
270Bridge deck grooving (mechanical) (604-05.31)SY2,171$3.62
271Steel piles (10 inch) (606-02.03)LF845$75.93
272Bridge deck drains (610-10.40)LS1$46,367
273Prestressed concrete bulb tee beam (6" web)(BT-72) (615-01.12)LF2,933$505.84
2746" perforated pipe with vertical drain system (710-09.01)LF225$8.48
2756" pipe underdrain (710-09.02)LF24$24.44
276Structural lighting (see plans) (714-01.01)LS1$16,863
277Pole 50FT class 2 metal (790-05.06)EACH3$6,275.96
278Pole 55FT class H1 metal (790-06.07)EACH1$9,207.03
279Pole 60FT class H1 metal (790-07.07)EACH4$10,301
280Pole 65FT class H1 metal (790-08.14)EACH5$11,334
281Pole(see plans) (790-20.01)EACH1$12,893
2823PH crossarm SGL LRG cond 15KV (790-25.08)EACH5$2,445.50
2833PH crossarm DBL prim support 15KV (790-25.10)EACH2$2,729.54
2843PH crossarm deadend SGL 15KV (790-25.21)EACH4$2,020.61
2853PH crossarm dde 15KV (790-25.23)EACH7$2,683.26
286Secondary assemblies LRG angle (790-30.02)EACH1$103.07
287Secondary conductor 2 AL triplex (790-30.13)LF136$5.76
288Down guy - through bolt type (790-32.01)EACH30$565.75
289Down guy - through bolt type heavy duty (790-32.02)EACH5$615.35
290Anchor (32,000LB) (790-32.25)EACH20$792.98
291OH cond 1/0 6/1 acsr raven (790-40.03)LF168$2.92
292OH cond 4/0 6/1 acsr penguin (790-40.06)LF2,640$4.31
293OH cond 795 37 aac arbutus (790-40.49)LF9,744$9.07
294UG pri cond 1/0 AL 15KV (790-41.03)LF612$16.63
2954IN dia PVC pipe (790-42.10)LF44$15.37
296Loadbreak junction 4 PT 200A 15KV (790-43.06)EACH3$1,041.80
297Deadbreak elbow 600A 15KV (790-43.13)EACH6$585.54
298Primary pullbox (790-43.47)EACH1$1,482.37
2991PH primary riser W/ 3IN conduit (790-43.53)EACH1$3,094.15
3003PH primary riser W/ 3IN conduit (790-43.57)EACH1$4,351.84
3011PH transformer conv W/pole MTD fuse & LA (790-46.02)EACH1$1,370.04
302Remove wire (790-98.01)LF6,309$2.24
303Remove poles (790-98.02)EACH7$495.57
304Remove framing/associated apparatus (790-98.03)EACH45$371.68
3054IN HDPE gas main (791-03.04)LF150$63.00
3068IN HDPE gas main (791-03.06)LF2,675$131.25
3078IN steel casing open cut (791-05.53)LF120$236.25
30816IN steel casing open cut (791-05.58)LF190$367.50
309Connect to 6IN EX. PE main (791-06.04)EACH3$6,300.00
3106IN PE gas valve assembly (791-07.03)EACH2$2,362.50
3118IN PE gas valve assembly (791-07.04)EACH7$4,620.00
312PE gas fittings (791-07.40)LB1,000$0.11
313Reconnect service assembly (791-08.40)EACH2$1,890.00
314Bridge hanger system and pipe (791-09.01)LS1$311,638
315Cathodic protection junction box (791-09.21)EACH2$2,625.00
316Retire in place 6IN serv cut & plug (791-10.06)EACH4$2,100.00
317Anchor 1IN (793-01.41)EACH3$761.25
318Guy wire 10M or 3/8IN (793-02.08)EACH3$488.25
319Install guy guard (793-02.99)EACH3$215.25
32010M strand (793-03.03)LF965$3.44
321Underground to overhead riser (793-14.26)EACH1$3,994.90
32212IN dip restrained joint water line (795-01.09)LF890$198.88
32312IN dip slip joint water line (795-01.10)LF1,620$160.94
324Bore/jack 24IN steel casing pipe-uncon. (795-05.68)LF50$942.48
325Bore/jack 24IN steel casing pipe-rock. (795-05.82)LF50$942.48
326Connect to 2IN water line (795-06.01)EACH1$6,055.18
