CDOT unit bid prices and bid tabulations
Unit prices bid on 145 Colorado DOT contracts let from 17 MAY 2023 to 10 SEP 2026, read from CDOT's own tabulations. 55 pay items have enough recent bids for a page of their own; every item is in the explorer.
- Contracts
- 145
- Bids
- 472
- Unit prices
- 39,455
Data through 10 SEP 2026, the latest CDOT letting read. Compiled by Mirage Metrics.
Price a CDOT pay item
Pay items bid most often in Colorado
| Pay item | Code | Unit | Low-bid median | Low bids |
|---|---|---|---|---|
| Traffic control management | 630-00012 | DAY | $1,450.00 | 107 |
| Construction traffic sign (panel size A) | 630-80341 | EACH | $50.00 | 98 |
| Traffic control inspection | 630-00007 | DAY | $340.00 | 101 |
| Traffic cone | 630-80380 | EACH | $10.52 | 96 |
| Flagging | 630-00000 | HR | $48.00 | 97 |
| Construction traffic sign (panel size B) | 630-80342 | EACH | $61.00 | 93 |
| Sanitary facility | 620-00020 | EACH | $4,000.00 | 90 |
| Portable message sign panel | 630-80355 | EACH | $6,302.50 | 94 |
| Drum channelizing device | 630-80360 | EACH | $38.50 | 86 |
| Potholing | 203-01597 | HR | $334.00 | 79 |
| Sweeping (sediment removal) | 208-00106 | HR | $180.00 | 74 |
| Aggregate bag | 208-00035 | LF | $12.02 | 71 |
Check my bid
Add the lines you are pricing, with your quantity and unit price. Each line is placed against what bidders carried in the last 24 months, at a similar quantity when enough bids exist. Your numbers stay in this browser.
Competitors
Who bids, how often they are low, how far off they are when they lose, and how much they leave on the table when they win.
Sort by: most bids counts every bid a firm submitted; most low bids counts the contracts where it was the low bidder; win rate is low bids divided by bids, for firms with five bids or more; low bid volume adds up its low bids in dollars. Gap when not low is the average distance from its total to the low bid; left on table is the average distance from its low bid to the second bid.
99 firms in Colorado, the 50 with the most bids shown.
| Bidder | Bids | Low bids | Win rate | Gap when not low | Left on table | Low bid volume |
|---|---|---|---|---|---|---|
| Oldcastle SW Group, Inc. | 30 | 13 | 43% | +17% | +17% | $134.5M |
| Myers & Sons Construction, LLC | 26 | 5 | 19% | +24% | +13% | $17.4M |
| Structures, Inc. | 20 | 7 | 35% | +24% | +10% | $34.1M |
| Kiewit Infrastructure Co. | 18 | 5 | 28% | +34% | $92.9M | |
| Morton Electric, Inc. | 18 | 5 | 28% | +11% | +19% | $8.9M |
| Martin Marietta Materials, Inc. | 16 | 5 | 31% | +19% | +6.0% | $61.5M |
| American West Construction, LLC | 14 | 5 | 36% | +24% | +32% | $6.5M |
| Rodriguez Construction Org., LLC | 13 | 2 | 15% | +48% | +6.0% | $5.0M |
| Roadsafe Traffic Systems, Inc | 13 | 9 | 69% | +15% | +9.0% | $27.7M |
| Brannan Sand and Gravel, LLC | 12 | 5 | 42% | +21% | +7.0% | $36.1M |
| Abco Contracting, Inc. | 12 | 2 | 17% | +23% | +4.0% | $8.1M |
| Jalisco International, Inc. | 11 | 4 | 36% | +21% | +11% | $18.4M |
| Native Sun Materials Inc | 11 | 3 | 27% | +30% | +16% | $13.2M |
| Kilgore Companies, LLC dba Elam Construction | 10 | 4 | 40% | +11% | +10% | $33.3M |
| Kraemer North America, LLC | 9 | 5 | 56% | +96% | +3.0% | $172.3M |
| Siete, Inc. | 9 | 2 | 22% | +21% | +9.0% | $6.8M |
| Sturgeon Electric Company, Inc. | 9 | 3 | 33% | +10% | +3.0% | $3.3M |
| Lighthouse Transportation Group, LLC | 8 | 1 | 13% | +21% | +2.0% | $656K |
| FNF Construction, Inc. | 8 | 0 | 0% | +19% | ||
| W.W. Clyde & Co. | 8 | 3 | 38% | +58% | +14% | $46.6M |
| Capital Paving & Construction, LLC | 7 | 3 | 43% | +8.0% | +6.0% | $20.9M |
| HCG Construction LLC | 6 | 2 | 33% | +22% | +20% | $3.4M |
| Branson Traffic Control Company, Inc | 6 | 1 | 17% | +8.0% | +101% | $479K |
| CC Enterprises - Traffic Control Specialists, Inc. | 6 | 0 | 0% | +9.0% | ||
| HANK WILLIAMS, INC. dba WILLIAMS CONSTRUCTION CONTRACTORS | 6 | 1 | 17% | +36% | $987K | |
| Insituform Technologies, LLC | 6 | 2 | 33% | +25% | +18% | $3.9M |
| Subsurface, Inc | 6 | 2 | 33% | +38% | +26% | $2.1M |
| Lobato Construction, LLC | 6 | 1 | 17% | +19% | +25% | $1.8M |
| Adiona Transportation Solutions LLC | 6 | 3 | 50% | +18% | +6.0% | $2.6M |
| Asphalt Specialties Co., Inc. | 5 | 3 | 60% | +13% | +18% | $39.0M |
| Workzone Traffic Control, LLC | 5 | 4 | 80% | +4.0% | +9.0% | $3.9M |
| KSK, LLC | 5 | 2 | 40% | +16% | +9.0% | $6.8M |
| Ralph L. Wadsworth Construction Company, LLC. | 5 | 0 | 0% | +29% | ||
| Tricon 2, LLC | 4 | 1 | 25% | +32% | +37% | $247K |
| Meridian Engineering Co. dba Meridian Contracting, Inc. | 4 | 0 | 0% | +31% | ||
| Concrete Concepts Design Inc, DBA Pyramid Construction Inc | 4 | 2 | 50% | +3.0% | +3.0% | $7.2M |
| Lumin8 Transportation Technologies, LLC | 4 | 0 | 0% | +17% | ||
| Streamline Markings, Inc | 4 | 2 | 50% | +11% | +14% | $3.8M |
| Ames Construction Incorporated | 4 | 2 | 50% | +6.0% | +85% | $2.5M |
| TLM Constructors, Inc. | 4 | 1 | 25% | +21% | +2.0% | $5.3M |
| Castle Rock Construction Company of Colorado, LLC | 4 | 1 | 25% | +9.0% | +20% | $3.5M |
| Holcim -WCR, Inc. Aggregate Industries - WCR, Inc. | 3 | 0 | 0% | +14% | ||
| Connell Resources Incorporated | 3 | 1 | 33% | +6.0% | +66% | $488K |
| Bettis Asphalt and Construction, Inc. | 3 | 0 | 0% | +3.0% | ||
| Edge Contracting, Inc. | 3 | 0 | 0% | +37% | ||
| Hudick Excavating, Inc. | 3 | 1 | 33% | +14% | +9.0% | $13.5M |
| Concrete Works of Colorado, Inc. | 3 | 0 | 0% | +41% | ||
| Chato'S Concrete, LLC | 3 | 0 | 0% | +26% | ||
| Goodland Construction, Inc. | 3 | 1 | 33% | +22% | +6.0% | $2.4M |
| RLW/SEMA , A Joint Venture | 2 | 2 | 100% | $113.2M |
Lettings
Open any contract to read the full tabulation: every line, every bidder.
Latest CDOT contracts in the data.
Sources and checks
Each price is copied from a bid tabulation the owner published after the letting. Nothing is estimated or averaged before it reaches this page.
| Owner | Lettings | Contracts | Bids | Prices | Check | How it was read |
|---|---|---|---|---|---|---|
| Texas DOT | 9 Jan 2020 to 19 Nov 2026 | 8,909 | 37,824 | 1,860,794 | Reconciled | TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out. |
| Ohio DOT | 23 Jan 2020 to 12 Nov 2026 | 4,408 | 15,816 | 1,093,243 | Reconciled | ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them. |
| Illinois DOT | 15 Jan 2021 to 18 Sep 2026 | 5,494 | 16,087 | 932,368 | Reconciled | IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total. |
| Florida DOT | 31 Jan 2018 to 28 Oct 2026 | 1,738 | 7,302 | 814,861 | Reconciled | FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out. |
| North Carolina DOT | 15 Jan 2013 to 20 Oct 2026 | 1,659 | 6,770 | 767,334 | Reconciled | NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out. |
| Virginia DOT | 29 Jan 2002 to 28 Oct 2026 | 7,628 | 18,240 | 674,864 | Reconciled | VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger. |
| Wisconsin DOT | 11 Jan 2022 to 10 Nov 2026 | 1,598 | 5,095 | 608,530 | Reconciled | WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out. |
| Indiana DOT | 12 Jan 2022 to 5 Nov 2026 | 2,082 | 7,109 | 552,581 | Reconciled | INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out. |
| Washington State DOT | 29 Dec 1999 to 7 Oct 2026 | 1,317 | 5,732 | 365,366 | Reconciled | WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept. |
| New York State DOT | 6 Jan 2022 to 15 Oct 2026 | 1,080 | 3,894 | 344,856 | Reconciled | NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped. |
| Kentucky Transportation Cabinet | 22 Nov 2019 to 22 Oct 2026 | 4,414 | 9,448 | 336,278 | Reconciled | KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out. |
| New Jersey DOT | 22 Jun 2017 to 16 Apr 2026 | 934 | 3,363 | 314,765 | Reconciled | NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price. |
| Missouri DOT | 17 Jan 2020 to 16 Oct 2026 | 1,896 | 5,865 | 293,103 | Reconciled | MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years. |
| South Carolina DOT | 11 Jan 2022 to 13 Oct 2026 | 1,037 | 3,257 | 175,917 | Reconciled | SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out. |
| Tennessee DOT | 9 Feb 2018 to 2 Oct 2026 | 1,257 | 3,169 | 156,766 | Reconciled | TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out. |
| Alabama DOT | 28 Jan 2022 to 28 Aug 2026 | 993 | 2,677 | 153,448 | Reconciled | ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total. |
| Oregon DOT | 7 Jan 2021 to 13 Aug 2026 | 394 | 1,571 | 131,407 | Not checkable | ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views. |
| Arkansas DOT | 12 Jan 2022 to 4 Nov 2026 | 1,118 | 2,578 | 80,673 | Reconciled | ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount. |
| Colorado DOT | 17 May 2023 to 10 Sep 2026 | 145 | 472 | 39,455 | Reconciled | CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out. |
| Iowa DOT | 19 Jan 2022 to 20 Oct 2026 | 112 | 415 | 12,634 | Reconciled | Iowa DOT bid tabulation PDFs: the letting of 19 January 2022 (read from the Internet Archive's copy of Iowa DOT's file) and lettings of August to October 2026. On A+B contracts the item total is kept and the time part dropped. Bids that did not match their published total are left out. |
| Caltrans | 25 Apr 2023 to 9 May 2023 | 33 | 95 | 4,418 | Reconciled | Caltrans bid summary PDFs; scanned pages read by OCR. Bids that did not match their published total are left out. |
How each bid was checked
For every bidder, quantity times unit price was summed over all lines of the contract and compared with the total bid printed by the owner. A bid is published only when the two match to within one dollar. The states marked not checkable or third party are explained in the table.
Read the numbers like an estimator
- Item codes and measurement rules are each owner's. Prices are compared inside one state and never pooled across states.
- Unit price moves with quantity, location and season. Set your quantity and region before you trust a median.
- Some bidders price a line at a cent and load the cost elsewhere. Those token prices, and bids more than three times the low bid, are left out of statistics by default and stay visible in tabulations.
- The low bidder's price on one line is not always the lowest price on that line. Orange marks the bidder who was low on the whole contract.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
The CDOT pay items bid most often
| Pay item | Code | Unit | Low-bid median | Low bids | Window | Bids, all time |
|---|---|---|---|---|---|---|
| Traffic control management | 630-00012 | DAY | $1,450.00 | 107 | Last 24 months | 457 |
| Construction traffic sign (panel size A) | 630-80341 | EACH | $50.00 | 98 | Last 24 months | 434 |
| Traffic control inspection | 630-00007 | DAY | $340.00 | 101 | Last 24 months | 433 |
| Traffic cone | 630-80380 | EACH | $10.52 | 96 | Last 24 months | 430 |
| Flagging | 630-00000 | HR | $48.00 | 97 | Last 24 months | 422 |
| Construction traffic sign (panel size B) | 630-80342 | EACH | $61.00 | 93 | Last 24 months | 410 |
| Sanitary facility | 620-00020 | EACH | $4,000.00 | 90 | Last 24 months | 399 |
| Portable message sign panel | 630-80355 | EACH | $6,302.50 | 94 | Last 24 months | 395 |
| Drum channelizing device | 630-80360 | EACH | $38.50 | 86 | Last 24 months | 368 |
| Potholing | 203-01597 | HR | $334.00 | 79 | Last 24 months | 331 |
| Sweeping (sediment removal) | 208-00106 | HR | $180.00 | 74 | Last 24 months | 324 |
| Aggregate bag | 208-00035 | LF | $12.02 | 71 | Last 24 months | 321 |
| Removal and disposal of sediment (labor) | 208-00103 | HR | $75.00 | 70 | Last 24 months | 312 |
| Removal and disposal of sediment (equipment) | 208-00105 | HR | $150.00 | 61 | Last 24 months | 279 |
| Removal of trash | 208-00107 | HR | $110.00 | 61 | Last 24 months | 265 |
| Erosion log type 1 (12 inch) | 208-00002 | LF | $7.00 | 61 | Last 24 months | 254 |
| Mycorrhizae | 212-00704 | LB | $22.25 | 60 | Last 24 months | 252 |
| Removal of pavement marking | 202-00250 | SF | $2.00 | 55 | Last 24 months | 251 |
| Advance warning flashing or sequencing arrow panel (C type) | 630-80358 | EACH | $1,681.18 | 55 | Last 24 months | 244 |
| Pre-fabricated vehicle tracking pad | 208-00075 | EACH | $5,000.00 | 54 | Last 24 months | 240 |
| Pre-fabricated concrete washout structure (type 1) | 208-00046 | EACH | $2,946.00 | 55 | Last 24 months | 235 |
| Hot mix asphalt (patching) (asphalt) | 403-00720 | TON | $300.00 | 50 | Last 24 months | 232 |
| Fence (plastic) | 607-11525 | LF | $4.30 | 49 | Last 24 months | 231 |
| Vertical panel | 630-80350 | EACH | $35.00 | 54 | Last 24 months | 230 |
| Removal of asphalt mat | 202-00220 | SY | $25.61 | 48 | Last 24 months | 226 |
| Modified epoxy pavement marking | 627-00008 | GAL | $171.50 | 58 | Last 24 months | 226 |
| Barricade (type 3 M-A) (temporary) | 630-80335 | EACH | $180.00 | 45 | Last 24 months | 219 |
| Sign panel (class I) | 614-00011 | SF | $30.00 | 49 | Last 24 months | 215 |
| Removal of ground sign | 202-00810 | EACH | $179.00 | 44 | Last 24 months | 210 |
| Removal of asphalt mat (planing) | 202-00240 | SY | $4.32 | 48 | Last 24 months | 207 |
| Erosion control management | 208-00207 | DAY | $386.75 | 40 | Last 24 months | 205 |
| Wildlife biologist | 240-00000 | HR | $205.63 | 43 | Last 24 months | 202 |
| Removal of delineator | 202-00090 | EACH | $17.00 | 45 | Last 24 months | 188 |
| Construction traffic sign (panel size C) | 630-80343 | EACH | $73.00 | 41 | Last 24 months | 180 |
| Field office (class 2) | 620-00002 | EACH | $45,000 | 43 | Last 24 months | 179 |
| Sign panel (class II) | 614-00012 | SF | $40.00 | 39 | Last 24 months | 176 |
| Organic fertilizer | 212-00700 | LB | $2.49 | 46 | Last 24 months | 175 |
| Mulch tackifier | 213-00061 | LB | $5.30 | 41 | Last 24 months | 175 |
| Blading | 203-01500 | HR | $192.90 | 38 | Last 24 months | 171 |
| Impact attenuator (temporary) | 630-85010 | EACH | $7,004.00 | 34 | Last 24 months | 167 |
| Removal of guardrail type 3 | 202-01130 | LF | $8.05 | 36 | Last 24 months | 166 |
| Removal of nests | 240-00010 | HR | $213.50 | 41 | Last 24 months | 164 |
| Pavement marking paint (high build) | 627-00013 | GAL | $94.22 | 30 | Last 24 months | 164 |
| Field laboratory (class 2) | 620-00012 | EACH | $44,991 | 37 | Last 24 months | 164 |
| Compost (mechanically applied) | 212-00701 | CY | $97.43 | 39 | Last 24 months | 163 |
| Combination loader | 203-01594 | HR | $150.60 | 40 | Last 24 months | 157 |
| Reset ground sign | 210-00810 | EACH | $495.50 | 32 | Last 24 months | 155 |
| Topsoil (onsite) | 207-00700 | CY | $23.00 | 32 | Last 24 months | 154 |
| Seeding (native) broadcast | 212-00708 | ACRE | $5,480.00 | 35 | Last 24 months | 152 |
| Preformed thermoplastic pavement marking (word-symbol) | 627-30405 | SF | $28.20 | 33 | Last 24 months | 148 |
| Emulsified asphalt (slow-setting) | 411-10255 | GAL | $5.50 | 35 | Last 24 months | 147 |
| Clean culvert | 202-04002 | EACH | $3,307.50 | 34 | Last 24 months | 143 |
| Uniformed traffic control | 630-00003 | HR | $170.00 | 33 | Last 24 months | 133 |
| Aggregate base course (class 6) | 304-06007 | CY | $101.50 | 27 | Last 24 months | 129 |
| Removal of end anchorage | 202-01300 | EACH | $489.69 | 30 | Last 24 months | 128 |
Who bids on CDOT work
| Bidder | Bids | Low bids | Win rate |
|---|---|---|---|
| Oldcastle SW Group, Inc. | 30 | 13 | 43% |
| Myers & Sons Construction, LLC | 26 | 5 | 19% |
| Structures, Inc. | 20 | 7 | 35% |
| Kiewit Infrastructure Co. | 18 | 5 | 28% |
| Morton Electric, Inc. | 18 | 5 | 28% |
| Martin Marietta Materials, Inc. | 16 | 5 | 31% |
| American West Construction, LLC | 14 | 5 | 36% |
| Rodriguez Construction Org., LLC | 13 | 2 | 15% |
| Roadsafe Traffic Systems, Inc | 13 | 9 | 69% |
| Brannan Sand and Gravel, LLC | 12 | 5 | 42% |
14 firms have a page with their full record: all CDOT bidders.
Latest lettings
| Let | Contract | Region | Project | Bids | Low bid | Low bidder | Source |
|---|---|---|---|---|---|---|---|
| 10 SEP 2026 | C27164 | Region 1 | SH053A, SH095A, SH287C | 8 | $925,986 | Jalisco International, Inc. | CDOT |
| 10 SEP 2026 | C27188 | Region 3 | This project consists of pavement marking removal, chip seal, pavement marking, and traffic control on SH 141B between MP 156.7 to 159.9, US | 2 | $2,594,340 | A-1 Chipseal Company | CDOT |
| 28 AUG 2026 | C27797 | Region 1 | ON US 85 AT MM 185.546, BETWEEN PROMENADE PKWY AND NEW BEAL | 4 | $286,745 | American West Construction, LLC | CDOT |
| 02 MAR 2026 | C27259 | Region 1 | This project will address emergency erosion at 2 locations near US 40 and Tonn Valley Drive. One location is located within CDOT ROW off of | 2 | $433,473 | CONCRETE EXPRESS, INC.dba CEI | CDOT |
| 11 FEB 2026 | C27393 | Region 1 | Permanent repairs to structure F-16-YE (Southbound Santa Fe to Eastbound C470 Flyover ) Site Number: 00 Days Road User Cost Per Time Unit: $ | 3 | $1,251,000 | Ames Construction Incorporated | CDOT |
| 30 JAN 2026 | C27376A | Region 1 | Repairs to structure F-16-YE (Southbound Santa Fe to Eastbound C470 Flyover -The scope of work will include the installation of a temporary | 3 | $1,251,000 | Ames Construction Incorporated | CDOT |
| 18 DEC 2025 | C24846 | County line to purcell blvd | 3 | $12,305,351 | Martin Marietta Materials, Inc. | CDOT | |
| 18 DEC 2025 | C26234 | Culvert (11) remove & replace culvert locations combined with (8)rehab culvert locations. remove & replace culvert locations as shown in the | 3 | $8,859,323 | Native Sun Materials Inc | CDOT | |
| 18 DEC 2025 | C26274 | This is bridge replacement project near hayden, colorado in routt county along us 40 at mp 108.35. the work includes water control, a tempor | 5 | $2,440,781 | Oldcastle SW Group, Inc. | CDOT | |
| 11 DEC 2025 | C25682 | This project is located along us 40 between mp 111.5 to mp 126.5. the project will overlay the roadway with a 1" leveling layer and a 1.5" t | 2 | $12,017,516 | Oldcastle SW Group, Inc. | CDOT | |
| 18 SEP 2025 | C23069-COMBO | Region 5 | US 50 CONEJOS RIVER BRIDGE STRUCTURE P-12-A BE | 5 | $2,866,394 | W.W. Clyde & Co. | CDOT |
| 18 SEP 2025 | C25393 | Region 2 | WIDENING AND RESURFACING OF I-25C FROM THE INTERSECTION WITH PINE STREET TO JUST BEFORE THE STRUCTURE N-17-BV OVER THE PICTOUR ARROYO. | 8 | $5,987,513 | Siete, Inc. | CDOT |
Every CDOT letting since 2022, contract by contract: CDOT letting results.
CDOT projects on the infrastructure map
Large Colorado DOT projects described on our infrastructure map, each with its owner's own sources:
Where these numbers come from
CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
| Year | Contracts |
|---|---|
| 2023 | 3 |
| 2024 | 80 |
| 2025 | 56 |
| 2026 | 6 |
Every state's coverage and check is on the bid results hub.
Other states: Alabama, Arkansas, California, Florida, Illinois, Indiana, Iowa, Kentucky, Missouri, New Jersey, New York, North Carolina, Ohio, Oregon, South Carolina, Tennessee, Texas, Virginia, Washington, Wisconsin.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.