TDOT contract CN263057 bid tabulation

The widening on s.r. 268 from u.s. 41 (u.s. 70s, s.r. 1, nw broad street) (l.m. 0.00) to u.s. 231 (s.r. 10, memorial boulevard) (l.m. 4.39), including bridges, retaining walls, signals, lighting, and paving. Let by Tennessee DOT on June 26, 2026, Rutherford County. 4 bids received; low bid $123,233,326 by Civil Constructors, LLC.

Owner
Tennessee DOT
Letting
26 JUN 2026
Pay items
575
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Civil Constructors, LLC$123,233,326Low
2Cleary Construction, Inc.$126,995,936+3.0%
3MasTec Civil, LLC$129,842,743+5.0%
4Jones Bros. Contractors, LLC$142,677,585+16%
TDOT contract CN263057: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Civil Constructors, LLC2. Cleary Construction, Inc.3. MasTec Civil, LLC4. Jones Bros. Contractors, LLC
1Construction stakes, lines and grades (105-01)LS1$783,450$675,000$1,220,000$975,000
2CPM project schedule (108-03)LS1$207,800$201,000$40,000$275,000
3Trainee (109-10.01)HR6,700$0.80$0.80$0.80$0.80
4Clearing and grubbing (201-01)LS1$532,943$1,538,000$1,160,000$9,900,000
5Removal of structures and obstructions (202-01)LS1$356,650$365,000$50,000$50,000
6Removal of pipe (8") (202-02.01)LF9$53.75$28.00$45.00$50.00
7Removal of pipe (12") (202-02.02)LF262$28.40$28.00$30.00$40.00
8Removal of pipe (15") (202-02.03)LF408$28.80$28.00$35.00$40.00
9Removal of pipe (18") (202-02.04)LF4,837$27.40$28.00$42.00$40.00
10Removal of pipe (24") (202-02.05)LF2,396$24.40$28.00$55.00$40.00
11Removal of pipe (30") (202-02.06)LF935$29.30$33.00$65.00$40.00
12Removal of pipe (36") (202-02.07)LF209$39.15$42.00$62.00$50.00
13Removal of pipe (60") (202-02.08)LF123$68.25$60.00$105.00$350.00
14Removal of pipe (22" X 14") (202-02.09)LF134$27.95$28.00$67.00$40.00
15Removal of pipe (24" X 18") (202-02.10)LF95$28.35$28.00$49.00$40.00
16Removal of pipe (30" X 20") (202-02.11)LF51$31.65$28.00$63.00$50.00
17Removal of pipe (30" X 24") (202-02.12)LF69$32.70$28.00$74.00$50.00
18Removal of pipe (30" X 18") (202-02.13)LF81$31.90$28.00$65.00$50.00
19Removal of pipe (48" X 30") (202-02.14)LF132$53.70$33.00$66.00$65.00
20Removal of rigid pavement, sidewalk, etc. (202-03)SY342$25.00$16.50$46.00$15.00
21Removal of asphalt pavement (202-03.01)SY16,491$8.80$5.15$19.00$10.00
22Road & drainage excavation (unclassified) (203-01)CY136,616$39.10$43.40$23.00$25.00
23Borrow excavation (graded solid rock) (203-02.01)TON132,885$35.25$24.50$30.00$30.00
24Borrow excavation (unclassified) (203-03)CY42,697$16.50$0.75$17.00$8.00
25Placing and spreading topsoil (203-04)CY15,553.52$34.70$28.00$17.00$15.00
26Undercutting (203-05)CY70,400$34.85$19.65$24.00$18.00
27Water (203-06)MG1,299$10.00$67.75$28.00$1.00
28Construction of haul road (203-50)LS1$308,320$203,000$380,000$540,000
29Foundation fill material (204-08)CY53$115.00$111.00$120.00$130.00
30Backfill material (flowable fill) (204-08.01)CY12$580.00$309.00$475.00$450.00
31RSS backfill material (205-02.01)CY20,287$37.20$17.50$61.00$40.00
3215" temporary slope drain (209-02.06)LF60$30.00$8.00$20.00$30.00
3318" temporary slope drain (209-02.07)LF2,724$36.00$10.00$30.00$35.00
3424" temporary slope drain (209-02.08)LF2,236$52.00$12.00$35.00$50.00
3530" temporary slope drain (209-02.09)LF380$67.00$14.00$45.00$65.00
36Sediment removal (209-05)CY2,584$18.00$46.10$23.00$20.00
37Temporary silt fence (with backing) (209-08.02)LF10,675$6.00$5.85$5.00$4.50
38Temporary silt fence (without backing) (209-08.03)LF36,651$2.20$2.10$3.00$2.50
39Rock check dam (209-08.07)EACH10$800.00$778.00$990.00$1,000.00
40Enhanced rock check dam (209-08.08)EACH46$800.00$778.00$1,400.00$1,200.00
41Sediment filter bag (15' X 15') (209-09.03)EACH4$573.00$953.00$360.00$700.00
42Curb inlet protection (type 4) (209-09.43)EACH256$143.00$139.00$155.00$130.00
43Catch basin protection (type A) (209-40.30)EACH8$860.00$778.00$460.00$390.00
44Catch basin protection (type D) (209-40.33)EACH59$201.00$194.00$335.00$280.00
45Temporary in stream diversion (209-65.04)LF467$57.30$55.55$130.00$75.00
46Mineral aggregate, type A base, grading D (303-01)TON168,267$29.15$29.70$27.00$25.00
47Granular backfill (roadway) (303-01.01)TON926$48.15$50.40$36.00$60.00
48Mineral aggregate (size 57) (303-10.01)TON468$65.36$50.40$57.00$65.00
49Mineral aggregate (size 57 - pabe) (303-10.04)TON292$115.00$111.00$66.50$98.00
50Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON12,499$116.90$100.50$114.00$125.00
51Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON12,291$127.25$104.00$123.00$128.00
52Asp. conc. mix(PG64-22) (BPMB-HM) GR. A-S (307-01.20)TON1,006$128.35$145.00$125.00$150.00
53Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21)TON31,467$113.50$102.70$111.00$130.00
54Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01)TON41,919$100.85$106.00$100.00$114.00
55Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08)TON20,595$113.50$114.40$111.00$119.00
56Bituminous material for prime coat (PC) (402-01)TON387$1,260.00$1,100.00$1,210.00$1,050.00
57Aggregate for cover material (PC) (402-02)TON1,371$80.25$75.30$77.00$50.00
58Bituminous material for tack coat (TC) (403-01)TON111$1,150.00$1,060.00$1,100.00$1,000.00
59Saw cutting asphalt pavement (407-20.05)LF575$4.05$8.90$8.00$5.00
60Acs mix (PG64-22) grading E shoulder (411-01.07)TON1,479$175.35$140.00$171.00$156.00
61Acs mix(PG64-22) grading D (411-01.10)TON5,492$174.25$173.00$169.00$170.00
62Acs mix(PG70-22) grading D (411-02.10)TON12,978$169.65$147.30$162.80$155.00
63Cold planing bituminous pavement (415-01.02)SY11,856$6.30$5.15$6.20$6.65
64Class A concrete (roadway) (604-01.01)CY131$1,400.00$1,390.00$2,100.00$1,300.00
65Steel bar reinforcement (roadway) (604-01.02)LB28,439$1.50$1.45$1.50$1.50
66Box tube safety rail (604-01.20)LF299$288.00$265.00$170.00$300.00
67Retaining wall (begin sta.166+14.00 to end sta.166+95.00) (604-07.01)SF335$148.00$225.00$150.00$130.00
68Retaining wall (begin sta.234+82.75 to end sta.237+00.00) (604-07.02)SF1,013$148.00$165.00$160.00$100.00
69Retaining wall (tree wall - driveway at 168+92.18) (604-07.03)SF285$160.00$164.00$110.00$100.00
70Retaining wall (tree wall - begin sta. 236+50.00TO end sta. 236+81.82) (604-07.04)SF97$215.00$162.00$110.00$100.00
7118" concrete pipe culvert (class III) (607-03.02)LF13,041$123.60$140.00$93.00$111.00
7218" concrete pipe culvert (class IV) (607-03.03)LF92$260.00$162.00$168.00$133.00
7324" concrete pipe culvert (class III) (607-05.02)LF4,121$203.60$178.00$118.00$121.00
7430" concrete pipe culvert (class III) (607-06.02)LF5,366$240.00$208.00$150.00$155.00
7536" concrete pipe culvert (class III) (607-07.02)LF4,507$448.00$357.00$196.00$185.00
7642" concrete pipe culvert (class III) (607-08.02)LF1,657$1,080.00$463.00$272.00$280.00
7742" concrete pipe culvert (class IV) (607-08.03)LF2,748$1,270.00$563.00$297.00$390.00
7854" concrete pipe culvert (class IV) (607-10.03)LF125$2,600.00$827.00$490.00$1,600.00
7923"X 14" horizontal oval concrete pipe culvert (607-16.01)LF111$233.00$134.00$151.00$100.00
8030"X 19" horizontal oval concrete pipe culvert (607-16.02)LF964$228.00$165.00$184.00$105.00
8138"X 24" horizontal oval concrete pipe culvert (607-16.04)LF229$279.00$198.00$224.00$380.00
8245"X 29" horizontal oval concrete pipe culvert (607-16.06)LF197$515.00$235.00$268.00$385.00
8360"X 38" horizontal oval concrete pipe culvert (607-16.09)LF350$462.00$335.00$370.00$1,100.00
8418" pipe culvert (side drain) (607-39.02)LF548$106.00$95.15$125.00$113.00
85Manholes, > 4' - 8' depth (611-01.02)EACH6$9,140.00$6,480.00$8,300.00$8,100.00
86Manholes, > 8' - 12' depth (611-01.03)EACH3$12,710$8,810.00$8,300.00$19,500
87Junction box, type 1 (611-02.10)EACH1$12,210$7,350.00$7,000.00$8,300.00
88Class A concrete (pipe endwalls) (611-07.01)CY67$1,670.00$1,640.00$3,300.00$2,750.00
89Steel bar reinforcement (pipe endwalls) (611-07.02)LB2,768$9.05$5.20$2.00$3.00
9018IN endwall (side drain) (611-07.31)EACH32$4,060.00$2,590.00$4,500.00$4,700.00
9124IN endwall (side drain) (611-07.32)EACH10$5,290.00$3,250.00$6,000.00$6,500.00
9218IN endwall (cross drain) 3:1 (611-07.54)EACH16$3,630.00$1,940.00$5,000.00$2,100.00
9330IN endwall (cross drain) 3:1 (611-07.60)EACH2$6,300.00$5,510.00$5,200.00$6,800.00
9436IN endwall (cross drain) 3:1 (611-07.63)EACH4$7,800.00$7,370.00$6,800.00$8,800.00
9542IN endwall (cross drain) 3:1 (611-07.66)EACH2$9,320.00$9,900.00$7,900.00$12,100
96Catch basins, type 12, 0' - 4' depth (611-12.01)EACH12$8,620.00$5,710.00$6,200.00$7,300.00
97Catch basins, type 12, > 4' - 8' depth (611-12.02)EACH105$9,790.00$6,520.00$7,100.00$7,800.00
98Catch basins, type 12, > 8' - 12' depth (611-12.03)EACH23$12,650$8,540.00$9,200.00$9,500.00
99Catch basins, type 12, > 12' - 16' depth (611-12.04)EACH7$17,230$11,800$11,100$12,100
100Catch basins, type 12, > 16' - 20' depth (611-12.05)EACH4$20,430$18,600$13,300$17,300
101Catch basins, type 12, > 20' - 24' depth (611-12.06)EACH3$33,230$19,900$20,500$16,200
102Catch basins, type 12, > 24' - 28' depth (611-12.07)EACH6$37,650$29,200$23,700$17,600
103Catch basins, type 14, 0' - 4' depth (611-14.01)EACH2$14,000$7,550.00$9,500.00$10,300
104Catch basins, type 14, > 4' - 8' depth (611-14.02)EACH39$21,560$11,000$12,400$13,500
105Catch basins, type 14, > 8' - 12' depth (611-14.03)EACH10$24,810$17,600$18,800$19,500
106Catch basins, type 14, > 12' - 16' depth (611-14.04)EACH6$32,280$21,300$20,700$23,400
107Catch basins, type 14, > 16' - 20' depth (611-14.05)EACH6$34,550$27,500$24,000$27,300
108Catch basins, type 14, > 20' - 24' depth (611-14.06)EACH2$49,780$34,300$34,300$27,900
109Catch basins, type 42, 0' - 4' depth (611-42.01)EACH20$7,130.00$5,270.00$5,100.00$6,800.00
110Catch basins, type 42, > 4' - 8' depth (611-42.02)EACH4$7,930.00$6,850.00$6,600.00$8,200.00
11118" temporary drainage pipe (621-03.02)LF252$65.00$82.90$64.00$73.00
11224" temporary drainage pipe (621-03.03)LF18$100.00$139.00$130.00$132.00
11336" temporary drainage pipe (621-03.05)LF16$175.00$187.00$156.00$150.00
114Concrete sidewalk (4 ") (701-01.01)SF126,976$7.80$7.55$7.70$6.70
115Concrete driveway (701-02)SF36,414$11.25$10.90$10.60$9.70
116Concrete curb ramp (701-02.03)SF17,001$10.90$10.55$18.00$9.35
117Concrete curb (702-01)CY69$869.00$842.00$900.00$758.00
118Concrete combined curb & gutter (702-03)CY4,424$466.00$452.00$540.00$400.00
119Metal beam guard fence (705-01.04)LF104$105.00$133.00$101.00$120.00
120W beam GR (type 2) MASH TL-3 (705-06.01)LF6,448$31.50$31.10$30.50$28.00
121GR terminaltrailing end (type 13) MASH TL-3 (705-06.10)EACH3$2,180.00$1,560.00$2,090.00$1,400.00
122Tangent energy absorbing term MASH TL-3 (705-06.20)EACH15$4,300.00$3,670.00$4,125.00$3,300.00
123Thrie beam bridge transition MASH TL-3 (705-06.25)EACH4$3,380.00$3,110.00$3,245.00$2,800.00
124Guardrail removed (706-01)LF4,528$0.55$1.35$0.60$1.20
125High-visibility construction fence (707-08.11)LF2,300$2.20$2.10$3.30$3.00
126Markers (concrete R.O.W. posts) (708-02.01)EACH105$591.00$333.00$330.00$365.00
127Machined rip-rap (class A-3) (709-05.05)TON5,940$60.25$50.00$61.00$70.00
128Machined rip-rap (class A-1) (709-05.06)TON7,858$77.90$55.80$75.00$70.00
129Machined rip-rap (class B) (709-05.08)TON1,720$71.65$49.95$92.00$70.00
130Aggregate underdrains (with pipe) (710-02)LF36,260$14.05$13.60$15.00$13.25
131Single slope half concrete barrier wall (711-05.72)LF218$252.00$245.00$255.00$415.00
132Traffic control (712-01)LS1$850,075$510,000$200,000$1,300,000
133Interconnected portable barrier rail (712-02.02)LF5,941$54.75$28.65$88.00$36.00
134Portable barrier rail (MASH TL-3) (712-02.10)LF450$137.00$50.00$86.00$150.00
135Portable barrier rail, reduced deflection (MASH TL-3) (712-02.12)LF450$142.00$123.00$88.00$220.00
136Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH12$10,540$6,450.00$13,200$9,500.00
137Flexible drums (channelizing) (712-04.01)EACH2,858$55.00$53.30$11.00$33.00
138Barrier rail delineator (712-04.50)EACH1,493$16.05$15.55$8.25$15.00
139Warning lights (type A) (712-05.01)EACH156$36.70$35.55$36.00$20.00
140Signs (construction) (712-06)SF5$28.65$27.75$7.00$30.00
141Temporary barricades (type III) (712-07.03)LF1,560$6.90$6.65$23.00$25.00
142Arrow board (type C) (712-08.03)EACH5$2,750.00$2,670.00$990.00$1,500.00
143Removable pavement marking (6" line) (712-09.08)LF4,400$3.00$2.90$2.90$2.60
144Removable wet reflective pavement marking tape (712-09.21)LF1,600$3.00$2.90$2.90$2.60
145Class A concrete (foundation for sign supports) (713-01.01)CY1$802.00$778.00$800.00$700.00
146Steel bar reinforcement(foundation for sign supports) (713-01.02)LB294$4.25$4.10$3.60$3.70
147Sign post delineation enhancement (713-02.21)LF160$4.35$4.20$5.00$3.80
148Flexible tubular delineator (713-02.30)EACH110$66.50$64.45$110.00$58.00
149Steel I-beams & WF-beams(breakaway) sign support (713-06)LB640$9.45$9.15$8.50$8.25
150"U" section steel posts (713-11.01)LB2,793$4.75$4.60$4.00$4.15
151Perforated/knockout square tube post (713-11.02)LB164$5.15$5.00$5.00$4.50
152Flat sheet aluminum signs (0.080" thick) (713-13.02)SF584$17.35$16.85$14.00$15.15
153Extruded aluminum panel signs (713-14)SF115$33.80$32.75$37.00$29.50
154Street name sign (rigid 0.100IN thick (713-14.21)SF72$28.65$27.75$39.00$25.00
155Street name sign (suspended 0.100IN thick) (713-14.22)SF493$25.20$24.45$44.00$84.00
156Removal & relocation of sign & support (713-15.02)EACH1$287.00$278.00$3,520.00$250.00
157Suspended flat sheet aluminum sign (0.080" thick) (713-15.07)EACH41$128.00$124.00$505.00$112.00
158Remove sign, support & footing (713-15.36)EACH3$229.00$220.00$43.00$200.00
159Changeable message sign unit (713-16.01)EACH10$11,690$11,300$4,400.00$11,000
160Jacked or bored conduit (714-03)LF5,450$68.75$16.85$119.00$15.00
161Direct burial conduit (2" PVC, schedule 40) (714-03.01)LF22,560$20.65$14.25$15.50$12.70
162Pull boxes (mte UM35L) (714-05.06)EACH180$1,380.00$1,960.00$2,000.00$1,750.00
163Cable (1/0 AK triplex) (714-06.08)LF32,380$8.95$6.25$3.60$5.55
164Cable (#6 solid bare copper soft drawn, ground) (714-06.09)LF1,000$2.50$2.85$4.00$2.53
165Cable (#2 acsr) (714-06.10)LF10,000$1.70$4.60$12.30$4.11
166Light standards (45' M.H., single) (714-08.09)EACH120$7,530.00$5,610.00$5,877.78$5,000.00
167Light standards (45' M.H., double) (714-08.10)EACH4$7,790.00$5,610.00$8,000.00$5,000.00
168Foundation (only) for light standard (714-08.20)EACH122$2,520.00$2,240.00$3,630.00$2,000.00
169Remove & relocate light standard (714-08.29)LS1$4,150.00$1,120.00$7,400.00$1,000.00
170Removal of light standard & foundation (714-08.32)EACH45$287.00$1,680.00$670.00$1,500.00
171Luminaires (147 watt single LED offset, light standard mounted) (714-09.09)EACH120$1,290.00$1,120.00$1,206.00$1,000.00
172Luminaires (147 watt double LED offset, light standard mounted) (714-09.11)EACH4$1,290.00$1,120.00$1,278.00$1,000.00
173Luminaires (147 watt LED offset, utility pole mounted by others) (714-09.12)EACH4$1,700.00$1,120.00$1,278.00$1,000.00
174Luminaires (208 watt LED offset, utility pole mounted by others) (714-09.13)EACH4$1,860.00$1,120.00$1,450.00$1,000.00
175Luminaires (147 watt LED offset, signal pole mounted) (714-09.15)EACH18$1,290.00$1,120.00$1,280.00$1,000.00
176Luminaires (208 watt LED offset, signal pole mounted) (714-09.16)EACH3$1,450.00$1,120.00$1,450.00$1,000.00
177Luminaires (147 watt LED offset, existing wood pole mounted) (714-09.17)EACH1$1,290.00$1,120.00$1,280.00$3,500.00
178Electrical connection (psa) (714-25.01)LS1$9,900.00$3,930.00$4,280.00$3,500.00
179Electrical connection (PSB) (714-25.02)LS1$12,880$3,930.00$4,650.00$3,500.00
180Electrical connection (PSC) (714-25.03)LS1$12,880$3,930.00$4,650.00$3,500.00
181Electrical connection (PSD) (714-25.04)LS1$12,880$3,930.00$4,650.00$3,500.00
182Electrical connection (pse) (714-25.05)LS1$12,880$3,930.00$4,650.00$3,500.00
183Electrical connection (PSF) (714-25.08)LS1$12,880$3,930.00$4,650.00$3,500.00
184Electrical connection (PSG) (714-25.09)EACH1$12,880$3,930.00$4,650.00$3,500.00
185Temporary raised pavement marker (716-01.05)EACH870$9.15$8.90$9.00$8.00
186Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH3,591$42.40$41.10$41.50$37.00
187Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22)EACH59$42.40$41.10$41.50$37.00
188Removal of snowplowable reflective marker (716-01.30)EACH600$11.45$11.10$11.00$10.00
189Plastic pavement marking(channelization striping) (716-02.04)SY59$40.10$38.90$39.00$35.00
190Plastic pavement marking (stop line) (716-02.05)LF1,809$20.65$20.00$20.00$18.00
191Plastic pavement marking (turn lane arrow) (716-02.06)EACH192$189.00$183.00$184.00$165.00
192Plastic pavement marking (8" dotted line) (716-02.08)LF751$2.30$2.20$2.30$2.00
193Plastic pavement marking (longitudinal cross-walk) (716-02.09)LF3,591$40.10$38.90$39.00$35.00
194Plastic pavement marking (8IN line) (716-02.12)LM0.20$8,600.00$8,330.00$8,376.00$7,500.00
195Plastic pavement marking (straight-turn arrow) (716-04.01)EACH7$344.00$333.00$335.00$300.00
196Plastic pavement marking(double turning arrow) (716-04.02)EACH3$344.00$333.00$335.00$300.00
197Plastic pavement marking (transverse shoulder) (716-04.04)LF75$8.00$7.80$8.00$7.00
198Plastic pavement marking (straight arrow) (716-04.05)EACH4$189.00$183.00$185.00$165.00
199Plastic pavement marking (bikelane symbol & arrow) (716-04.13)EACH14$470.00$455.00$458.00$410.00
200Plastic pavement marking-bike symbol/arrow shared (716-04.15)EACH1$470.00$455.00$458.00$410.00
201Painted pavement marking (channelization striping) (716-05.04)SY28$17.20$16.65$17.00$15.00
202Painted pavement marking (stop line) (716-05.05)LF1,410$11.45$11.10$12.00$10.00
203Painted pavement marking (turn lane arrow) (716-05.06)EACH80$68.75$66.65$67.00$60.00
204Painted pavement markings(8" line) (716-05.49)LM18.90$1,490.00$1,440.00$1,452.00$1,300.00
205Removal of pavement marking (channelization striping) (716-08.04)SY100$8.60$8.35$8.40$7.50
206Removal of pavement marking (stop line) (716-08.05)LF1,233$5.75$5.55$5.60$5.00
207Removal of pavement marking (turn lane arrow) (716-08.06)EACH56$57.30$55.55$56.00$50.00
208Removal of pavement marking (line) (716-08.20)LM11.50$5,730.00$5,550.00$5,584.00$5,000.00
209Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM40.50$7,450.00$7,220.00$7,259.00$6,500.00
210Mobilization (717-01)LS1$2,289,200$6,000,000$12,985,000$14,250,000
211Field office (type 2) (722-01.02)LS1$113,230$358,000$250,000$275,000
212CCTV pole removal (725-20.05)EACH2$573.00$1,680.00$1,800.00$1,500.00
213CCTV camera system (see footnote) (725-20.94)EACH8$11,760$6,170.00$6,300.00$5,500.00
214Network switch (see footnote) (725-21.15)EACH8$9,900.00$11,200$6,030.00$5,500.00
215Removal of signal equipment (730-01.02)EACH4$1,720.00$16,800$3,820.00$1,500.00
216Modification of existing traffic signal equipment (730-01.03)EACH4$1,470.00$2,810.00$32,300$1,280.00
217Remove & relocate school signal equipment (730-01.05)LS1$2,770.00$5,610.00$4,300.00$2,420.00
218Signal head assembly (130 A3 with backplate) (730-02.03)EACH10$1,600.00$1,510.00$1,700.00$1,399.00
219Signal head assembly (130 pole mounted) (730-02.08)EACH1$1,740.00$1,230.00$1,360.00$1,519.00
220Signal head assembly (130 with backplate) (730-02.09)EACH52$1,600.00$1,510.00$1,690.00$1,399.00
221Signal head assembly (140 A4F with backplate) (730-02.59)EACH33$2,290.00$1,800.00$2,075.00$2,002.00
222Install pull box (type B) (730-03.21)EACH77$1,150.00$3,930.00$1,240.00$1,000.00
223Install pull box (fiber optic-type A) (730-03.23)EACH8$3,030.00$5,610.00$3,500.00$2,640.00
224Fiber optic splice fusion (730-03.33)EACH8$481.00$3,370.00$815.00$420.00
225Fiber optic cable (48F) (730-03.50)LF27,000$3.00$7.10$5.20$2.60
226Fiber optic cable (12F) (730-03.51)LF1,200$2.75$5.85$6.80$2.40
227Electrical service connection (730-05.01)EACH11$9,170.00$3,930.00$5,300.00$8,000.00
228Signal cable - 5 conductor (730-08.02)LF6,700$2.85$2.65$3.11$2.50
229Signal cable - 7 conductor (730-08.03)LF21,000$3.15$3.10$3.90$2.75
230Signal cable - 9 conductor (730-08.04)LF3,000$3.45$3.65$4.00$3.00
231Riser assembly (2" PVC) (730-11.10)EACH14$688.00$3,370.00$1,066.00$600.00
232Conduit 2" diameter (PVC schedule 40) (730-12.02)LF3,700$20.65$14.25$24.00$18.00
233Conduit 2" diameter (directional bore) (730-12.23)LF90$68.75$22.45$69.00$60.00
234Conduit 3" diameter (directional bore) (730-12.24)LF3,650$74.50$24.70$75.60$65.00
235Vehicle detector (radar/video) (730-13.16)EACH8$43,510$40,400$39,200$37,965
236Cabinet (PHB) (730-15.07)EACH1$28,910$30,300$27,500$25,225
237Cabinet (eight phase base mounted) (730-15.32)EACH7$29,120$30,300$30,600$25,410
238Eight phase actuated controller (730-16.02)EACH8$7,460.00$5,610.00$8,800.00$6,513.00
239Controller (flashing beacon) (730-16.03)EACH3$3,870.00$1,120.00$2,200.00$3,376.00
240Controller (atc) (730-16.04)EACH8$7,460.00$5,610.00$7,500.00$6,513.00
241Guying device (angle anchor) (730-22.02)EACH47$688.00$2,810.00$1,200.00$600.00
242Pedestal pole (type A) (730-23.28)EACH18$4,010.00$7,290.00$3,750.00$3,499.00
243Cantilever signal support (2 @ 40' & 45') (730-23.87)EACH1$48,190$64,000$49,000$42,043
244Cantilever signal support (1 arm @ 45') (730-23.88)EACH1$35,380$54,400$28,200$30,872
245Cantilever signal support (2 @ 40' & 50') (730-24.85)EACH2$56,950$70,700$59,000$49,685
246Cantilever signal support (2 @ 40' & 55') (730-24.86)EACH1$62,040$74,100$65,000$54,130
247Cantilever signal support (2 @ 40' & 65') (730-24.88)EACH2$65,840$76,900$71,000$57,443
248Cantilever signal support (2 @ 40' & 90') (730-24.96)EACH1$96,400$99,900$106,000$84,109
249Cantilever signal support (3 @ 40', 50', & 70') (730-24.97)EACH1$85,940$92,000$98,000$74,981
250Cantilever signal support (1 arm @ 50') (730-25.01)EACH3$35,490$54,400$34,000$30,963
251Cantilever signal support (1 arm @ 55') (730-25.07)EACH4$44,110$60,900$44,000$38,482
252Cantilever signal support (2 @ 55' & 65') (730-25.10)EACH1$67,010$78,000$76,000$58,462
253Cantilever signal support (1 arm @ 60') (730-25.11)EACH2$47,320$63,100$48,200$41,283
254Cantilever signal support (1 arm @ 65') (730-25.13)EACH1$51,030$70,100$64,000$44,519
255Cantilever signal support (1 arm @ 70') (730-25.14)EACH2$53,200$67,600$65,300$46,415
256Cantilever signal support (1 arm @ 75') (730-25.15)EACH1$46,840$62,800$78,000$40,867
257Cantilever signal support (1 arm @ 80') (730-25.16)EACH2$66,420$77,400$94,000$57,955
258Cantilever signal support (1 arm @ 85') (730-25.17)EACH1$70,800$80,800$83,000$61,768
259Cantilever signal support (1 arm @ 90') (730-25.18)EACH1$72,480$81,900$105,000$63,236
260Audible pedestrian signal (730-26.04)EACH52$1,980.00$2,810.00$1,180.00$1,728.00
261Pedestrian pushbutton post (730-26.06)EACH2$1,300.00$6,170.00$3,000.00$1,136.00
262Battery back-UP system (730-35.06)EACH7$11,840$11,200$17,800$10,333
263Pedestrian hybrid beacon assembly (730-50.25)EACH2$10,150$3,930.00$4,700.00$8,856.00
264School speed limit flashing assembly (hard-wired) (730-50.31)EACH6$5,300.00$11,200$6,300.00$4,626.00
265Geomembrane (740-06.01)SY178$18.10$81.15$13.20$40.00
266Geogrid reinforcement type 2 (740-07.04)SY819$5.75$5.55$14.00$8.50
267Uniaxial geogrid reinforcement type 2 (740-07.12)SY82,262$4.25$3.00$6.60$4.10
268Geotextile (type III)(erosion control) (740-10.03)SY3,553$4.60$4.10$4.50$3.30
269Geotextile (type IV)(stabilization) (740-10.04)SY119,236$4.05$5.05$5.40$3.00
270Temporary sediment tube 20IN (740-11.04)LF22,151$4.60$2.10$5.00$3.60
271Fiber optic storage loop(installation only) (798-06.57)EACH22$458.00$561.00$730.00$500.00
272Transfer fiberoptic cable (798-08.06)EACH1$3,280.00$35,900$1,000.00$32,000
273Temporary seeding (with mulch) (801-01.07)UNIT840$51.60$43.30$50.00$45.00
274Natve seed MX final stablizatn of slopes (801-01.38)UNIT37$172.00$63.75$165.00$150.00
275Water (seeding & sodding) (801-03)MG1,022$57.30$55.55$55.00$50.00
276Sodding (new sod) (803-01)SY93,321$5.45$5.30$6.00$4.75
277Project mowing (806-02.03)CYCL6$5,730.00$5,550.00$11,000$5,000.00
278Class A concrete (box bridges) (604-02.01)CY170$1,310.00$1,330.00$2,100.00$1,400.00
279Steel bar reinforcement (box bridges) (604-02.02)LB33,036$1.50$1.45$2.40$1.54
280Removal of asbestos (202-01.02)LS1$56,160$54,400$58,000$52,700
281Removal of structures (exist. BR. no. 75-SR268-0.84) (202-04.01)LS1$307,170$298,000$350,000$750,000
282Dry excavation (bridges) (204-02.01)CY468$28.65$27.75$17.30$40.00
283Wet excavation (bridges) (204-03.01)CY48$74.50$72.20$70.00$75.00
284Rock excavation (bridges) (204-04.01)CY140$138.00$133.00$225.00$100.00
285Rock drilling (bridges) (204-05)LF48$57.30$55.55$100.00$40.00
286Foundation preparation(pier no. 1, sta. 56+08.00) (204-10.01)LS1$11,460$11,100$16,300$60,000
287Foundation preparation(pier no. 2, sta. 57+48.00) (204-10.02)LS1$11,460$11,100$16,500$60,000
288Granular backfill (bridges) (303-01.02)TON112$51.60$50.00$100.00$60.00
289Steel structures (602-03)LS1$4,330,540$4,200,000$3,580,000$3,375,000
290Bearing device (2 1/2" reinforced elast. bearing pad) (602-10.60)EACH16$5,850.00$5,670.00$320.00$5,000.00
291Epoxy coated reinforcing steel (604-02.03)LB284,001$2.05$2.00$2.05$1.65
292Class A concrete (bridges) (604-03.01)CY616$1,290.00$1,250.00$1,600.00$1,000.00
293Steel bar reinforcement (bridges) (604-03.02)LB84,652$1.85$1.80$2.00$1.75
294Pavement @ bridge ends (604-03.04)SY416$544.00$528.00$470.00$435.00
295Class DS concrete (604-03.32)CY966$1,255.00$1,220.00$1,300.00$1,100.00
296Applied texture finish (new structures) (604-04.01)SY1,721$18.35$17.75$20.00$14.50
297Bridge deck grooving (mechanical) (604-05.31)SY2,987$5.15$5.00$13.50$3.98
298Steel piles (10 inch) (606-02.03)LF742$94.00$91.10$130.00$98.00
299Pile tips (steel piles, 10 inch) (606-02.06)EACH38$181.00$176.00$169.00$200.00
300Deck drains (grate type 2) (610-10.45)EACH94$2,750.00$2,670.00$2,130.00$2,000.00
301Bridge deck crack sealing (617-02)LF896$5.75$5.55$20.00$4.00
302Sealant (HMWM) (617-05)GAL5$344.00$333.00$850.00$350.00
303Concrete parapet with structural tubing (620-05)LF859$401.00$389.00$425.00$337.00
304Temporary shoring (621-05.01)SF1,090$37.00$25.50$45.00$130.00
3056" perforated pipe with vertical drain system (710-09.01)LF258$50.45$48.90$32.00$75.00
3066" pipe underdrain (710-09.02)LF96$22.90$22.20$29.00$15.00
307Structural lighting (75F00050005) (714-01.01)LS1$24,990$42,400$43,300$37,763
308Pole 45FT class H2 metal (790-04.09)EACH22$5,920.00$5,800.00$4,900.00$5,168.40
309Pole 50FT class H2 metal (790-05.08)EACH27$6,760.00$6,610.00$5,700.00$5,894.80
310Pole 55FT class H2 metal (790-06.08)EACH10$7,690.00$7,530.00$6,700.00$6,713.20
311Pole 60FT class H2 metal (790-07.08)EACH70$8,580.00$8,400.00$7,500.00$7,486.40
312Pole 65FT class H2 metal (790-08.04)EACH23$9,560.00$9,360.00$8,500.00$8,344.40
313Pole 70FT class H2 metal (790-09.05)EACH5$10,830$10,600$9,700.00$9,450.40
314Pole 70FT class H4 metal (790-09.07)EACH4$12,590$12,300$11,500$10,988
315Pole 75FT class H2 metal (790-10.05)EACH1$12,690$12,400$10,600$11,073
316Pole 75FT class H4 metal (790-10.07)EACH1$14,630$14,300$13,000$12,766
317Pole 85FT class H4 metal (790-12.07)EACH23$17,400$17,000$15,000$15,186
318Pole 90FT class H4 metal (790-13.07)EACH4$19,000$18,600$20,000$16,580
3191PH dde angle 25KV (790-22.11)EACH1$809.00$792.00$1,200.00$706.20
3201PH dead end tap W/ extension 25KV (790-22.15)EACH32$665.00$651.00$1,500.00$580.00
3211PH dde tangent 25KV (790-22.16)EACH1$823.00$806.00$1,200.00$718.32
3221PH SGL dead end xarm 25KV (790-22.18)EACH6$1,410.00$1,380.00$2,200.00$1,228.40
3233PH crossarm 25KV (790-26.01)EACH1$1,220.00$1,200.00$1,800.00$1,065.20
3243PH crossarm SGL LRG cond 25KV (790-26.03)EACH61$1,180.00$1,150.00$1,600.00$1,028.40
3253PH vertical tangent 25KV (790-26.10)EACH2$1,280.00$1,250.00$1,835.00$1,116.60
3263PH xarm DBL 10FT LRG cond SM angle 25KV (790-26.15)EACH192$1,860.00$1,820.00$2,300.00$1,625.90
3273PH vertical angle LRG cond 25KV (790-26.20)EACH1$2,180.00$2,130.00$2,100.00$1,901.80
3283PH vertical dde angle 25KV (790-26.21)EACH6$2,940.00$2,880.00$2,700.00$2,568.30
3293PH crossarm dead end 25KV (790-26.26)EACH49$1,620.00$1,590.00$2,500.00$1,415.40
3303PH crossarm FBRGLS dde 25KV (790-26.45)EACH26$2,870.00$2,810.00$3,300.00$2,508.20
3313PH special const crossarm dde 25KV (790-26.47)EACH5$5,390.00$5,280.00$2,900.00$4,705.80
332Secondary assemblies LRG angle (790-30.02)EACH116$196.00$192.00$690.00$171.00
333Secondary assemblies deadend (790-30.03)EACH36$218.00$213.00$715.00$190.20
334Secondary conductor 6 AL duplex (790-30.06)LF425$3.05$2.95$3.25$2.64
335Secondary conductor 2 AL triplex (790-30.13)LF466$4.25$4.15$5.20$3.71
336Secondary conductor 1/0 AL triplex (790-30.14)LF81$5.95$5.85$7.10$5.20
337Secondary conductor 4/0 AL triplex (790-30.17)LF151$9.90$9.70$12.20$8.64
338Secondary conductor 1/0 AL qplex (790-30.22)LF201$7.60$7.45$5.22$6.63
339Secondary conductor 4/0 AL qplex (790-30.25)LF242$11.90$11.65$15.50$10.37
340Service assembly-pole type (790-31.02)EACH1$1,020.00$999.00$1,800.00$890.00
341Down guy - through bolt type (790-32.01)EACH15$416.00$407.00$425.00$362.80
342Down guy - through bolt type heavy duty (790-32.02)EACH486$402.00$394.00$600.00$351.16
343OH guy - through bolt type (790-32.07)EACH76$651.00$637.00$590.00$567.93
344Guy guard (790-32.23)EACH14$28.40$27.85$51.00$24.80
345Rock anchor expanding type (790-33.17)EACH11$563.00$551.00$1,110.00$491.12
346Anchor triple eye power installed (790-33.20)EACH258$833.00$815.00$900.00$726.42
347Transfer capacitor bank (790-36.02)EACH3$5,700.00$5,580.00$4,200.00$4,974.52
348Transfer service (790-36.04)EACH14$309.00$303.00$1,360.00$270.00
349Transfer street light (790-36.13)EACH9$332.00$325.00$450.00$290.00
350Transfer conductor (790-36.14)EACH93$258.00$252.00$550.00$225.00
351OH cond 2 7/1 acsr sparate (790-40.02)LF10,982$2.95$2.90$2.70$2.57
352OH cond 1/0 6/1 acsr raven (790-40.03)LF3,167$3.45$3.35$3.50$2.99
353OH cond 3/0 6/1 acsr pigeon (790-40.05)LF2,562$3.70$3.65$4.15$3.25
354OH cond 336.4 18/1 acsr merlin (790-40.09)LF29,920$5.75$5.60$4.00$5.00
355OH cond 795 37 aac arbutus (790-40.49)LF155,439$9.25$9.10$6.90$8.09
356OH cond 954 61 aac goldenrod (790-40.86)LF16,212$13.20$12.90$10.70$11.50
357UG pri cond 4/0 AL 15KV (790-41.06)LF1,890$16.45$16.10$16.70$14.35
358UG pri cond 1 AL 25KV (790-41.12)LF3,189$17.60$17.25$26.70$15.37
359UG pri cond 4/0 AL 25KV (790-41.16)LF2,319$14.90$14.60$16.70$13.10
360UG sec cond 2/0 AL TPLX (790-41.47)LF90$7.25$7.10$9.25$6.34
361UG sec cond 4/0 AL TPLX (790-41.49)LF933$8.30$8.15$11.70$7.26
362UG sec cond 350 AL TPLX (790-41.51)LF50$14.25$13.95$16.70$12.42
363Conduit - rolled plastic 2IN dia (790-42.02)LF1,972$24.20$23.70$6.15$21.12
3641 duct @ 36IN-48IN depth (790-42.16)LF928$217.00$212.00$24.00$189.26
3652 duct bank @ 36IN-48IN depth (790-42.17)LF2,806$244.00$238.00$28.00$212.54
366Loadbreak elbow 200A 15KV (790-43.01)EACH20$419.00$411.00$1,070.00$366.00
367Loadbreak junction 4 PT 200A 15KV (790-43.06)EACH21$2,130.00$2,090.00$2,135.00$1,860.33
368Elbow arrester 200A 15KV (790-43.08)EACH23$1,130.00$1,110.00$1,640.00$986.86
369Loadbreak elbow 200A 25KV (790-43.17)EACH47$478.00$468.00$1,550.00$417.40
370Loadbreak parking bushing 200A 25KV (790-43.19)EACH17$304.00$298.00$1,240.00$265.60
371Splice 200A 25KV (790-43.26)EACH61$397.00$389.00$1,500.00$346.54
372Outdoor terminator urd 25KV (790-43.27)EACH32$746.00$731.00$1,975.00$651.26
373UG ground rod assembly (790-43.34)EACH11$257.00$252.00$435.00$224.46
374Secondary pullbox large (790-43.46)EACH34$1,480.00$1,450.00$2,750.00$1,290.20
375Primary pullbox (790-43.47)EACH23$2,350.00$2,300.00$3,560.00$2,050.32
376Secondary riser W/ 2IN conduit (790-43.50)EACH8$954.00$934.00$870.00$832.20
377Secondary riser W/ 3IN conduit (790-43.51)EACH30$1,030.00$1,010.00$1,200.00$902.84
378Secondary riser W/ 4IN conduit (790-43.52)EACH23$934.00$915.00$1,480.00$815.22
379Secondary pullbox (for smart grid fiber) (790-43.67)EACH10$2,730.00$2,670.00$2,420.00$2,380.30
380Loadbreak bushing insert 25KV (790-43.80)EACH10$403.00$394.00$465.00$351.24
381Loadbreak bushing insert 15KV (790-43.81)EACH8$708.00$693.00$350.00$618.00
382Insulated protective cap (790-43.82)EACH9$480.00$470.00$330.00$418.92
3832PH XFMR BNK pole MTD W/ fuse/arresters (790-47.02)EACH1$2,420.00$2,370.00$4,650.00$2,112.70
3843PH XFMR BNK pole MTD no fuse/arresters (790-49.01)EACH6$4,150.00$4,060.00$4,500.00$3,618.76
3851PH pad MTD transformer radial feed (790-50.01)EACH2$1,790.00$1,750.00$3,420.00$1,559.60
3861PH pad MTD transformer loop feed (790-50.02)EACH1$1,330.00$1,300.00$3,430.00$1,159.60
3871PH transformer pad (790-50.03)EACH3$1,260.00$1,240.00$3,600.00$1,102.00
388Cutout knife switch-SNGL loadbreak 25KV (790-59.03)EACH99$896.00$877.00$2,650.00$782.00
389Golb switch 25KV (790-59.05)EACH8$11,220$11,000$11,600$9,790.00
3903PH sectionalizing cabinet 25KV (790-60.20)EACH7$5,210.00$5,100.00$49,400$4,545.20
3911PH sectionalizing cabinet 25KV (790-60.21)EACH1$3,690.00$3,620.00$5,900.00$3,222.68
3921PH fuse cutout xarm mount 25KV (790-61.01)EACH54$585.00$573.00$1,540.00$510.32
3933PH sectlr or recl W/ byp SW electc 25KV (790-61.11)EACH1$16,690$16,300$9,400.00$14,564
394Lightning arrester arm MTD 9 KV (790-65.03)EACH122$401.00$393.00$610.00$350.12
395Lightning arrester arm MTD 18 KV (790-65.05)EACH51$307.00$300.00$900.00$267.56
3963PH capacitor assembly 15KV (790-65.15)EACH3$4,100.00$4,010.00$30,000$3,576.80
397Lightning arrester 3PH 46 KV (790-65.20)EACH6$2,190.00$2,140.00$2,200.00$1,908.00
398Pole ground for air break switch (790-68.07)EACH1$1,480.00$1,450.00$2,400.00$1,295.30
399Dead end shoe (790-68.11)EACH46$182.00$178.00$540.00$158.80
400Large braces (790-68.12)EACH8$191.00$187.00$750.00$166.54
401SGL phase mounting bracket - fiberglass (790-68.13)EACH12$253.00$248.00$780.00$221.00
402Fiberglass crossarm assembly (790-69.04)EACH28$772.00$755.00$960.00$673.00
403Hardware for SGL PH conv trans (790-69.06)EACH37$759.00$743.00$630.00$661.92
404Ground-ground rod for ST pole (790-69.11)EACH6$508.00$497.00$430.00$443.19
405Ground assembly ground plate type (790-69.12)EACH183$162.00$159.00$340.00$141.54
406Pole top pin (790-69.22)EACH2$225.00$220.00$425.00$196.46
407Epoxy dead end (790-69.24)EACH5$141.00$138.00$490.00$123.40
408Extension link - epoxy -1FT (790-69.26)EACH32$83.90$82.15$270.00$73.20
409Extension link - epoxy -6FT (790-69.28)EACH305$131.00$128.00$410.00$114.02
410Arm pin (790-69.32)EACH38$126.00$123.00$495.00$109.60
4113PH sensor mount (790-69.44)EACH3$861.00$843.00$3,900.00$751.60
4123PH post insulator tangent 115KV (790-71.90)EACH19$3,020.00$2,950.00$3,705.56$2,632.00
4133PH post insulator small angle 115KV (790-71.91)EACH5$3,970.00$3,890.00$4,825.00$3,466.00
4143PH suspension insulator vertical double deadend 110KV (790-71.92)EACH3$3,920.00$3,840.00$4,066.67$3,420.40
4153PH suspension insulator vertical deadend 110KV (790-71.93)EACH1$2,910.00$2,850.00$3,900.00$2,538.20
4163PH horizontal deadend 110KV (790-71.94)EACH1$10,730$10,500$5,000.00$9,360.80
417Switch golb 46KV (790-71.95)EACH1$46,530$45,600$40,600$40,598
418Line post (790-73.03)EACH3$1,950.00$1,910.00$1,060.00$1,698.00
4196M strand (790-74.01)LF5,759$3.00$4.45$5.80$5.50
42024 fiber(material only) (790-74.05)LF1,007$4.20$1.22$1.60$1.50
421144 fiber(material only) (790-74.10)LF5,426$5.50$2.90$3.60$3.50
42212-96 fiber(installation only) (790-74.19)LF1,007$2.60$3.90$5.25$5.50
423108-144 fiber(installation only) (790-74.20)LF5,426$2.60$4.80$5.90$5.50
424Fiber splice-12 fiber ribbon (790-74.25)EACH64$384.00$470.00$690.00$625.00
425Fiber tangent assembly (790-74.31)EACH28$404.00$552.00$780.00$725.00
426Fiber deadend assembly (790-74.32)EACH6$595.00$439.00$610.00$575.00
427Fiber double deadend assembly (790-74.33)EACH4$1,110.00$552.00$725.00$675.00
428Fiber storage single loop (790-74.34)EACH6$732.00$477.00$660.00$625.00
429Fiber splice enclosure(see footnote) (790-74.40)EACH5$610.00$645.00$644.44$800.00
430Remove wire (790-98.01)LF248,778$2.10$2.10$2.20$1.85
431Remove poles (790-98.02)EACH235$745.00$572.00$810.00$650.00
432Remove framing/associated apparatus (790-98.03)EACH1,657$378.00$250.00$430.00$330.00
433Remove fiber optic cable (790-98.04)LF6,045$2.00$1.55$1.35$1.75
434Tree and brush removal off row (790-98.20)LS1$143,270$132,000$45,000$125,000
435Tree and brush removal off row (790-98.20)LS1$143,270$132,000$94,000$125,000
4362IN steel gas main (791-01.02)LF175$148.00$96.00$104.50$260.00
4374IN steel gas main (791-01.04)LF625$172.00$106.00$121.00$330.00
4386IN steel gas main (791-01.05)LF50$257.00$168.00$158.40$340.00
4398IN steel gas main (791-01.06)LF22,900$229.00$278.00$270.00$680.00
4402IN HDPE gas main (791-03.02)LF3,350$77.60$87.00$82.50$38.00
4414IN HDPE gas main (791-03.04)LF18,530$40.55$52.00$50.60$48.00
4426IN HDPE gas main (791-03.05)LF10$712.00$87.00$82.50$88.00
443HDD 4IN PE pipe - unconsolidated (791-04.04)LF120$285.00$174.00$165.00$360.00
444HDD 8IN steel pipe - unconsolidated (791-04.24)LF1,010$484.00$610.00$577.50$982.00
445Connect to 2IN EX. PE main (791-06.02)EACH23$1,480.00$3,485.00$3,300.00$550.00
446Connect to 4IN EX. PE main (791-06.03)EACH3$2,540.00$4,065.00$3,850.00$850.00
447Connect to 6IN EX. PE main (791-06.04)EACH1$4,100.00$7,550.00$7,150.00$2,100.00
448Connect to 8IN EX. STL main (791-06.13)EACH1$19,560$30,830$20,350$10,500
449Connect to 2IN EX. STL main W/ stopple (791-06.31)EACH2$5,750.00$13,940$5,060.00$9,200.00
450Connect to 4IN EX. STL main W/ stopple (791-06.32)EACH3$9,640.00$18,890$9,680.00$15,000
451Connect to 6IN EX. STL main W/ stopple (791-06.33)EACH1$34,990$25,600$14,025$25,000
4522IN PE gas valve assembly (791-07.01)EACH19$1,600.00$870.00$825.00$650.00
4534IN PE gas valve assembly (791-07.02)EACH17$2,410.00$1,510.00$1,650.00$850.00
4542IN steel gas valve assembly (791-07.09)EACH1$3,610.00$5,250.00$825.00$5,740.00
4554IN steel gas valve assembly (791-07.10)EACH8$4,800.00$8,690.00$1,925.00$7,500.00
4566IN steel gas valve assembly (791-07.11)EACH1$6,790.00$14,000$3,025.00$1,600.00
4578IN steel gas valve assembly (791-07.12)EACH7$40,620$61,700$35,475$32,000
4583/4IN service assembly (791-08.02)EACH23$1,110.00$1,510.00$1,430.00$290.00
4593/4IN PE service pipe (791-08.07)LF1,850$71.90$122.00$115.50$48.00
4603-wire cathodic protection station (791-09.02)EACH13$1,650.00$1,452.00$1,375.00$250.00
461Regulator station (791-09.04)EACH7$14,890$17,300$8,800.00$15,000
462Remove regulator station (791-09.08)EACH9$7,070.00$10,800$2,750.00$4,500.00
463Fault current mitigation system (791-09.22)EACH4$13,150$25,850$24,480$15,600
464Retire gas main (791-10.10)LS1$48,820$14,000$11,000$3,500.00
46532LB magnesium anode (791-12.04)EACH16$1,960.00$1,750.00$1,650.00$600.00
4668IN ansi 300 weld-in insulator (791-12.30)EACH1$22,490$27,300$15,950$20,000
467Anchor 1IN (793-01.41)EACH131$1,150.00$1,060.00$1,375.00$950.00
46812IN pedestal (793-11.10)EACH19$2,870.00$1,110.00$1,455.00$1,000.00
469Handhole 24INX36INX24IN (793-11.23)EACH6$4,130.00$5,550.00$2,475.00$5,000.00
4701 duct formation @ 36IN depth (793-13.12)LF836$77.95$67.30$46.70$60.00
471Underground to overhead riser (793-14.26)EACH19$688.00$555.00$528.00$500.00
472Remove poles all sizes (793-98.04)EACH1$458.00$833.00$730.00$750.00
473Remove pedestals (793-98.06)EACH7$344.00$150.00$235.00$225.00
474Remove underground to overhead riser (793-98.07)EACH3$344.00$250.00$292.00$225.00
475Remove anchor (any size) (793-98.08)EACH57$344.00$250.00$138.00$225.00
4766IN dip slip joint water line (795-01.04)LF975$137.00$255.00$150.00$240.00
4778IN dip slip joint water line (795-01.06)LF1,750$181.00$280.00$175.00$260.00
47810IN dip slip joint water line (795-01.08)LF225$253.00$310.00$218.00$300.00
47912IN dip slip joint water line (795-01.10)LF350$363.00$335.00$229.00$310.00
48016IN dip slip joint water line (795-01.14)LF6,100$233.00$370.00$420.00$425.00
48120IN dip slip joint water line (795-01.18)LF11,360$285.80$440.00$460.00$535.00
48224IN dip slip joint water line (795-01.20)LF400$434.00$530.00$645.00$795.00
4834IN PVC casing pipe open cut (795-05.92)LF2,000$108.00$70.00$208.00$140.00
484Connect to 6IN water line (795-06.04)EACH2$2,840.00$8,000.00$8,500.00$5,500.00
485Connect to 8IN water line (795-06.05)EACH8$3,570.00$8,250.00$8,900.00$5,500.00
486Connect to 10IN water line (795-06.06)EACH2$5,640.00$8,500.00$9,400.00$6,000.00
487Connect to 12IN water line (795-06.07)EACH1$7,100.00$9,000.00$9,500.00$6,000.00
488Connect to 16IN water line (795-06.09)EACH7$11,870$18,000$9,600.00$7,000.00
489Connect to 20IN water line (795-06.11)EACH7$14,290$20,000$11,000$8,500.00
490Cut and cap 4IN water line (795-06.32)EACH1$2,610.00$3,000.00$4,300.00$4,800.00
491Cut and cap 8IN water line (795-06.34)EACH5$4,000.00$3,500.00$5,400.00$5,000.00
492Cut & cap 10IN water line (795-06.36)EACH2$4,420.00$3,500.00$4,700.00$5,100.00
493Cut and cap 12IN water line (795-06.37)EACH9$5,170.00$3,750.00$5,120.00$5,200.00
494Cut and cap 16IN water line (795-06.39)EACH18$6,680.00$4,750.00$6,780.00$10,500
495Cut and cap 20IN water line (795-06.42)EACH25$7,860.00$5,500.00$6,780.00$6,000.00
49620IN X 20IN tapping sleeve and valve (795-07.27)EACH1$75,340$105,000$88,000$65,000
497Insertion valve (16IN) (795-07.37)EACH2$60,780$55,000$97,000$52,000
498Insertion valve (20IN) (795-07.39)EACH2$82,490$75,000$110,000$72,000
4996IN gate valve assembly (795-08.04)EACH39$3,480.00$3,000.00$3,600.00$3,300.00
5008IN gate valve assembly (795-08.05)EACH18$4,480.00$4,250.00$4,700.00$4,100.00
50110IN gate valve assembly (795-08.06)EACH2$5,970.00$6,250.00$6,700.00$5,500.00
50212IN gate valve assembly (795-08.09)EACH1$7,190.00$7,650.00$8,100.00$6,800.00
50316IN butterfly valve assembly (795-08.13)EACH22$11,465$19,000$16,300$9,500.00
50420IN butterfly valve assembly (795-08.17)EACH27$14,435$25,500$23,000$12,000
505Relocate/reconnect service assembly (795-09.09)EACH29$2,530.00$1,000.00$1,250.00$2,900.00
5061IN pex service pipe (795-09.62)LF700$81.05$40.00$39.00$100.00
5072IN pexa service pipe (795-09.64)LF200$91.35$50.00$193.00$120.00
508Fire hydrant assembly (795-11.02)EACH33$10,990$17,000$18,500$8,500.00
509Reconnect fire hydrant (795-11.03)EACH3$3,520.00$6,500.00$9,450.00$1,700.00
510Relocate fire hydrant (795-11.04)EACH2$13,620$7,000.00$9,950.00$8,000.00
511Retire in place existing water main (795-11.12)LF19,100$0.75$7.00$22.00$8.00
512Pipe grouting (795-12.03)LS1$292,590$350,000$28,000$70,000
513Adjust existing valve boxes (795-12.20)EACH30$464.00$625.00$1,000.00$650.00
514DI fittings (795-13.01)LB99,500$8.80$12.00$14.50$6.75
51520IN steel casing pipe open cut method (795-15.05)LF75$440.00$530.00$780.00$315.00
51624IN steel casing pipe open cut method (795-15.07)LF85$595.00$630.00$875.00$375.00
51742IN steel casing pipe open cut method (795-15.12)LF175$959.00$1,530.00$1,370.00$535.00
51816IN steel casing pipe open cut method (795-15.25)LF815$309.00$410.00$660.00$165.00
519Retire water meter assemblies (795-21.01)LS1$26,030$21,500$29,000$35,000
520Retire water valves and hydrants (795-21.02)LS1$23,710$21,500$38,900$40,000
52112IN dip force main (797-01.05)LF100$533.00$740.00$430.00$335.00
52216IN dip force main (797-01.07)LF1,850$448.00$535.00$320.00$460.00
5238IN dip gravity sewer 0FT-6FT depth (797-05.01)LF1,100$272.00$418.00$158.00$225.00
5248IN dip gravity sewer 6FT-12FT depth (797-05.02)LF242$394.00$714.00$182.00$280.00
5258IN dip gravity sewer 12FT-18FT depth (797-05.03)LF1,160$387.00$544.00$228.00$380.00
52610IN dip gravity sewer 6FT-12FT depth (797-05.06)LF100$478.00$500.00$198.00$330.00
52716IN dip gravity sewer 6FT-12FT depth (797-05.14)LF150$708.00$705.00$296.00$425.00
528__in dip gravity sewer 0FT-6FT depth (797-05.29)LF2,990$484.00$634.00$428.00$495.00
529__in dip gravity sewer 6FT-12FT depth (797-05.30)LF5,450$544.00$751.00$520.00$560.00
530__in dip gravity sewer 12FT-18FT depth (797-05.31)LF150$1,080.00$1,197.00$550.00$590.00
531__in dip gravity sewer >18FT depth (797-05.32)LF1,260$1,225.00$1,197.00$800.00$785.00
53215IN PVC gravity sewer 6FT-12FT depth (797-05.64)LF650$368.00$450.00$326.00$275.00
53315IN PVC gravity sewer 12FT-18FT depth (797-05.65)LF700$281.00$585.00$360.00$345.00
53448IN manhole 0FT-4FT depth (797-07.01)EACH3$8,160.00$8,750.00$5,700.00$5,500.00
53548IN manhole 4FT-6FT depth (797-07.02)EACH5$9,340.00$8,750.00$6,800.00$6,000.00
53648IN manhole 6FT-8FT depth (797-07.03)EACH1$10,220$8,750.00$7,700.00$6,500.00
53748IN manhole 8FT-10FT depth (797-07.04)EACH6$11,090$9,000.00$8,500.00$7,000.00
53848IN manhole 10FT-12FT depth (797-07.05)EACH4$11,970$9,500.00$9,500.00$7,500.00
53948IN manhole 12FT-14FT depth (797-07.06)EACH2$13,410$9,500.00$10,200$9,000.00
54048IN manhole 14FT-16FT depth (797-07.07)EACH3$15,400$11,000$11,000$10,000
54148IN manhole 16FT-20FT depth (797-07.08)EACH2$18,370$13,500$12,550$12,000
54260IN manhole 4FT-6FT depth (797-07.13)EACH1$10,410$12,500$8,900.00$8,500.00
54360IN manhole 6FT-8FT depth (797-07.14)EACH2$11,570$12,500$9,500.00$9,000.00
54460IN manhole 8FT-10FT depth (797-07.15)EACH3$13,290$12,500$10,600$9,500.00
54560IN manhole 10FT-12FT depth (797-07.16)EACH13$15,430$13,500$12,300$11,000
54660IN manhole 12FT-14FT depth (797-07.17)EACH5$17,230$14,000$13,500$12,000
54760IN manhole 14FT-16FT depth (797-07.18)EACH12$19,030$14,500$14,500$13,000
54860IN manhole 16FT-20FT depth (797-07.19)EACH6$21,850$17,000$19,100$15,000
54960IN manhole 20FT-24FT depth (797-07.20)EACH7$25,550$25,000$31,200$17,000
55072IN manhole 10FT-12FT depth (797-07.27)EACH2$18,950$15,500$38,000$13,000
551Manhole drop connection assembly (797-07.56)EACH6$10,190$3,500.00$7,000.00$3,200.00
552Adjust existing manhole (797-07.60)EACH20$1,850.00$4,250.00$1,300.00$2,300.00
553Remove sewer manhole (797-07.80)EACH3$1,270.00$5,000.00$3,900.00$875.00
5546IN clean out assembly (797-08.08)EACH25$1,250.00$4,500.00$3,800.00$1,700.00
5558IN clean out assembly (797-08.09)EACH25$1,140.00$6,500.00$5,100.00$1,720.00
556Connect service lines (all sizes) (797-08.20)EACH43$9,420.00$24,500$25,000$4,600.00
55716IN gate valve assembly (797-08.67)EACH2$23,420$27,500$21,000$21,500
558Connect EX. 8IN sewer to new manhole (797-10.09)EACH14$3,300.00$8,500.00$9,300.00$6,300.00
559Connect EX.10-18IN sewer to new manhole (797-10.10)EACH6$5,510.00$11,000$22,800$6,400.00
560Connect EX. >18IN sewer to new manhole (797-10.11)EACH2$9,660.00$61,500$34,000$6,500.00
561Connect to existing pump station (797-10.12)EACH1$8,640.00$21,000$8,000.00$7,000.00
562Connect to 2IN force main (797-10.14)EACH1$6,370.00$8,000.00$5,500.00$5,000.00
563Connect to 3IN force main (797-10.15)EACH1$5,850.00$8,000.00$6,500.00$5,500.00
564Connect to 4IN force main (797-10.16)EACH2$5,600.00$8,500.00$9,600.00$5,500.00
565Connect to 8IN force main (797-10.18)EACH1$11,730$13,500$13,000$6,000.00
566Connect to 12IN force main (797-10.20)EACH2$7,030.00$9,500.00$17,500$7,000.00
567Retirein place 48IN manhole (797-11.25)EACH25$2,140.00$3,300.00$3,800.00$1,500.00
568Retirein place 60IN manhole (797-11.26)EACH6$3,540.00$3,300.00$7,700.00$1,500.00
569Retirein place 72IN manhole (797-11.27)EACH4$4,860.00$3,500.00$15,000$1,500.00
570Retirein place existing sewer 8IN-14IN (797-11.31)LF1,408$37.60$20.00$35.00$15.00
571Retirein place existing sewer 15IN-24IN (797-11.32)LF8,565$32.00$40.00$45.00$15.00
572Remove existing sewer 8IN-14IN (797-11.35)LF540$30.45$75.00$45.00$20.00
573Remove existing sewer 15IN-24IN (797-11.36)LF1,173$49.00$75.00$50.00$20.00
574By-pass pumping (797-11.38)LS1$171,920$900,000$579,000$150,000
575TV inspection (797-11.39)LF17,000$4.00$4.00$9.20$2.50
TDOT contract CN263057: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of June 26, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy