FDOT contract T7562 bid tabulation
SR 586 (CURLEW RD) AND SR 595 (US ALT 19 / BAYSHORE BLVD)... Let by Florida DOT on April 29, 2026, Pinellas, District 7. 7 bids received; low bid $27,734,147 by Watson Civil Construction, Inc..
- Owner
- Florida DOT
- Letting
- 29 APR 2026
- Pay items
- 328
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Watson Civil Construction, Inc. | $27,734,147 | Low |
| 2 | Cone & Graham, Inc. | $32,022,000 | +15% |
| 3 | Russell Engineering, Inc. | $32,620,596 | +18% |
| 4 | Nelson, David, Construction Co. | $32,885,125 | +19% |
| 5 | De Moya Contracting LLC | $34,679,749 | +25% |
| 6 | Crisdel Group, Inc | $41,293,548 | +49% |
| 7 | Ajax Paving Industries of Florida LLC | $54,886,754 | +98% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Watson Civil Construction, Inc. | 2. Cone & Graham, Inc. | 3. Russell Engineering, Inc. | 4. Nelson, David, Construction Co. | 5. De Moya Contracting LLC | 6. Crisdel Group, Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $1,370,000 | $1,045,000 | $1,255,013 | $2,600,000 | $1,200,000 | $2,000,000 |
| 0010 | Mobilization (0101-1) | LS | 1 | $137,000 | $295,000 | $1,000,000 | $300,000 | $1,100,000 | $317,000 |
| 0015 | Mobilization (0101-1) | LS | 1 | $1,233,000 | $1,750,000 | $1,000,000 | $400,000 | $1,100,000 | $1,915,000 |
| 0020 | Maintenance of traffic (0102-1) | DA | 1 | $650,000 | $1,408,250 | $2,365,000 | $1,000,000 | $800,000 | $1,700,000 |
| 0025 | Maintenance of traffic (0102-1) | DA | 1 | $65,000 | $239,000 | $1,000,000 | $800,000 | $750,000 | $35,000 |
| 0030 | Maintenance of traffic (0102-1) | DA | 1 | $585,000 | $1,408,250 | $1,000,000 | $540,000 | $700,000 | $1,700,000 |
| 0035 | Special detour- temporary pavement (0102-2200) | SY | 1 | $243,000 | $626,000 | $155,013 | $300,000 | $400,000 | $210,000 |
| 0040 | Special detour- temporary pavement (0102-2200) | SY | 1 | $29,100 | $32,000 | $13,055 | $50,000 | $50,000 | $41,500 |
| 0045 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $108,000 | $50,000 | $255,013 | $25,000 | $50,000 | $75,000 |
| 0050 | Commercial material for temporary driveway maintenance (0102-3) | CY | 68.70 | $320.00 | $115.00 | $100.00 | $200.00 | $100.00 | $250.00 |
| 0055 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $47,000 | $46,000 | $50,000 | $50,000 | $75,000 | $163,000 |
| 0060 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $27,000 | $53,415 | $30,000 | $15,000 | $50,000 | $44,000 |
| 0065 | Pedestrian escort/flagger (0102-5) | HR | 48 | $29.00 | $90.00 | $250.00 | $200.00 | $40.00 | $55.00 |
| 0070 | Traffic control officer (0102-14) | HR | 1,560 | $120.00 | $90.00 | $95.00 | $90.00 | $85.00 | $84.00 |
| 0075 | Temporary highway lighting (0102-30) | EACH | 1 | $27,000 | $5,000.00 | $5,000.00 | $7,500.00 | $5,000.00 | $5,250.00 |
| 0080 | Work zone sign (0102-60) | ED | 269,889 | $0.25 | $0.17 | $0.19 | $0.30 | $0.17 | $0.30 |
| 0085 | Business sign (0102-61) | EACH | 17 | $45.00 | $45.00 | $55.00 | $30.00 | $100.00 | $58.00 |
| 0090 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 6,396 | $41.00 | $38.00 | $39.00 | $40.00 | $38.00 | $40.00 |
| 0095 | Temporary barrier, relocate, low profile concrete (0102-71-23) | LF | 10,680 | $19.00 | $9.00 | $18.00 | $25.00 | $9.00 | $12.00 |
| 0100 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 302,019 | $0.14 | $0.09 | $0.25 | $0.20 | $0.09 | $0.10 |
| 0105 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 679,240 | $0.04 | $0.03 | $0.03 | $0.15 | $0.03 | $0.04 |
| 0110 | Temporary separator, F&I remove (0102-75-1) | LF | 2,525 | $21.00 | $27.00 | $19.00 | $30.00 | $19.75 | $17.00 |
| 0115 | Arrow board / advance warning arrow panel (0102-76) | ED | 2,097 | $7.00 | $4.75 | $5.00 | $10.00 | $4.75 | $5.50 |
| 0120 | Portable changeable message sign, temporary (0102-99) | ED | 19,817 | $13.00 | $8.75 | $9.00 | $10.00 | $8.75 | $11.00 |
| 0125 | Temporary signalization and maintenance, intersection (0102-104) | ED | 2,715 | $40.00 | $65.91 | $66.00 | $80.00 | $65.91 | $70.00 |
| 0130 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 2,715 | $40.00 | $27.84 | $28.00 | $35.00 | $27.84 | $30.00 |
| 0135 | Existing ITS maintenance (0102-112) | DA | 905 | $165.00 | $42.64 | $43.00 | $50.00 | $150.00 | $45.00 |
| 0140 | Type III barricade (0102-115) | ED | 26,929 | $0.33 | $0.23 | $0.25 | $0.40 | $0.23 | $0.30 |
| 0145 | Temporary raised rumble per day, includes all sets and relocations (0102-909) | DA | 52 | $31.00 | $30.00 | $60.00 | $100.00 | $30.00 | $100.00 |
| 0150 | Temporary slope drain / runoff control structure (0104-6) | LF | 217 | $46.00 | $61.40 | $52.00 | $30.00 | $200.00 | $90.00 |
| 0155 | Sediment basin / containment system (0104-7) | EACH | 1 | $3,650.00 | $950.00 | $10,000 | $5,000.00 | $5,000.00 | $11,000 |
| 0160 | Sediment basin / containment system- cleanout (0104-9) | EACH | 1 | $1,600.00 | $12,000 | $2,000.00 | $5,000.00 | $5,000.00 | $7,200.00 |
| 0165 | Sediment barrier (0104-10-3) | LF | 15,341 | $1.65 | $2.10 | $2.00 | $2.00 | $3.50 | $3.70 |
| 0170 | Floating turbidity barrier (0104-11) | LF | 85 | $18.60 | $12.00 | $20.00 | $30.00 | $15.00 | $62.00 |
| 0175 | Staked turbidity barrier- nylon reinforced PVC (0104-12) | LF | 133 | $4.05 | $5.00 | $20.00 | $10.00 | $10.00 | $10.00 |
| 0180 | Soil tracking prevention device (0104-15) | EACH | 6 | $3,700.00 | $4,000.00 | $1,055.00 | $5,000.00 | $4,500.00 | $18,000 |
| 0185 | Inlet protection system (0104-18) | EACH | 109 | $130.00 | $125.00 | $295.00 | $150.00 | $175.00 | $270.00 |
| 0190 | Litter removal (0107-1) | ACRE | 790.53 | $50.00 | $50.00 | $59.00 | $30.00 | $50.00 | $41.00 |
| 0195 | Mowing (0107-2) | ACRE | 546.72 | $94.50 | $94.00 | $200.00 | $50.00 | $50.00 | $48.00 |
| 0200 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $18,000 | $27,250 | $25,500 | $30,000 | $25,000 | $12,600 |
| 0205 | Monitor existing structures- vibration monitoring (0108-2) | LS | 1 | $3,600.00 | $57,200 | $35,600 | $70,000 | $25,000 | $70,000 |
| 0210 | Monitor existing structures- groundwater monitoring (0108-3) | LS | 1 | $7,500.00 | $87,800 | $25,200 | $105,000 | $25,000 | $17,000 |
| 0215 | Clearing & grubbing 44804115201, (0110-1-1) | ACRE | 1 | $840,000 | $900,000 | $450,000 | $400,000 | $100,000 | $100,000 |
| 0220 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $364,000 | $842,000 | $413,628 | $300,000 | $500,000 | $300,000 |
| 0225 | Removal of existing concrete (0110-4-10) | SY | 7,092 | $25.00 | $21.00 | $40.00 | $35.00 | $75.00 | $28.00 |
| 0230 | Mailbox, F&I single (0110-7-1) | EACH | 3 | $320.00 | $375.00 | $551.00 | $300.00 | $450.00 | $360.00 |
| 0235 | Tree root and branch pruning (0110-22) | EACH | 17 | $1,100.00 | $4,750.00 | $2,250.00 | $2,000.00 | $1,500.00 | $1,575.00 |
| 0240 | Regular excavation (0120-1) | CY | 10,414.20 | $12.00 | $35.00 | $32.00 | $50.00 | $20.00 | $71.00 |
| 0245 | Embankment (0120-6) | CY | 3,944.80 | $8.00 | $60.00 | $7.60 | $10.00 | $30.00 | $75.00 |
| 0250 | Type B stabilization (0160-4) | SY | 12,642 | $19.00 | $26.00 | $7.00 | $20.00 | $20.00 | $27.00 |
| 0255 | Optional base, base group 01 (0285-701) | SY | 145 | $47.00 | $40.00 | $25.00 | $60.00 | $60.00 | $69.00 |
| 0260 | Optional base, base group 06 (0285-706) | SY | 4,620 | $31.00 | $32.00 | $33.00 | $40.00 | $65.00 | $32.00 |
| 0265 | Optional base, base group 10 (0285-710) | SY | 1,016 | $43.00 | $45.00 | $42.00 | $50.00 | $80.00 | $33.00 |
| 0270 | Optional base, base group 11 (0285-711) | SY | 4,545 | $64.50 | $65.15 | $70.00 | $80.00 | $95.00 | $62.00 |
| 0275 | Turnout base- optional materials (0286-1) | SY | 598 | $47.00 | $43.00 | $45.55 | $70.00 | $100.00 | $40.00 |
| 0280 | Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2) | SY | 19,861 | $5.75 | $5.50 | $5.60 | $5.60 | $5.00 | $5.80 |
| 0285 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 68,681 | $5.80 | $5.52 | $4.20 | $5.60 | $6.00 | $5.80 |
| 0290 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 19,308 | $6.75 | $6.42 | $8.35 | $6.50 | $8.00 | $6.75 |
| 0295 | Superpave asphaltic conc, traffic B (0334-1-12) | TN | 9,930.40 | $178.00 | $170.50 | $185.00 | $180.00 | $225.00 | $180.00 |
| 0300 | Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81) | TN | 9,464.60 | $208.00 | $198.71 | $215.55 | $205.00 | $250.00 | $209.00 |
| 0305 | Concrete class NS, gravity index 400-011 (0400-0-11) | CY | 593.10 | $833.00 | $700.00 | $1,380.00 | $1,300.00 | $1,200.00 | $1,110.00 |
| 0310 | Concrete class NS, steps (0400-0-13) | CY | 3.30 | $1,100.00 | $700.00 | $1,690.00 | $1,200.00 | $5,000.00 | $2,500.00 |
| 0315 | Concrete, class I (seal) (0400-1-30) | CY | 3.40 | $4,300.00 | $2,500.00 | $2,068.00 | $1,600.00 | $5,000.00 | $1,200.00 |
| 0320 | Concrete class II, retaining walls (0400-2-11) | CY | 118.30 | $1,120.00 | $1,310.00 | $1,325.00 | $1,500.00 | $2,000.00 | $1,630.00 |
| 0325 | Concrete class IV, culverts (0400-4-1) | CY | 124 | $2,300.00 | $3,800.00 | $5,013.00 | $7,500.00 | $2,800.00 | $3,600.00 |
| 0330 | Conc class IV, bulkhead (0400-4-8) | CY | 4 | $2,050.00 | $5,125.00 | $5,755.00 | $1,700.00 | $2,900.00 | $4,200.00 |
| 0335 | Reinforcing steel- roadway (0415-1-1) | LB | 23,566 | $2.00 | $1.00 | $3.32 | $1.00 | $2.00 | $1.10 |
| 0340 | Reinforcing steel- retaining wall (0415-1-3) | LB | 13,979 | $2.10 | $1.80 | $3.00 | $1.00 | $2.00 | $1.10 |
| 0345 | Reinforcing steel- bulkhead (0415-1-8) | LB | 247 | $4.35 | $2.00 | $5.00 | $1.00 | $2.00 | $1.10 |
| 0350 | Inlets, curb, type P-1, <10' (0425-1311) | EACH | 1 | $8,000.00 | $12,000 | $11,868 | $12,000 | $15,000 | $13,000 |
| 0355 | Inlets, curb, type P-5, <10' (0425-1351) | EACH | 28 | $7,300.00 | $11,700 | $10,555 | $12,000 | $15,000 | $13,500 |
| 0360 | Inlets, curb, type P-6, <10' (0425-1361) | EACH | 13 | $7,800.00 | $11,800 | $10,685 | $12,000 | $15,000 | $9,800.00 |
| 0365 | Inlets, curb, type J-5, <10' (0425-1451) | EACH | 24 | $15,300 | $23,125 | $19,413 | $26,000 | $25,000 | $31,000 |
| 0370 | Inlets, curb, type J-6, <10' (0425-1461) | EACH | 12 | $20,000 | $29,380 | $21,837 | $27,000 | $20,000 | $33,000 |
| 0375 | Inlets, curb, type J-6, >10' (0425-1462) | EACH | 2 | $22,000 | $31,200 | $25,481 | $26,000 | $25,000 | $22,000 |
| 0380 | Inlets, curb, type 7, <10' (0425-1471) | EACH | 2 | $8,700.00 | $12,950 | $11,978 | $7,000.00 | $15,000 | $19,500 |
| 0385 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 5 | $5,000.00 | $7,250.00 | $9,247.00 | $7,000.00 | $15,000 | $5,600.00 |
| 0390 | Inlets, ditch bottom, type C modified- back of sidewalk, <10' (0425-1531) | EACH | 3 | $5,000.00 | $6,125.00 | $8,037.00 | $6,000.00 | $15,000 | $5,200.00 |
| 0395 | Inlets, DT bot, type D, <10' (0425-1541) | EACH | 1 | $6,700.00 | $7,950.00 | $10,564 | $7,000.00 | $15,000 | $14,500 |
| 0400 | Inlets, ditch bottom, type D, J bot, <10' (0425-1543) | EACH | 1 | $7,700.00 | $10,800 | $10,473 | $8,000.00 | $20,000 | $6,600.00 |
| 0405 | Inlets, DT bot, type E, J bot, <10' (0425-1553) | EACH | 4 | $7,600.00 | $17,400 | $16,197 | $13,000 | $20,000 | $22,000 |
| 0410 | Inlets, DT bot, type F, <10' (0425-1561) | EACH | 1 | $5,800.00 | $9,300.00 | $9,755.00 | $8,500.00 | $15,000 | $8,000.00 |
| 0415 | Inlets, DT bot, type H, <10' (0425-1581) | EACH | 1 | $7,110.00 | $14,700 | $11,462 | $19,000 | $15,000 | $15,000 |
| 0420 | Inlets, DT bot, type H, J bottom <10' (0425-1583) | EACH | 2 | $13,900 | $32,400 | $19,000 | $50,000 | $15,000 | $72,000 |
| 0425 | Inlets, DT bot, type H, modify (0425-1589) | EACH | 3 | $26,000 | $22,200 | $24,592 | $16,000 | $20,000 | $27,500 |
| 0430 | Inlets, adjacent barrier, J bottom, < 10' (0425-1923) | EACH | 1 | $21,000 | $33,000 | $24,870 | $42,000 | $20,000 | $69,000 |
| 0435 | Manholes, P-7, <10' (0425-2-41) | EACH | 5 | $5,400.00 | $8,900.00 | $9,785.00 | $8,500.00 | $15,000 | $7,100.00 |
| 0440 | Manholes, P-8, <10' (0425-2-61) | EACH | 5 | $7,500.00 | $10,200 | $12,277 | $7,000.00 | $15,000 | $10,600 |
| 0445 | Manholes, J-7, <10' (0425-2-71) | EACH | 6 | $17,300 | $21,400 | $20,013 | $24,000 | $20,000 | $53,000 |
| 0450 | Manholes, J-7, >10' (0425-2-72) | EACH | 2 | $19,000 | $23,800 | $21,755 | $31,000 | $20,000 | $35,000 |
| 0455 | Manholes, J-8, <10' (0425-2-91) | EACH | 2 | $11,700 | $8,900.00 | $14,555 | $15,000 | $20,000 | $19,000 |
| 0460 | Yard drain (0425-10) | EACH | 1 | $1,700.00 | $4,600.00 | $3,706.00 | $4,500.00 | $2,500.00 | $9,300.00 |
| 0465 | Desilting pipe, 0 - 24" (0430-94-1) | LF | 2,961 | $5.00 | $5.00 | $26.00 | $15.00 | $40.00 | $4.20 |
| 0470 | Desilting pipe, 25 - 36" (0430-94-2) | LF | 1,845 | $6.00 | $7.00 | $29.00 | $18.00 | $40.00 | $6.50 |
| 0475 | Desilting pipe, 37 - 48" (0430-94-3) | LF | 16 | $7.00 | $9.00 | $337.00 | $30.00 | $100.00 | $9.00 |
| 0480 | Desilting pipe, 61" or greater (0430-94-5) | LF | 261 | $25.00 | $13.00 | $69.00 | $50.00 | $120.00 | $19.00 |
| 0485 | Pipe culvert,optional material,round, 15"S/CD (0430-175115) | LF | 10 | $270.00 | $520.00 | $344.00 | $180.00 | $180.00 | $572.00 |
| 0490 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 3,896 | $182.00 | $240.00 | $162.00 | $150.00 | $200.00 | $484.00 |
| 0495 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 2,395 | $195.00 | $205.00 | $136.00 | $180.00 | $220.00 | $426.00 |
| 0500 | Pipe culvert, opt material, round, 30"S/CD (0430-175130) | LF | 1,463 | $225.00 | $275.00 | $290.00 | $260.00 | $250.00 | $576.00 |
| 0505 | Pipe culvert, opt material, round, 36"S/CD (0430-175136) | LF | 695 | $275.00 | $330.00 | $406.00 | $330.00 | $300.00 | $756.00 |
| 0510 | Pipe culvert, opt material, round, 42"S/CD (0430-175142) | LF | 241 | $331.00 | $385.00 | $477.00 | $450.00 | $350.00 | $815.00 |
| 0515 | Pipe culvert, opt material, round, 48"S/CD (0430-175148) | LF | 91 | $403.00 | $450.00 | $308.00 | $550.00 | $400.00 | $985.00 |
| 0520 | Pipe culvert,optional material,other shape-elip/arch, 24"S/CD (0430-175224) | LF | 329 | $262.00 | $280.00 | $172.00 | $250.00 | $300.00 | $399.00 |
| 0525 | Pipe culvert, opt material, shape - elip/arch, 30"S/CD (0430-175230) | LF | 3,009 | $322.00 | $300.00 | $218.00 | $350.00 | $350.00 | $526.00 |
| 0530 | Pipe culvert, opt material, shape - elip/arch, 36"S/CD (0430-175236) | LF | 1,210 | $415.00 | $365.00 | $297.00 | $450.00 | $400.00 | $677.00 |
| 0535 | Pipe culvert, opt material, shape - elip/arch, 42"S/CD (0430-175242) | LF | 773 | $517.00 | $435.00 | $401.00 | $650.00 | $400.00 | $744.00 |
| 0540 | Pipe culvert, opt material, shape - elip/arch, 48"S/CD (0430-175248) | LF | 924 | $598.00 | $550.00 | $530.00 | $800.00 | $450.00 | $894.00 |
| 0545 | Pipe filling and plugging- place out of service (0430-830) | CY | 1,443.10 | $339.00 | $265.00 | $279.00 | $700.00 | $450.00 | $374.00 |
| 0550 | Mitered end section, optional round, 18" CD (0430-982125) | EACH | 5 | $1,800.00 | $3,075.00 | $2,455.00 | $3,200.00 | $5,000.00 | $4,100.00 |
| 0555 | Mitered end section, optional round, 48" CD (0430-982141) | EACH | 1 | $7,500.00 | $9,600.00 | $13,000 | $14,000 | $15,000 | $16,300 |
| 0560 | Mitered end section, optional - elliptical / arch, 24" CD (0430-982629) | EACH | 1 | $2,500.00 | $3,330.00 | $5,680.00 | $4,000.00 | $10,000 | $6,400.00 |
| 0565 | Mitered end section, optional - elliptical / arch, 48" CD (0430-982641) | EACH | 1 | $9,300.00 | $8,500.00 | $15,055 | $13,000 | $15,000 | $14,500 |
| 0570 | Mitered end section, optional round, 18" SD (0430-984125) | EACH | 8 | $1,800.00 | $3,075.00 | $2,413.00 | $3,500.00 | $5,000.00 | $5,600.00 |
| 0575 | Mitered end section, optional round, 24" SD (0430-984129) | EACH | 5 | $2,100.00 | $3,400.00 | $2,630.00 | $4,000.00 | $7,500.00 | $5,900.00 |
| 0580 | Sheet piling steel, F&I (0455-133-3) | SF | 413 | $217.00 | $175.00 | $206.00 | $160.00 | $300.00 | $162.00 |
| 0585 | Pipe handrail - guiderail, steel (0515-1-1) | LF | 696 | $71.00 | $76.00 | $74.00 | $80.00 | $130.00 | $78.00 |
| 0590 | Pedestrian / bicycle railing, steel, 42" type 1 (0515-2211) | LF | 674 | $99.00 | $107.00 | $117.00 | $110.00 | $150.00 | $123.00 |
| 0595 | Bollards (0519-78) | EACH | 15 | $750.00 | $1,200.00 | $727.00 | $700.00 | $5,000.00 | $1,830.00 |
| 0600 | Concrete curb & gutter, type E (0520-1-7) | LF | 4,414 | $47.00 | $55.70 | $55.00 | $45.00 | $50.00 | $87.00 |
| 0605 | Concrete curb & gutter, type F (0520-1-10) | LF | 8,021 | $48.00 | $38.00 | $55.00 | $35.00 | $50.00 | $96.00 |
| 0610 | Concrete curb, type D (0520-2-4) | LF | 397 | $35.00 | $23.50 | $42.00 | $30.00 | $50.00 | $97.00 |
| 0615 | Traffic separator concrete- type I, 4' wide (0520-5-11) | LF | 468 | $81.00 | $51.00 | $99.55 | $60.00 | $80.00 | $144.00 |
| 0620 | Traffic separator concrete- type I, 6' wide (0520-5-12) | LF | 1,441 | $87.00 | $61.50 | $148.00 | $90.00 | $100.00 | $123.00 |
| 0625 | Traffic separator concrete- type I, 8.5' wide (0520-5-16) | LF | 168 | $105.00 | $87.15 | $213.00 | $135.00 | $110.00 | $178.00 |
| 0630 | Concrete traffic separator, special- variable width (0520-70) | SY | 914 | $147.00 | $114.75 | $222.00 | $100.00 | $110.00 | $192.00 |
| 0635 | Median concrete barrier, grade-separated (0521-1-12) | LF | 158 | $206.00 | $660.00 | $591.00 | $700.00 | $600.00 | $457.00 |
| 0640 | Concrete traffic railing barrier, with junction slab, 32" vertical face (0521-8-3) | LF | 254 | $524.00 | $490.00 | $966.00 | $600.00 | $750.00 | $900.00 |
| 0645 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 5,041 | $68.00 | $46.75 | $75.00 | $85.00 | $110.00 | $98.00 |
| 0650 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 1,866 | $81.00 | $64.50 | $100.00 | $120.00 | $120.00 | $203.00 |
| 0655 | Bus shelter pad- concrete (0522-4) | SY | 13 | $242.00 | $112.50 | $186.00 | $160.00 | $250.00 | $262.00 |
| 0660 | Concrete ditch pavt, non reinforced, 3" (0524-1-1) | SY | 78 | $86.00 | $78.30 | $107.00 | $120.00 | $100.00 | $220.00 |
| 0665 | Concrete ditch pavement, non reinforced, 6" (0524-1-4) | SY | 340 | $136.00 | $80.10 | $136.00 | $150.00 | $120.00 | $160.00 |
| 0670 | Concrete slope pavement,non reinforced, 3" (0524-2-1) | SY | 34 | $163.00 | $105.75 | $237.00 | $120.00 | $120.00 | $235.00 |
| 0675 | Detectable warnings (0527-2) | SF | 1,200 | $45.00 | $30.75 | $32.00 | $30.00 | $50.00 | $53.00 |
| 0680 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 37 | $215.00 | $430.00 | $185.00 | $300.00 | $200.00 | $245.00 |
| 0685 | Bedding stone (0530-74) | TN | 26 | $286.00 | $620.00 | $155.00 | $250.00 | $200.00 | $269.00 |
| 0690 | Guardrail removal (0536-73) | LF | 104 | $4.65 | $3.00 | $8.00 | $5.00 | $5.00 | $23.00 |
| 0695 | Crash cushion, TL-2, narrow (0544-2-1) | EACH | 1 | $21,800 | $24,000 | $25,000 | $55,000 | $35,000 | $26,000 |
| 0700 | Performance turf, sod (0570-1-2) | SY | 24,412 | $6.25 | $6.25 | $8.75 | $8.00 | $6.00 | $3.75 |
| 0705 | Performance turf, sod and shoulder treatment index (0570-1-3) | SY | 9 | $186.00 | $6.25 | $129.00 | $10.00 | $15.00 | $22.00 |
| 0710 | Raised pavement marker, type B (0706-1-3) | EACH | 8,004 | $3.80 | $3.70 | $3.70 | $5.00 | $3.70 | $4.00 |
| 0715 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 24.12 | $1,920.00 | $1,874.46 | $1,875.00 | $1,825.00 | $1,875.00 | $2,000.00 |
| 0720 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 0.18 | $2,550.00 | $2,479.89 | $2,535.00 | $2,250.00 | $2,535.00 | $2,600.00 |
| 0725 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 9,033 | $1.35 | $1.30 | $1.30 | $1.00 | $1.30 | $1.40 |
| 0730 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 1,489 | $1.45 | $1.40 | $1.40 | $1.50 | $1.40 | $1.50 |
| 0735 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 8,166 | $1.55 | $1.50 | $1.50 | $2.00 | $1.50 | $1.60 |
| 0740 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 5.06 | $510.00 | $499.31 | $500.00 | $700.00 | $500.00 | $525.00 |
| 0745 | Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide, (0710-11133) | GM | 0.10 | $960.00 | $937.50 | $1,000.00 | $1,100.00 | $1,000.00 | $1,050.00 |
| 0750 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 2.73 | $662.00 | $648.57 | $650.00 | $800.00 | $650.00 | $683.00 |
| 0755 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 209 | $36.00 | $35.00 | $35.00 | $65.00 | $35.00 | $37.00 |
| 0760 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 551 | $36.00 | $35.00 | $35.00 | $40.00 | $35.00 | $37.00 |
| 0765 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 20.50 | $1,920.00 | $1,874.82 | $1,875.00 | $1,800.00 | $1,875.00 | $2,000.00 |
| 0770 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 3,005 | $1.55 | $1.50 | $1.55 | $1.50 | $1.50 | $1.60 |
| 0775 | Painted pavement markings, standard, yellow, skip, 6" (0710-11231) | GM | 0.23 | $506.00 | $495.69 | $6,555.00 | $700.00 | $500.00 | $525.00 |
| 0780 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 1.23 | $661.00 | $646.82 | $1,855.00 | $850.00 | $650.00 | $683.00 |
| 0786 | Temporary pedestrian access (0926-102-1) | SFD | 26,096 | $0.41 | $1.70 | $0.60 | $1.00 | $2.00 | $2.70 |
| 0790 | Disputes review board, meeting- DO not bid (0999-20-1) | DA | 62 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 |
| 0795 | Disputes review board, hearing- DO not bid (0999-20-2) | EACH | 2 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 |
| 0800 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $70,000 | $70,000 | $70,000 | $70,000 | $70,000 | $70,000 |
| 0805 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 |
| 0810 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $70,000 | $70,000 | $70,000 | $70,000 | $70,000 | $70,000 |
| 0815 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 137 | $460.00 | $575.00 | $450.00 | $585.00 | $450.00 | $614.00 |
| 0820 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 36 | $1,850.00 | $2,150.00 | $1,800.00 | $2,650.00 | $1,800.00 | $2,800.00 |
| 0825 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 5 | $3,100.00 | $2,550.00 | $3,000.00 | $3,350.00 | $3,000.00 | $3,500.00 |
| 0830 | Single column ground sign assembly, F&I barrier less than 12 SF (0700-1311) | EACH | 6 | $3,600.00 | $3,250.00 | $3,500.00 | $3,500.00 | $3,500.00 | $3,700.00 |
| 0835 | Single column ground sign assembly, F&I barrier 12.0-20.0 SF (0700-1312) | EACH | 2 | $3,800.00 | $3,550.00 | $3,700.00 | $4,200.00 | $3,700.00 | $4,400.00 |
| 0840 | Single column ground sign assembly, relocate (0700-1500) | EACH | 26 | $256.00 | $1,300.00 | $250.00 | $250.00 | $250.00 | $263.00 |
| 0845 | Single column ground sign assembly, remove (0700-1600) | EACH | 173 | $16.00 | $40.00 | $15.00 | $75.00 | $15.00 | $79.00 |
| 0850 | Single column ground sign assembly, F&I cantilever mount, 12.0-20.0 SF (0700-1912) | EACH | 1 | $4,100.00 | $3,350.00 | $4,000.00 | $4,100.00 | $4,000.00 | $4,300.00 |
| 0855 | Single column ground sign assembly, F&I cantilever mount, 20.1-30.0 SF (0700-1913) | EACH | 1 | $4,200.00 | $3,550.00 | $4,100.00 | $4,600.00 | $4,100.00 | $4,830.00 |
| 0860 | Multi-column ground sign assembly, F&I ground mount, 20.0 SF (0700-2112) | EACH | 3 | $6,200.00 | $5,000.00 | $6,000.00 | $6,600.00 | $6,000.00 | $6,930.00 |
| 0865 | Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114) | EACH | 2 | $8,700.00 | $9,000.00 | $8,500.00 | $8,850.00 | $8,500.00 | $9,292.50 |
| 0870 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 4 | $1,550.00 | $750.00 | $1,500.00 | $2,000.00 | $1,500.00 | $2,100.00 |
| 0875 | Sign panel, relocate, UP to 12 SF (0700-3501) | EACH | 4 | $103.00 | $250.00 | $100.00 | $75.00 | $100.00 | $79.00 |
| 0880 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 1 | $10.50 | $40.00 | $10.00 | $30.00 | $10.00 | $32.00 |
| 0885 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 45 | $103.00 | $100.00 | $110.00 | $125.00 | $100.00 | $132.00 |
| 0890 | Tubular marker, 36" white post (0704-1-3) | EACH | 9 | $179.00 | $300.00 | $185.00 | $185.00 | $175.00 | $195.00 |
| 0895 | Tubular marker, 36" yellow (0704-1-4) | EACH | 35 | $179.00 | $300.00 | $185.00 | $185.00 | $175.00 | $195.00 |
| 0900 | Object marker, type 1 (0705-10-1) | EACH | 26 | $286.00 | $225.00 | $285.00 | $225.00 | $280.00 | $240.00 |
| 0905 | Delineator, flexible tubular (0705-11-1) | EACH | 20 | $103.00 | $125.00 | $105.00 | $125.00 | $100.00 | $130.00 |
| 0910 | Raised pavement marker, type B (0706-1-3) | EACH | 3,065 | $3.80 | $3.70 | $3.75 | $4.00 | $3.70 | $4.00 |
| 0915 | Painted pavement markings, standard, yellow, island nose (0710-11290) | SF | 45 | $4.10 | $4.00 | $4.00 | $5.00 | $4.00 | $4.20 |
| 0920 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 158 | $4.60 | $4.50 | $4.50 | $5.00 | $4.50 | $4.75 |
| 0925 | Painted pavement markings, surface (0710-90) | LS | 1 | $54,000 | $57,447 | $58,000 | $31,000 | $57,447 | $60,000 |
| 0930 | Painted pavement markings, surface (0710-90) | LS | 1 | $38,000 | $40,062 | $41,000 | $16,000 | $40,062 | $42,000 |
| 0935 | Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102) | GM | 0.23 | $6,500.00 | $6,325.00 | $6,555.00 | $8,500.00 | $6,555.00 | $6,900.00 |
| 0940 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 4,802 | $3.25 | $3.15 | $3.16 | $4.50 | $3.15 | $3.30 |
| 0945 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 971 | $4.90 | $4.75 | $4.75 | $7.00 | $4.75 | $5.00 |
| 0950 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 908 | $6.45 | $6.30 | $6.30 | $8.00 | $6.30 | $6.60 |
| 0955 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 1.92 | $1,890.00 | $1,846.27 | $1,855.00 | $3,200.00 | $1,854.00 | $1,950.00 |
| 0960 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 20 | $89.00 | $87.00 | $87.00 | $160.00 | $87.00 | $92.00 |
| 0965 | Thermoplastic, standard, arrow (0711-11170) | EACH | 183 | $59.00 | $57.00 | $57.00 | $125.00 | $57.00 | $60.00 |
| 0970 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 1,558 | $4.45 | $4.35 | $4.35 | $7.00 | $4.35 | $4.60 |
| 0975 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.76 | $1,750.00 | $1,700.00 | $1,700.00 | $3,200.00 | $1,700.00 | $1,800.00 |
| 0980 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 3,476 | $16.70 | $16.27 | $16.30 | $14.50 | $16.27 | $17.00 |
| 0985 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 88 | $225.00 | $220.00 | $220.00 | $300.00 | $220.00 | $230.00 |
| 0990 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 90 | $94.00 | $92.00 | $92.00 | $200.00 | $92.00 | $97.00 |
| 0995 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 9.36 | $5,050.00 | $4,911.80 | $4,917.00 | $5,700.00 | $4,916.00 | $5,200.00 |
| 1000 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 2.73 | $1,260.00 | $1,225.85 | $1,230.00 | $1,400.00 | $1,229.00 | $1,300.00 |
| 1005 | Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133) | GM | 0.25 | $2,500.00 | $2,448.21 | $2,458.00 | $8,000.00 | $2,458.00 | $2,600.00 |
| 1010 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 6.59 | $4,650.00 | $4,516.31 | $4,517.00 | $5,700.00 | $4,517.00 | $4,800.00 |
| 1015 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 0.40 | $1,150.00 | $1,107.29 | $1,130.00 | $1,400.00 | $1,130.00 | $1,200.00 |
| 1020 | Green-colored pavement markings, bike lane (0714-10) | SF | 1,474 | $12.00 | $11.40 | $10.55 | $15.00 | $15.00 | $16.00 |
| 1025 | Conduit, furnish & install, open trench (0630-2-11) | LF | 5 | $71.00 | $24.49 | $25.00 | $25.00 | $24.49 | $26.00 |
| 1030 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 467 | $24.50 | $27.50 | $28.00 | $7.50 | $27.50 | $29.00 |
| 1035 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 3 | $2,600.00 | $1,005.34 | $1,006.00 | $1,000.00 | $1,005.35 | $1,050.00 |
| 1040 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 1,608 | $3.10 | $2.12 | $2.13 | $2.10 | $2.12 | $2.25 |
| 1045 | Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 0' arm length (0715-61400) | EACH | 2 | $8,200.00 | $9,915.06 | $9,916.00 | $10,000 | $9,915.06 | $10,400 |
| 1050 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 2 | $900.00 | $694.38 | $695.00 | $700.00 | $694.38 | $730.00 |
| 1055 | Existing ITS maintenance (0102-112) | DA | 905 | $122.00 | $175.00 | $43.00 | $43.00 | $150.00 | $53.00 |
| 1060 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 0.84 | $4,600.00 | $5,306.37 | $5,332.00 | $5,400.00 | $5,331.64 | $6,000.00 |
| 1065 | Itsfm location documentation- intersection (0611-2-1) | EACH | 1 | $2,900.00 | $3,297.20 | $3,296.00 | $3,350.00 | $3,297.20 | $4,000.00 |
| 1070 | Itsfm location documentation- ITS site (0611-2-2) | EACH | 1 | $2,200.00 | $2,490.44 | $2,491.00 | $2,550.00 | $2,490.44 | $2,600.00 |
| 1075 | Conduit, furnish & install, open trench (0630-2-11) | LF | 2,435 | $25.00 | $28.34 | $28.55 | $32.00 | $28.34 | $30.00 |
| 1080 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 2,980 | $52.00 | $44.11 | $44.25 | $50.00 | $44.11 | $46.00 |
| 1085 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 4 | $16,700 | $11,658 | $11,659 | $13,000 | $11,658 | $12,300 |
| 1090 | Signal cable, remove- intersection (0632-7-6) | PI | 3 | $790.00 | $775.60 | $776.00 | $870.00 | $775.60 | $815.00 |
| 1095 | Fiber optic cable, F&I, underground,2-12 fibers (0633-1121) | LF | 415 | $4.35 | $4.91 | $5.00 | $5.50 | $4.91 | $5.00 |
| 1100 | Fiber optic cable, F&I, underground, 97 - 144 fibers (0633-1124) | LF | 6,563 | $6.10 | $6.95 | $6.95 | $7.80 | $6.95 | $7.00 |
| 1105 | Fiber optic cable, remove, underground (0633-1620) | LF | 4,646 | $1.60 | $1.75 | $1.75 | $2.00 | $1.75 | $1.80 |
| 1110 | Fiber optic connection, install, splice (0633-2-31) | EACH | 452 | $55.00 | $63.14 | $64.00 | $71.00 | $63.14 | $66.00 |
| 1115 | Fiber optic connection hardware, F&I, splice (0633-3-11) | EACH | 5 | $1,460.00 | $1,683.68 | $1,684.00 | $1,900.00 | $1,683.68 | $1,800.00 |
| 1120 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 49 | $61.00 | $70.15 | $71.00 | $79.00 | $70.15 | $74.00 |
| 1125 | Fiber optic connection hardware, F&I, preterminated connector assembly (0633-3-13) | EACH | 3 | $92.00 | $105.23 | $106.00 | $120.00 | $105.23 | $111.00 |
| 1130 | Fiber optic connection hardware, F&I, buffer tube fan out kit (0633-3-14) | EACH | 5 | $104.00 | $119.26 | $120.00 | $135.00 | $119.26 | $125.00 |
| 1135 | Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16) | EACH | 3 | $2,400.00 | $2,735.97 | $2,736.00 | $3,100.00 | $2,735.97 | $2,900.00 |
| 1140 | Fiber optic cable locator (0633-6) | DA | 1,810 | $140.00 | $175.00 | $175.00 | $200.00 | $250.00 | $184.00 |
| 1145 | Multi-conductor cable, furnish & install, composite (0633-8-12) | LF | 689 | $4.50 | $4.28 | $4.29 | $5.00 | $4.28 | $4.50 |
| 1150 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 3 | $1,350.00 | $1,489.67 | $1,490.00 | $1,700.00 | $1,489.67 | $1,600.00 |
| 1155 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 16 | $3,200.00 | $2,976.00 | $2,977.00 | $3,400.00 | $2,976.00 | $3,200.00 |
| 1160 | Pull & splice box, F&I, 30" X 60" rectangular or 36" round size (0635-2-13) | EACH | 3 | $6,100.00 | $6,309.86 | $6,310.00 | $7,100.00 | $6,309.86 | $6,600.00 |
| 1165 | Pull & splice box, F&I, 17" X 30" cover size (0635-2-14) | EACH | 19 | $2,600.00 | $1,858.51 | $1,859.00 | $2,100.00 | $1,858.51 | $1,950.00 |
| 1170 | Electrical power service, F&I, underground, meter furnished by power company (0639-1121) | AS | 2 | $9,800.00 | $7,324.50 | $7,325.00 | $8,300.00 | $7,324.50 | $7,700.00 |
| 1175 | Electrical service wire, & install (0639-2-1) | LF | 88 | $7.65 | $11.65 | $11.66 | $13.00 | $11.65 | $12.00 |
| 1180 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 1 | $3,300.00 | $2,460.26 | $2,461.00 | $2,800.00 | $2,460.26 | $2,600.00 |
| 1185 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 3 | $3,100.00 | $1,726.34 | $1,727.00 | $2,000.00 | $1,726.34 | $1,800.00 |
| 1190 | Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60) | EACH | 1 | $592.00 | $1,589.23 | $1,590.00 | $1,800.00 | $1,589.23 | $1,700.00 |
| 1195 | Aluminum signals pole, (0646-1-11) | EACH | 23 | $2,300.00 | $2,490.01 | $2,491.00 | $2,800.00 | $2,490.01 | $2,600.00 |
| 1200 | Aluminum signals pole, furnish install pedestrian detector post (0646-1-12) | EACH | 1 | $2,200.00 | $1,890.78 | $1,891.00 | $2,200.00 | $1,890.78 | $2,000.00 |
| 1205 | Aluminum signals pole, remove (0646-1-60) | EACH | 10 | $495.00 | $439.47 | $440.00 | $500.00 | $439.47 | $460.00 |
| 1210 | Steel mast arm assembly, and install, single arm 50' (0649-21-6) | EACH | 3 | $58,000 | $67,579 | $67,560 | $76,000 | $100,000 | $71,000 |
| 1215 | Steel mast arm assembly, and install, single arm 60' (0649-21-10) | EACH | 2 | $72,500 | $85,352 | $85,352 | $96,000 | $123,000 | $90,000 |
| 1220 | Steel mast arm assembly, remove, deep foundation- bolt on attachment (0649-26-5) | EACH | 4 | $3,600.00 | $18,964 | $18,965 | $22,000 | $18,964 | $20,000 |
| 1225 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 11 | $1,450.00 | $1,598.30 | $1,599.00 | $1,800.00 | $1,598.30 | $1,700.00 |
| 1230 | Vehicular traffic signal, furnish & install aluminum, 4 section, 1 way (0650-1-16) | AS | 3 | $1,900.00 | $1,981.84 | $1,982.00 | $2,300.00 | $1,981.84 | $2,100.00 |
| 1235 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 22 | $810.00 | $928.18 | $930.00 | $1,100.00 | $928.18 | $975.00 |
| 1240 | Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12) | AS | 2 | $1,720.00 | $1,748.11 | $1,749.00 | $2,000.00 | $1,748.11 | $1,850.00 |
| 1245 | Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60) | AS | 13 | $99.00 | $189.44 | $190.00 | $215.00 | $189.44 | $200.00 |
| 1250 | Midblock crosswalk: hybrid beacon assembly, & install complete assembly (0654-3-10) | AS | 4 | $2,150.00 | $4,173.60 | $4,174.00 | $4,700.00 | $4,173.60 | $4,400.00 |
| 1255 | Loop detector inductive, F&I, type 9 (0660-1109) | EACH | 13 | $315.00 | $562.93 | $563.00 | $650.00 | $562.93 | $600.00 |
| 1260 | Loop detector inductive, F&I, type 10 (0660-1110) | EACH | 4 | $357.00 | $652.00 | $652.00 | $740.00 | $652.00 | $700.00 |
| 1265 | Loop assembly- F&I, type A (0660-2101) | AS | 33 | $1,950.00 | $1,535.01 | $1,536.00 | $1,800.00 | $1,535.01 | $1,600.00 |
| 1270 | Vehicle detection system- microwave, furnish & install cabinet equipment (0660-3-11) | EACH | 1 | $9,800.00 | $9,317.96 | $9,318.00 | $10,500 | $9,317.96 | $9,800.00 |
| 1275 | Vehicle detection system- microwave, furnish & install, above ground equipment (0660-3-12) | EACH | 4 | $9,600.00 | $9,309.26 | $9,310.00 | $10,500 | $9,309.26 | $9,800.00 |
| 1280 | Vehicle detection system- furnish & install cabinet equipment (0660-4-11) | EACH | 1 | $8,100.00 | $7,493.97 | $7,494.00 | $8,500.00 | $7,493.97 | $7,900.00 |
| 1285 | Vehicle detection system- furnish & install above ground equipment (0660-4-12) | EACH | 4 | $10,250 | $10,011 | $10,011 | $11,300 | $10,011 | $10,500 |
| 1290 | Vehicle detection system- adjust/modify cabinet (0660-4-51) | EACH | 1 | $1,650.00 | $1,080.89 | $1,081.00 | $1,300.00 | $1,080.89 | $1,200.00 |
| 1295 | Signal priority and preemption system, F&I, optical, cabinet electronics (0663-1111) | EACH | 2 | $8,300.00 | $7,972.14 | $7,973.00 | $9,000.00 | $7,972.14 | $8,400.00 |
| 1300 | Signal priority and preemption system, F&I, optical, detector (0663-1112) | EACH | 6 | $3,050.00 | $3,263.89 | $3,264.00 | $3,700.00 | $3,263.89 | $3,500.00 |
| 1305 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 26 | $350.00 | $305.92 | $306.00 | $350.00 | $305.92 | $320.00 |
| 1310 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 5 | $99.00 | $55.09 | $56.00 | $62.00 | $55.09 | $58.00 |
| 1315 | Traffic controller assembly, F&I, NEMA W/standard lock, 2 preemption (0670-5162) | AS | 2 | $53,800 | $54,420 | $54,420 | $62,000 | $77,000 | $57,000 |
| 1320 | Traffic controller assembly, remove controller with (0670-5600) | AS | 1 | $790.00 | $605.91 | $606.00 | $700.00 | $605.91 | $636.00 |
| 1325 | Traffic controller, modify (0671-2-40) | EACH | 2 | $5,900.00 | $3,919.95 | $3,920.00 | $4,500.00 | $3,919.95 | $4,100.00 |
| 1330 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 2 | $5,550.00 | $5,550.32 | $5,551.00 | $6,300.00 | $5,550.32 | $5,900.00 |
| 1335 | Uninterruptible power supply, furnish and install, online/double conversion with cabinet (0685-1-14) | EACH | 2 | $16,000 | $11,995 | $11,996 | $13,500 | $11,995 | $12,600 |
| 1340 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 5 | $2,500.00 | $2,777.87 | $2,778.00 | $3,200.00 | $2,777.87 | $3,000.00 |
| 1345 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 10 | $2,550.00 | $2,354.00 | $2,355.00 | $2,700.00 | $2,354.00 | $2,500.00 |
| 1350 | Traffic monitoring site cabinet, furnish & install, type 3, pedestal mount (0695-7132) | EACH | 3 | $8,100.00 | $7,706.52 | $7,707.00 | $8,700.00 | $7,706.52 | $9,100.00 |
| 1355 | Traffic monitoring site cabinet, remove existing cabinet (0695-7600) | EACH | 1 | $790.00 | $573.64 | $574.00 | $650.00 | $573.64 | $600.00 |
| 1360 | Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22) | EACH | 4 | $3,450.00 | $5,624.01 | $5,625.00 | $6,400.00 | $5,624.01 | $6,000.00 |
| 1365 | Enhanced highway sign AC powered, F&I overhead highlighted sign <12 SF (0700-141340) | EACH | 1 | $6,200.00 | $8,450.26 | $8,451.00 | $9,500.00 | $8,450.26 | $8,900.00 |
| 1370 | Enhanced highway sign AC powered, F&I overhead blank out sign <12 SF (0700-141360) | EACH | 1 | $6,400.00 | $7,889.02 | $7,890.00 | $9,900.00 | $7,889.02 | $8,300.00 |
| 1375 | Concrete class NS, steps (0400-0-13) | CY | 3 | $1,450.00 | $4,500.00 | $1,839.00 | $750.00 | $3,000.00 | $2,000.00 |
| 1380 | Special drainage structure, utility conflict manhole (0425-100-24) | EACH | 1 | $12,200 | $12,000 | $15,467 | $9,000.00 | $30,000 | $29,000 |
| 1385 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $53,050 | $53,050 | $53,050 | $53,050 | $53,050 | $53,050 |
| 1390 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $8,200.00 | $8,200.00 | $8,200.00 | $8,200.00 | $8,200.00 | $8,200.00 |
| 1395 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 1400 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $5,820.00 | $5,820.00 | $5,820.00 | $5,820.00 | $5,820.00 | $5,820.00 |
| 1405 | Utility pipe, install, 0-1.9" (1050-13001) | LF | 200 | $52.00 | $159.00 | $108.00 | $100.00 | $150.00 | $208.00 |
| 1410 | Utility pipe, install, 2-4.9" (1050-13002) | LF | 150 | $60.00 | $185.00 | $147.00 | $110.00 | $150.00 | $214.00 |
| 1415 | Utility pipe,remove & dispose, 0 1.9" (1050-16001) | LF | 397 | $24.00 | $20.00 | $53.00 | $24.00 | $50.00 | $24.00 |
| 1420 | Utility pipe,remove & dispose, 2- 4.9" (1050-16002) | LF | 239 | $37.00 | $20.00 | $66.00 | $30.00 | $50.00 | $25.00 |
| 1425 | Utility pipe,remove & dispose, 5- 7.9" (1050-16003) | LF | 2,637 | $42.00 | $35.00 | $67.00 | $29.00 | $50.00 | $21.00 |
| 1430 | Utility pipe,remove & dispose, 8- 19.9" (1050-16004) | LF | 3,073 | $49.00 | $88.00 | $67.00 | $37.00 | $75.00 | $30.00 |
| 1435 | Utility pipe,plug & place out of service, 2- 4.9" (1050-18002) | LF | 499 | $21.00 | $10.00 | $21.00 | $10.00 | $50.00 | $3.50 |
| 1445 | Utility pipe,plug & place out of service, 8-19.9" (1050-18004) | LF | 2,955 | $47.00 | $25.00 | $26.00 | $28.00 | $50.00 | $7.00 |
| 1446 | Utility pipe- poly vinyl chloride, furnish & install, water/sewer, (1050-31202) | LF | 28 | $97.00 | $150.00 | $200.00 | $110.00 | $100.00 | $353.00 |
| 1455 | Utility pipe- poly vinyl chloride, furnish & install, water/sewer, (1050-31204) | LF | 67 | $124.00 | $420.00 | $208.00 | $250.00 | $100.00 | $265.00 |
| 1460 | Utility pipe- poly vinyl chloride, furnish & install, water/sewer, (1050-31206) | LF | 82 | $187.00 | $180.00 | $179.00 | $190.00 | $150.00 | $161.00 |
| 1465 | Utility pipe- poly vinyl chloride, furnish & install, water/sewer, (1050-31208) | LF | 943 | $104.00 | $185.00 | $95.00 | $92.00 | $175.00 | $475.00 |
| 1466 | Utility pipe- poly vinyl chloride, furnish & install, water/sewer, 10" (1050-31210) | LF | 112 | $105.00 | $325.00 | $252.00 | $95.00 | $200.00 | $2,500.00 |
| 1470 | Utility pipe- poly vinyl chloride, furnish & install, water/sewer, 12" (1050-31212) | LF | 23 | $220.00 | $1,300.00 | $303.00 | $160.00 | $250.00 | $5,100.00 |
| 1485 | Utility pipe- polyethylene, furnish & install, 4" (1050-41104) | LF | 50 | $85.00 | $40.00 | $130.00 | $40.00 | $200.00 | $82.00 |
| 1490 | Utility pipe- high density polyethylene, furnish & install, water/sewer, 2" (1050-42202) | LF | 346 | $73.00 | $75.00 | $67.00 | $65.00 | $100.00 | $108.00 |
| 1495 | Utility pipe- high density polyethylene, furnish & install, water/sewer, 6" (1050-42206) | LF | 445 | $87.00 | $105.00 | $239.00 | $248.00 | $125.00 | $255.00 |
| 1500 | Utility pipe- high density polyethylene, furnish & install, water/sewer, 10" (1050-42210) | LF | 560 | $142.00 | $135.00 | $287.00 | $300.00 | $200.00 | $280.00 |
| 1505 | Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 6" (1050-51206) | LF | 187 | $220.00 | $275.00 | $161.00 | $140.00 | $150.00 | $700.00 |
| 1510 | Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 8" (1050-51208) | LF | 1,361 | $145.00 | $160.00 | $123.00 | $125.00 | $200.00 | $430.00 |
| 1515 | Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 10" (1050-51210) | LF | 13 | $274.00 | $230.00 | $481.00 | $130.00 | $300.00 | $460.00 |
| 1520 | Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 12" (1050-51212) | LF | 1,109 | $228.00 | $250.00 | $155.00 | $190.00 | $300.00 | $597.00 |
| 1525 | Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 16" (1050-51216) | LF | 895 | $288.00 | $350.00 | $202.00 | $259.00 | $350.00 | $668.00 |
| 1530 | Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 18" (1050-51218) | LF | 110 | $400.00 | $575.00 | $320.00 | $380.00 | $500.00 | $2,655.00 |
| 1535 | Utility fittings for PVC pipe, furnish and install, cap/plug, 8" (1055-31508) | EACH | 3 | $497.00 | $400.00 | $1,513.00 | $600.00 | $5,000.00 | $1,052.00 |
| 1540 | Utility fittings for PVC pipe, furnish and install, cap/plug, (1055-31512) | EACH | 2 | $765.00 | $585.00 | $1,706.00 | $1,000.00 | $5,000.00 | $1,300.00 |
| 1545 | Utility fittings for PVC pipe, furnish and install, cap/plug, (1055-31516) | EACH | 20 | $1,450.00 | $1,000.00 | $2,756.00 | $1,800.00 | $5,000.00 | $1,900.00 |
| 1550 | Utility fittings, ductile iron, furnish & install elbow, 8" (1055-51108) | EACH | 39 | $1,670.00 | $800.00 | $1,896.00 | $850.00 | $5,000.00 | $735.00 |
| 1555 | Utility fittings, ductile iron, furnish & install elbow, (1055-51110) | EACH | 3 | $774.00 | $850.00 | $1,887.00 | $900.00 | $5,000.00 | $700.00 |
| 1560 | Utility fittings, ductile iron, furnish & install elbow, (1055-51112) | EACH | 49 | $2,200.00 | $1,500.00 | $2,192.00 | $1,300.00 | $5,000.00 | $1,020.00 |
| 1565 | Utility fittings, ductile iron, furnish & install elbow, (1055-51116) | EACH | 24 | $2,500.00 | $2,200.00 | $3,535.00 | $2,500.00 | $7,500.00 | $2,020.00 |
| 1570 | Utility fittings, ductile iron, furnish & install elbow, (1055-51118) | EACH | 9 | $4,600.00 | $2,750.00 | $4,176.00 | $3,500.00 | $10,000 | $2,700.00 |
| 1575 | Utility fittings, ductile iron, furnish & install tee, 8" (1055-51208) | EACH | 3 | $980.00 | $1,250.00 | $3,217.00 | $1,100.00 | $5,000.00 | $775.00 |
| 1580 | Utility fittings, ductile iron, furnish & install tee, 12" (1055-51212) | EACH | 3 | $1,700.00 | $2,000.00 | $2,990.00 | $2,000.00 | $5,000.00 | $1,600.00 |
| 1585 | Utility fittings, ductile iron, furnish & install tee, 16" (1055-51216) | EACH | 4 | $2,900.00 | $2,750.00 | $4,690.00 | $3,000.00 | $12,000 | $2,400.00 |
| 1590 | Utility fittings, ductile iron, furnish & install reducer, 10" (1055-51310) | EACH | 2 | $940.00 | $1,000.00 | $1,785.00 | $850.00 | $5,000.00 | $580.00 |
| 1595 | Utility structure, below ground, F&I, water / sewer > 80 FT3, > 12' (1060-11223) | EACH | 3 | $8,500.00 | $15,000 | $13,611 | $10,500 | $25,000 | $36,000 |
| 1600 | Utility structure, below ground, adjust/modify (1060-15) | EACH | 1 | $5,400.00 | $8,500.00 | $33,325 | $4,600.00 | $5,000.00 | $5,700.00 |
| 1605 | Utility fixture, valve assembly, furnish and install, 4" (1080-24104) | EACH | 2 | $2,400.00 | $2,500.00 | $2,465.00 | $4,900.00 | $7,500.00 | $1,800.00 |
| 1610 | Utility fixture, valve assembly, furnish and install, 6" (1080-24106) | EACH | 4 | $2,500.00 | $3,500.00 | $2,340.00 | $6,100.00 | $7,500.00 | $2,000.00 |
| 1615 | Utility fixture, valve assembly, furnish and install, 8" (1080-24108) | EACH | 8 | $3,400.00 | $4,500.00 | $3,780.00 | $10,500 | $10,000 | $2,700.00 |
| 1620 | Utility fixture, valve assembly, furnish and install, 12" (1080-24112) | EACH | 4 | $5,900.00 | $5,500.00 | $6,482.00 | $8,000.00 | $10,000 | $5,200.00 |
| 1625 | Utility fixture, valve assembly, furnish and install, 16" (1080-24116) | EACH | 3 | $9,400.00 | $750.00 | $9,365.00 | $13,500 | $15,000 | $8,500.00 |
| 1630 | Utility fixture, vac/air furnish & install 2" (1080-26102) | EACH | 8 | $10,000 | $12,500 | $9,513.00 | $20,000 | $10,000 | $13,500 |
| 1635 | Utility fixture- sample point, furnish & install, 6" (1080-32106) | EACH | 1 | $1,300.00 | $750.00 | $2,880.00 | $2,600.00 | $2,500.00 | $850.00 |
| 1640 | Utility fixture- sample point, furnish & install, 8" (1080-32108) | EACH | 5 | $1,700.00 | $850.00 | $2,855.00 | $4,200.00 | $2,500.00 | $875.00 |
| 1645 | Utility fixture- sample point, furnish & install, 16" (1080-32116) | EACH | 1 | $2,900.00 | $950.00 | $3,270.00 | $4,100.00 | $5,000.00 | $1,200.00 |
| 1650 | Utility fixture, plug valve, furnish and install 8" (1080-33108) | EACH | 2 | $7,800.00 | $5,000.00 | $8,100.00 | $5,800.00 | $15,000 | $6,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of April 29, 2026. Compiled by Mirage Metrics.