327Connect to 6IN water line (795-06.04)EACH2$8,713.68
328Connect to 8IN water line (795-06.05)EACH1$8,493.61
329Connect to 10IN water line (795-06.06)EACH3$14,497
330Cut/cap existing lines (all sizes) (795-06.30)EACH2$4,467.28
3312IN gate valve assembly (795-08.01)EACH1$3,675.87
3326IN gate valve assembly (795-08.04)EACH1$4,654.17
33312IN gate valve assembly (795-08.09)EACH5$10,209
334Relocate/reconnect service assembly (795-09.09)EACH1$4,330.76
335(TI) of 3IN PVC casing for service pipe-uncon (795-09.35)LF60$42.25
3363/4IN service pipe (795-09.37)LF50$43.05
337Reconnect service assembly (795-09.51)EACH4$1,987.13
3382IN auto air release valve assembly (795-10.05)EACH2$4,825.48
339Blow-off assembly (795-11.01)EACH3$3,666.25
340Fire hydrant assembly (795-11.02)EACH1$12,349
341Reconnect fire hydrant (795-11.03)EACH1$5,407.36
342Retire in place existing water main (795-11.12)LF700$204.01
343Remove fire hydrant (795-12.01)EACH1$1,562.41
344DI fittings (795-13.01)LB3,200$11.01
345Bridge hanger system (795-13.04)LS1$223,485
34624IN steel casing pipe open cut method (795-15.07)LF75$617.24
3472IN PVC force main (797-03.04)LF171$66.74
3488IN PVC force main (797-03.07)LF1,780$125.00
3498IN PVC gravity sewer 6FT-12FT depth (797-05.52)LF30$210.00
3508IN PVC gravity sewer 12FT-18FT depth (797-05.53)LF30$210.00
35110IN PVC gravity sewer 6FT-12FT depth (797-05.56)LF600$125.00
35210IN PVC gravity sewer 12FT-18FT depth (797-05.57)LF215$287.00
35324IN PVC gravity sewer 12FT-18FT depth (797-05.73)LF90$480.25
35424IN PVC gravity sewer >18FT depth (797-05.74)LF205$606.46
355__in PVC gravity sewer 6FT-12FT depth (797-05.80)LF40$140.14
356__in PVC gravity sewer 12FT-18FT depth (797-05.81)LF40$400.51
357Bore/jack 16IN steel casing pipe-uncon. (797-06.64)LF25$992.46
358Bore/jack 16IN steel casing pipe-rock. (797-06.77)LF25$992.46
359Open cut 16IN steel casing pipe (797-06.90)LF100$580.43
360Open cut 48IN steel casing pipe (797-06.96)LF250$1,394.49
36148IN manhole 6FT-8FT depth (797-07.03)EACH2$6,344.54
36248IN manhole 8FT-10FT depth (797-07.04)EACH3$8,917.12
36360IN manhole 8FT-10FT depth (797-07.15)EACH1$18,903
36460IN manhole 10FT-12FT depth (797-07.16)EACH1$20,607
36560IN manhole 12FT-14FT depth (797-07.17)EACH1$14,986
366Manhole drop connection assembly (797-07.56)EACH1$6,249.60
367Adjust existing manhole (raise to new grade) (797-07.61)EACH1$5,248.48
368DI fittings (797-08.01)LB3,000$17.27
3696IN PVC pipe for service lateral (797-08.05)LF100$87.71
3708IN plug valve assembly (797-09.08)EACH2$21,066
3711IN combo air release valve assembly (797-09.19)EACH2$5,670.69
372Cut and cap 10IN gravity (797-09.48)EACH1$8,519.91
373Connect EX.10-18IN sewer to new manhole (797-10.10)EACH2$9,510.96
374Connect EX. >18IN sewer to new manhole (797-10.11)EACH1$11,073
37560IN manhole rehabilitation (797-11.11)VF20$803.91
376Retirein place existing sewer 8IN-14IN (797-11.31)LF270$204.01
377By-pass pumping (797-11.38)LS1$75,096
378Bridge hanger system (797-11.43)LS1$173,933
TDOT contract CN261011: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of February 6, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy