TDOT contract CN263057 bid tabulation
The widening on s.r. 268 from u.s. 41 (u.s. 70s, s.r. 1, nw broad street) (l.m. 0.00) to u.s. 231 (s.r. 10, memorial boulevard) (l.m. 4.39), including bridges, retaining walls, signals, lighting, and paving. Let by Tennessee DOT on June 26, 2026, Rutherford County. 4 bids received; low bid $123,233,326 by Civil Constructors, LLC.
- Owner
- Tennessee DOT
- Letting
- 26 JUN 2026
- Pay items
- 575
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Civil Constructors, LLC | $123,233,326 | Low |
| 2 | Cleary Construction, Inc. | $126,995,936 | +3.0% |
| 3 | MasTec Civil, LLC | $129,842,743 | +5.0% |
| 4 | Jones Bros. Contractors, LLC | $142,677,585 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Civil Constructors, LLC | 2. Cleary Construction, Inc. | 3. MasTec Civil, LLC | 4. Jones Bros. Contractors, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $783,450 | $675,000 | $1,220,000 | $975,000 |
| 2 | CPM project schedule (108-03) | LS | 1 | $207,800 | $201,000 | $40,000 | $275,000 |
| 3 | Trainee (109-10.01) | HR | 6,700 | $0.80 | $0.80 | $0.80 | $0.80 |
| 4 | Clearing and grubbing (201-01) | LS | 1 | $532,943 | $1,538,000 | $1,160,000 | $9,900,000 |
| 5 | Removal of structures and obstructions (202-01) | LS | 1 | $356,650 | $365,000 | $50,000 | $50,000 |
| 6 | Removal of pipe (8") (202-02.01) | LF | 9 | $53.75 | $28.00 | $45.00 | $50.00 |
| 7 | Removal of pipe (12") (202-02.02) | LF | 262 | $28.40 | $28.00 | $30.00 | $40.00 |
| 8 | Removal of pipe (15") (202-02.03) | LF | 408 | $28.80 | $28.00 | $35.00 | $40.00 |
| 9 | Removal of pipe (18") (202-02.04) | LF | 4,837 | $27.40 | $28.00 | $42.00 | $40.00 |
| 10 | Removal of pipe (24") (202-02.05) | LF | 2,396 | $24.40 | $28.00 | $55.00 | $40.00 |
| 11 | Removal of pipe (30") (202-02.06) | LF | 935 | $29.30 | $33.00 | $65.00 | $40.00 |
| 12 | Removal of pipe (36") (202-02.07) | LF | 209 | $39.15 | $42.00 | $62.00 | $50.00 |
| 13 | Removal of pipe (60") (202-02.08) | LF | 123 | $68.25 | $60.00 | $105.00 | $350.00 |
| 14 | Removal of pipe (22" X 14") (202-02.09) | LF | 134 | $27.95 | $28.00 | $67.00 | $40.00 |
| 15 | Removal of pipe (24" X 18") (202-02.10) | LF | 95 | $28.35 | $28.00 | $49.00 | $40.00 |
| 16 | Removal of pipe (30" X 20") (202-02.11) | LF | 51 | $31.65 | $28.00 | $63.00 | $50.00 |
| 17 | Removal of pipe (30" X 24") (202-02.12) | LF | 69 | $32.70 | $28.00 | $74.00 | $50.00 |
| 18 | Removal of pipe (30" X 18") (202-02.13) | LF | 81 | $31.90 | $28.00 | $65.00 | $50.00 |
| 19 | Removal of pipe (48" X 30") (202-02.14) | LF | 132 | $53.70 | $33.00 | $66.00 | $65.00 |
| 20 | Removal of rigid pavement, sidewalk, etc. (202-03) | SY | 342 | $25.00 | $16.50 | $46.00 | $15.00 |
| 21 | Removal of asphalt pavement (202-03.01) | SY | 16,491 | $8.80 | $5.15 | $19.00 | $10.00 |
| 22 | Road & drainage excavation (unclassified) (203-01) | CY | 136,616 | $39.10 | $43.40 | $23.00 | $25.00 |
| 23 | Borrow excavation (graded solid rock) (203-02.01) | TON | 132,885 | $35.25 | $24.50 | $30.00 | $30.00 |
| 24 | Borrow excavation (unclassified) (203-03) | CY | 42,697 | $16.50 | $0.75 | $17.00 | $8.00 |
| 25 | Placing and spreading topsoil (203-04) | CY | 15,553.52 | $34.70 | $28.00 | $17.00 | $15.00 |
| 26 | Undercutting (203-05) | CY | 70,400 | $34.85 | $19.65 | $24.00 | $18.00 |
| 27 | Water (203-06) | MG | 1,299 | $10.00 | $67.75 | $28.00 | $1.00 |
| 28 | Construction of haul road (203-50) | LS | 1 | $308,320 | $203,000 | $380,000 | $540,000 |
| 29 | Foundation fill material (204-08) | CY | 53 | $115.00 | $111.00 | $120.00 | $130.00 |
| 30 | Backfill material (flowable fill) (204-08.01) | CY | 12 | $580.00 | $309.00 | $475.00 | $450.00 |
| 31 | RSS backfill material (205-02.01) | CY | 20,287 | $37.20 | $17.50 | $61.00 | $40.00 |
| 32 | 15" temporary slope drain (209-02.06) | LF | 60 | $30.00 | $8.00 | $20.00 | $30.00 |
| 33 | 18" temporary slope drain (209-02.07) | LF | 2,724 | $36.00 | $10.00 | $30.00 | $35.00 |
| 34 | 24" temporary slope drain (209-02.08) | LF | 2,236 | $52.00 | $12.00 | $35.00 | $50.00 |
| 35 | 30" temporary slope drain (209-02.09) | LF | 380 | $67.00 | $14.00 | $45.00 | $65.00 |
| 36 | Sediment removal (209-05) | CY | 2,584 | $18.00 | $46.10 | $23.00 | $20.00 |
| 37 | Temporary silt fence (with backing) (209-08.02) | LF | 10,675 | $6.00 | $5.85 | $5.00 | $4.50 |
| 38 | Temporary silt fence (without backing) (209-08.03) | LF | 36,651 | $2.20 | $2.10 | $3.00 | $2.50 |
| 39 | Rock check dam (209-08.07) | EACH | 10 | $800.00 | $778.00 | $990.00 | $1,000.00 |
| 40 | Enhanced rock check dam (209-08.08) | EACH | 46 | $800.00 | $778.00 | $1,400.00 | $1,200.00 |
| 41 | Sediment filter bag (15' X 15') (209-09.03) | EACH | 4 | $573.00 | $953.00 | $360.00 | $700.00 |
| 42 | Curb inlet protection (type 4) (209-09.43) | EACH | 256 | $143.00 | $139.00 | $155.00 | $130.00 |
| 43 | Catch basin protection (type A) (209-40.30) | EACH | 8 | $860.00 | $778.00 | $460.00 | $390.00 |
| 44 | Catch basin protection (type D) (209-40.33) | EACH | 59 | $201.00 | $194.00 | $335.00 | $280.00 |
| 45 | Temporary in stream diversion (209-65.04) | LF | 467 | $57.30 | $55.55 | $130.00 | $75.00 |
| 46 | Mineral aggregate, type A base, grading D (303-01) | TON | 168,267 | $29.15 | $29.70 | $27.00 | $25.00 |
| 47 | Granular backfill (roadway) (303-01.01) | TON | 926 | $48.15 | $50.40 | $36.00 | $60.00 |
| 48 | Mineral aggregate (size 57) (303-10.01) | TON | 468 | $65.36 | $50.40 | $57.00 | $65.00 |
| 49 | Mineral aggregate (size 57 - pabe) (303-10.04) | TON | 292 | $115.00 | $111.00 | $66.50 | $98.00 |
| 50 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 12,499 | $116.90 | $100.50 | $114.00 | $125.00 |
| 51 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 12,291 | $127.25 | $104.00 | $123.00 | $128.00 |
| 52 | Asp. conc. mix(PG64-22) (BPMB-HM) GR. A-S (307-01.20) | TON | 1,006 | $128.35 | $145.00 | $125.00 | $150.00 |
| 53 | Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21) | TON | 31,467 | $113.50 | $102.70 | $111.00 | $130.00 |
| 54 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01) | TON | 41,919 | $100.85 | $106.00 | $100.00 | $114.00 |
| 55 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08) | TON | 20,595 | $113.50 | $114.40 | $111.00 | $119.00 |
| 56 | Bituminous material for prime coat (PC) (402-01) | TON | 387 | $1,260.00 | $1,100.00 | $1,210.00 | $1,050.00 |
| 57 | Aggregate for cover material (PC) (402-02) | TON | 1,371 | $80.25 | $75.30 | $77.00 | $50.00 |
| 58 | Bituminous material for tack coat (TC) (403-01) | TON | 111 | $1,150.00 | $1,060.00 | $1,100.00 | $1,000.00 |
| 59 | Saw cutting asphalt pavement (407-20.05) | LF | 575 | $4.05 | $8.90 | $8.00 | $5.00 |
| 60 | Acs mix (PG64-22) grading E shoulder (411-01.07) | TON | 1,479 | $175.35 | $140.00 | $171.00 | $156.00 |
| 61 | Acs mix(PG64-22) grading D (411-01.10) | TON | 5,492 | $174.25 | $173.00 | $169.00 | $170.00 |
| 62 | Acs mix(PG70-22) grading D (411-02.10) | TON | 12,978 | $169.65 | $147.30 | $162.80 | $155.00 |
| 63 | Cold planing bituminous pavement (415-01.02) | SY | 11,856 | $6.30 | $5.15 | $6.20 | $6.65 |
| 64 | Class A concrete (roadway) (604-01.01) | CY | 131 | $1,400.00 | $1,390.00 | $2,100.00 | $1,300.00 |
| 65 | Steel bar reinforcement (roadway) (604-01.02) | LB | 28,439 | $1.50 | $1.45 | $1.50 | $1.50 |
| 66 | Box tube safety rail (604-01.20) | LF | 299 | $288.00 | $265.00 | $170.00 | $300.00 |
| 67 | Retaining wall (begin sta.166+14.00 to end sta.166+95.00) (604-07.01) | SF | 335 | $148.00 | $225.00 | $150.00 | $130.00 |
| 68 | Retaining wall (begin sta.234+82.75 to end sta.237+00.00) (604-07.02) | SF | 1,013 | $148.00 | $165.00 | $160.00 | $100.00 |
| 69 | Retaining wall (tree wall - driveway at 168+92.18) (604-07.03) | SF | 285 | $160.00 | $164.00 | $110.00 | $100.00 |
| 70 | Retaining wall (tree wall - begin sta. 236+50.00TO end sta. 236+81.82) (604-07.04) | SF | 97 | $215.00 | $162.00 | $110.00 | $100.00 |
| 71 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 13,041 | $123.60 | $140.00 | $93.00 | $111.00 |
| 72 | 18" concrete pipe culvert (class IV) (607-03.03) | LF | 92 | $260.00 | $162.00 | $168.00 | $133.00 |
| 73 | 24" concrete pipe culvert (class III) (607-05.02) | LF | 4,121 | $203.60 | $178.00 | $118.00 | $121.00 |
| 74 | 30" concrete pipe culvert (class III) (607-06.02) | LF | 5,366 | $240.00 | $208.00 | $150.00 | $155.00 |
| 75 | 36" concrete pipe culvert (class III) (607-07.02) | LF | 4,507 | $448.00 | $357.00 | $196.00 | $185.00 |
| 76 | 42" concrete pipe culvert (class III) (607-08.02) | LF | 1,657 | $1,080.00 | $463.00 | $272.00 | $280.00 |
| 77 | 42" concrete pipe culvert (class IV) (607-08.03) | LF | 2,748 | $1,270.00 | $563.00 | $297.00 | $390.00 |
| 78 | 54" concrete pipe culvert (class IV) (607-10.03) | LF | 125 | $2,600.00 | $827.00 | $490.00 | $1,600.00 |
| 79 | 23"X 14" horizontal oval concrete pipe culvert (607-16.01) | LF | 111 | $233.00 | $134.00 | $151.00 | $100.00 |
| 80 | 30"X 19" horizontal oval concrete pipe culvert (607-16.02) | LF | 964 | $228.00 | $165.00 | $184.00 | $105.00 |
| 81 | 38"X 24" horizontal oval concrete pipe culvert (607-16.04) | LF | 229 | $279.00 | $198.00 | $224.00 | $380.00 |
| 82 | 45"X 29" horizontal oval concrete pipe culvert (607-16.06) | LF | 197 | $515.00 | $235.00 | $268.00 | $385.00 |
| 83 | 60"X 38" horizontal oval concrete pipe culvert (607-16.09) | LF | 350 | $462.00 | $335.00 | $370.00 | $1,100.00 |
| 84 | 18" pipe culvert (side drain) (607-39.02) | LF | 548 | $106.00 | $95.15 | $125.00 | $113.00 |
| 85 | Manholes, > 4' - 8' depth (611-01.02) | EACH | 6 | $9,140.00 | $6,480.00 | $8,300.00 | $8,100.00 |
| 86 | Manholes, > 8' - 12' depth (611-01.03) | EACH | 3 | $12,710 | $8,810.00 | $8,300.00 | $19,500 |
| 87 | Junction box, type 1 (611-02.10) | EACH | 1 | $12,210 | $7,350.00 | $7,000.00 | $8,300.00 |
| 88 | Class A concrete (pipe endwalls) (611-07.01) | CY | 67 | $1,670.00 | $1,640.00 | $3,300.00 | $2,750.00 |
| 89 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 2,768 | $9.05 | $5.20 | $2.00 | $3.00 |
| 90 | 18IN endwall (side drain) (611-07.31) | EACH | 32 | $4,060.00 | $2,590.00 | $4,500.00 | $4,700.00 |
| 91 | 24IN endwall (side drain) (611-07.32) | EACH | 10 | $5,290.00 | $3,250.00 | $6,000.00 | $6,500.00 |
| 92 | 18IN endwall (cross drain) 3:1 (611-07.54) | EACH | 16 | $3,630.00 | $1,940.00 | $5,000.00 | $2,100.00 |
| 93 | 30IN endwall (cross drain) 3:1 (611-07.60) | EACH | 2 | $6,300.00 | $5,510.00 | $5,200.00 | $6,800.00 |
| 94 | 36IN endwall (cross drain) 3:1 (611-07.63) | EACH | 4 | $7,800.00 | $7,370.00 | $6,800.00 | $8,800.00 |
| 95 | 42IN endwall (cross drain) 3:1 (611-07.66) | EACH | 2 | $9,320.00 | $9,900.00 | $7,900.00 | $12,100 |
| 96 | Catch basins, type 12, 0' - 4' depth (611-12.01) | EACH | 12 | $8,620.00 | $5,710.00 | $6,200.00 | $7,300.00 |
| 97 | Catch basins, type 12, > 4' - 8' depth (611-12.02) | EACH | 105 | $9,790.00 | $6,520.00 | $7,100.00 | $7,800.00 |
| 98 | Catch basins, type 12, > 8' - 12' depth (611-12.03) | EACH | 23 | $12,650 | $8,540.00 | $9,200.00 | $9,500.00 |
| 99 | Catch basins, type 12, > 12' - 16' depth (611-12.04) | EACH | 7 | $17,230 | $11,800 | $11,100 | $12,100 |
| 100 | Catch basins, type 12, > 16' - 20' depth (611-12.05) | EACH | 4 | $20,430 | $18,600 | $13,300 | $17,300 |
| 101 | Catch basins, type 12, > 20' - 24' depth (611-12.06) | EACH | 3 | $33,230 | $19,900 | $20,500 | $16,200 |
| 102 | Catch basins, type 12, > 24' - 28' depth (611-12.07) | EACH | 6 | $37,650 | $29,200 | $23,700 | $17,600 |
| 103 | Catch basins, type 14, 0' - 4' depth (611-14.01) | EACH | 2 | $14,000 | $7,550.00 | $9,500.00 | $10,300 |
| 104 | Catch basins, type 14, > 4' - 8' depth (611-14.02) | EACH | 39 | $21,560 | $11,000 | $12,400 | $13,500 |
| 105 | Catch basins, type 14, > 8' - 12' depth (611-14.03) | EACH | 10 | $24,810 | $17,600 | $18,800 | $19,500 |
| 106 | Catch basins, type 14, > 12' - 16' depth (611-14.04) | EACH | 6 | $32,280 | $21,300 | $20,700 | $23,400 |
| 107 | Catch basins, type 14, > 16' - 20' depth (611-14.05) | EACH | 6 | $34,550 | $27,500 | $24,000 | $27,300 |
| 108 | Catch basins, type 14, > 20' - 24' depth (611-14.06) | EACH | 2 | $49,780 | $34,300 | $34,300 | $27,900 |
| 109 | Catch basins, type 42, 0' - 4' depth (611-42.01) | EACH | 20 | $7,130.00 | $5,270.00 | $5,100.00 | $6,800.00 |
| 110 | Catch basins, type 42, > 4' - 8' depth (611-42.02) | EACH | 4 | $7,930.00 | $6,850.00 | $6,600.00 | $8,200.00 |
| 111 | 18" temporary drainage pipe (621-03.02) | LF | 252 | $65.00 | $82.90 | $64.00 | $73.00 |
| 112 | 24" temporary drainage pipe (621-03.03) | LF | 18 | $100.00 | $139.00 | $130.00 | $132.00 |
| 113 | 36" temporary drainage pipe (621-03.05) | LF | 16 | $175.00 | $187.00 | $156.00 | $150.00 |
| 114 | Concrete sidewalk (4 ") (701-01.01) | SF | 126,976 | $7.80 | $7.55 | $7.70 | $6.70 |
| 115 | Concrete driveway (701-02) | SF | 36,414 | $11.25 | $10.90 | $10.60 | $9.70 |
| 116 | Concrete curb ramp (701-02.03) | SF | 17,001 | $10.90 | $10.55 | $18.00 | $9.35 |
| 117 | Concrete curb (702-01) | CY | 69 | $869.00 | $842.00 | $900.00 | $758.00 |
| 118 | Concrete combined curb & gutter (702-03) | CY | 4,424 | $466.00 | $452.00 | $540.00 | $400.00 |
| 119 | Metal beam guard fence (705-01.04) | LF | 104 | $105.00 | $133.00 | $101.00 | $120.00 |
| 120 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 6,448 | $31.50 | $31.10 | $30.50 | $28.00 |
| 121 | GR terminaltrailing end (type 13) MASH TL-3 (705-06.10) | EACH | 3 | $2,180.00 | $1,560.00 | $2,090.00 | $1,400.00 |
| 122 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 15 | $4,300.00 | $3,670.00 | $4,125.00 | $3,300.00 |
| 123 | Thrie beam bridge transition MASH TL-3 (705-06.25) | EACH | 4 | $3,380.00 | $3,110.00 | $3,245.00 | $2,800.00 |
| 124 | Guardrail removed (706-01) | LF | 4,528 | $0.55 | $1.35 | $0.60 | $1.20 |
| 125 | High-visibility construction fence (707-08.11) | LF | 2,300 | $2.20 | $2.10 | $3.30 | $3.00 |
| 126 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 105 | $591.00 | $333.00 | $330.00 | $365.00 |
| 127 | Machined rip-rap (class A-3) (709-05.05) | TON | 5,940 | $60.25 | $50.00 | $61.00 | $70.00 |
| 128 | Machined rip-rap (class A-1) (709-05.06) | TON | 7,858 | $77.90 | $55.80 | $75.00 | $70.00 |
| 129 | Machined rip-rap (class B) (709-05.08) | TON | 1,720 | $71.65 | $49.95 | $92.00 | $70.00 |
| 130 | Aggregate underdrains (with pipe) (710-02) | LF | 36,260 | $14.05 | $13.60 | $15.00 | $13.25 |
| 131 | Single slope half concrete barrier wall (711-05.72) | LF | 218 | $252.00 | $245.00 | $255.00 | $415.00 |
| 132 | Traffic control (712-01) | LS | 1 | $850,075 | $510,000 | $200,000 | $1,300,000 |
| 133 | Interconnected portable barrier rail (712-02.02) | LF | 5,941 | $54.75 | $28.65 | $88.00 | $36.00 |
| 134 | Portable barrier rail (MASH TL-3) (712-02.10) | LF | 450 | $137.00 | $50.00 | $86.00 | $150.00 |
| 135 | Portable barrier rail, reduced deflection (MASH TL-3) (712-02.12) | LF | 450 | $142.00 | $123.00 | $88.00 | $220.00 |
| 136 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 12 | $10,540 | $6,450.00 | $13,200 | $9,500.00 |
| 137 | Flexible drums (channelizing) (712-04.01) | EACH | 2,858 | $55.00 | $53.30 | $11.00 | $33.00 |
| 138 | Barrier rail delineator (712-04.50) | EACH | 1,493 | $16.05 | $15.55 | $8.25 | $15.00 |
| 139 | Warning lights (type A) (712-05.01) | EACH | 156 | $36.70 | $35.55 | $36.00 | $20.00 |
| 140 | Signs (construction) (712-06) | SF | 5 | $28.65 | $27.75 | $7.00 | $30.00 |
| 141 | Temporary barricades (type III) (712-07.03) | LF | 1,560 | $6.90 | $6.65 | $23.00 | $25.00 |
| 142 | Arrow board (type C) (712-08.03) | EACH | 5 | $2,750.00 | $2,670.00 | $990.00 | $1,500.00 |
| 143 | Removable pavement marking (6" line) (712-09.08) | LF | 4,400 | $3.00 | $2.90 | $2.90 | $2.60 |
| 144 | Removable wet reflective pavement marking tape (712-09.21) | LF | 1,600 | $3.00 | $2.90 | $2.90 | $2.60 |
| 145 | Class A concrete (foundation for sign supports) (713-01.01) | CY | 1 | $802.00 | $778.00 | $800.00 | $700.00 |
| 146 | Steel bar reinforcement(foundation for sign supports) (713-01.02) | LB | 294 | $4.25 | $4.10 | $3.60 | $3.70 |
| 147 | Sign post delineation enhancement (713-02.21) | LF | 160 | $4.35 | $4.20 | $5.00 | $3.80 |
| 148 | Flexible tubular delineator (713-02.30) | EACH | 110 | $66.50 | $64.45 | $110.00 | $58.00 |
| 149 | Steel I-beams & WF-beams(breakaway) sign support (713-06) | LB | 640 | $9.45 | $9.15 | $8.50 | $8.25 |
| 150 | "U" section steel posts (713-11.01) | LB | 2,793 | $4.75 | $4.60 | $4.00 | $4.15 |
| 151 | Perforated/knockout square tube post (713-11.02) | LB | 164 | $5.15 | $5.00 | $5.00 | $4.50 |
| 152 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 584 | $17.35 | $16.85 | $14.00 | $15.15 |
| 153 | Extruded aluminum panel signs (713-14) | SF | 115 | $33.80 | $32.75 | $37.00 | $29.50 |
| 154 | Street name sign (rigid 0.100IN thick (713-14.21) | SF | 72 | $28.65 | $27.75 | $39.00 | $25.00 |
| 155 | Street name sign (suspended 0.100IN thick) (713-14.22) | SF | 493 | $25.20 | $24.45 | $44.00 | $84.00 |
| 156 | Removal & relocation of sign & support (713-15.02) | EACH | 1 | $287.00 | $278.00 | $3,520.00 | $250.00 |
| 157 | Suspended flat sheet aluminum sign (0.080" thick) (713-15.07) | EACH | 41 | $128.00 | $124.00 | $505.00 | $112.00 |
| 158 | Remove sign, support & footing (713-15.36) | EACH | 3 | $229.00 | $220.00 | $43.00 | $200.00 |
| 159 | Changeable message sign unit (713-16.01) | EACH | 10 | $11,690 | $11,300 | $4,400.00 | $11,000 |
| 160 | Jacked or bored conduit (714-03) | LF | 5,450 | $68.75 | $16.85 | $119.00 | $15.00 |
| 161 | Direct burial conduit (2" PVC, schedule 40) (714-03.01) | LF | 22,560 | $20.65 | $14.25 | $15.50 | $12.70 |
| 162 | Pull boxes (mte UM35L) (714-05.06) | EACH | 180 | $1,380.00 | $1,960.00 | $2,000.00 | $1,750.00 |
| 163 | Cable (1/0 AK triplex) (714-06.08) | LF | 32,380 | $8.95 | $6.25 | $3.60 | $5.55 |
| 164 | Cable (#6 solid bare copper soft drawn, ground) (714-06.09) | LF | 1,000 | $2.50 | $2.85 | $4.00 | $2.53 |
| 165 | Cable (#2 acsr) (714-06.10) | LF | 10,000 | $1.70 | $4.60 | $12.30 | $4.11 |
| 166 | Light standards (45' M.H., single) (714-08.09) | EACH | 120 | $7,530.00 | $5,610.00 | $5,877.78 | $5,000.00 |
| 167 | Light standards (45' M.H., double) (714-08.10) | EACH | 4 | $7,790.00 | $5,610.00 | $8,000.00 | $5,000.00 |
| 168 | Foundation (only) for light standard (714-08.20) | EACH | 122 | $2,520.00 | $2,240.00 | $3,630.00 | $2,000.00 |
| 169 | Remove & relocate light standard (714-08.29) | LS | 1 | $4,150.00 | $1,120.00 | $7,400.00 | $1,000.00 |
| 170 | Removal of light standard & foundation (714-08.32) | EACH | 45 | $287.00 | $1,680.00 | $670.00 | $1,500.00 |
| 171 | Luminaires (147 watt single LED offset, light standard mounted) (714-09.09) | EACH | 120 | $1,290.00 | $1,120.00 | $1,206.00 | $1,000.00 |
| 172 | Luminaires (147 watt double LED offset, light standard mounted) (714-09.11) | EACH | 4 | $1,290.00 | $1,120.00 | $1,278.00 | $1,000.00 |
| 173 | Luminaires (147 watt LED offset, utility pole mounted by others) (714-09.12) | EACH | 4 | $1,700.00 | $1,120.00 | $1,278.00 | $1,000.00 |
| 174 | Luminaires (208 watt LED offset, utility pole mounted by others) (714-09.13) | EACH | 4 | $1,860.00 | $1,120.00 | $1,450.00 | $1,000.00 |
| 175 | Luminaires (147 watt LED offset, signal pole mounted) (714-09.15) | EACH | 18 | $1,290.00 | $1,120.00 | $1,280.00 | $1,000.00 |
| 176 | Luminaires (208 watt LED offset, signal pole mounted) (714-09.16) | EACH | 3 | $1,450.00 | $1,120.00 | $1,450.00 | $1,000.00 |
| 177 | Luminaires (147 watt LED offset, existing wood pole mounted) (714-09.17) | EACH | 1 | $1,290.00 | $1,120.00 | $1,280.00 | $3,500.00 |
| 178 | Electrical connection (psa) (714-25.01) | LS | 1 | $9,900.00 | $3,930.00 | $4,280.00 | $3,500.00 |
| 179 | Electrical connection (PSB) (714-25.02) | LS | 1 | $12,880 | $3,930.00 | $4,650.00 | $3,500.00 |
| 180 | Electrical connection (PSC) (714-25.03) | LS | 1 | $12,880 | $3,930.00 | $4,650.00 | $3,500.00 |
| 181 | Electrical connection (PSD) (714-25.04) | LS | 1 | $12,880 | $3,930.00 | $4,650.00 | $3,500.00 |
| 182 | Electrical connection (pse) (714-25.05) | LS | 1 | $12,880 | $3,930.00 | $4,650.00 | $3,500.00 |
| 183 | Electrical connection (PSF) (714-25.08) | LS | 1 | $12,880 | $3,930.00 | $4,650.00 | $3,500.00 |
| 184 | Electrical connection (PSG) (714-25.09) | EACH | 1 | $12,880 | $3,930.00 | $4,650.00 | $3,500.00 |
| 185 | Temporary raised pavement marker (716-01.05) | EACH | 870 | $9.15 | $8.90 | $9.00 | $8.00 |
| 186 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 3,591 | $42.40 | $41.10 | $41.50 | $37.00 |
| 187 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 59 | $42.40 | $41.10 | $41.50 | $37.00 |
| 188 | Removal of snowplowable reflective marker (716-01.30) | EACH | 600 | $11.45 | $11.10 | $11.00 | $10.00 |
| 189 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 59 | $40.10 | $38.90 | $39.00 | $35.00 |
| 190 | Plastic pavement marking (stop line) (716-02.05) | LF | 1,809 | $20.65 | $20.00 | $20.00 | $18.00 |
| 191 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 192 | $189.00 | $183.00 | $184.00 | $165.00 |
| 192 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 751 | $2.30 | $2.20 | $2.30 | $2.00 |
| 193 | Plastic pavement marking (longitudinal cross-walk) (716-02.09) | LF | 3,591 | $40.10 | $38.90 | $39.00 | $35.00 |
| 194 | Plastic pavement marking (8IN line) (716-02.12) | LM | 0.20 | $8,600.00 | $8,330.00 | $8,376.00 | $7,500.00 |
| 195 | Plastic pavement marking (straight-turn arrow) (716-04.01) | EACH | 7 | $344.00 | $333.00 | $335.00 | $300.00 |
| 196 | Plastic pavement marking(double turning arrow) (716-04.02) | EACH | 3 | $344.00 | $333.00 | $335.00 | $300.00 |
| 197 | Plastic pavement marking (transverse shoulder) (716-04.04) | LF | 75 | $8.00 | $7.80 | $8.00 | $7.00 |
| 198 | Plastic pavement marking (straight arrow) (716-04.05) | EACH | 4 | $189.00 | $183.00 | $185.00 | $165.00 |
| 199 | Plastic pavement marking (bikelane symbol & arrow) (716-04.13) | EACH | 14 | $470.00 | $455.00 | $458.00 | $410.00 |
| 200 | Plastic pavement marking-bike symbol/arrow shared (716-04.15) | EACH | 1 | $470.00 | $455.00 | $458.00 | $410.00 |
| 201 | Painted pavement marking (channelization striping) (716-05.04) | SY | 28 | $17.20 | $16.65 | $17.00 | $15.00 |
| 202 | Painted pavement marking (stop line) (716-05.05) | LF | 1,410 | $11.45 | $11.10 | $12.00 | $10.00 |
| 203 | Painted pavement marking (turn lane arrow) (716-05.06) | EACH | 80 | $68.75 | $66.65 | $67.00 | $60.00 |
| 204 | Painted pavement markings(8" line) (716-05.49) | LM | 18.90 | $1,490.00 | $1,440.00 | $1,452.00 | $1,300.00 |
| 205 | Removal of pavement marking (channelization striping) (716-08.04) | SY | 100 | $8.60 | $8.35 | $8.40 | $7.50 |
| 206 | Removal of pavement marking (stop line) (716-08.05) | LF | 1,233 | $5.75 | $5.55 | $5.60 | $5.00 |
| 207 | Removal of pavement marking (turn lane arrow) (716-08.06) | EACH | 56 | $57.30 | $55.55 | $56.00 | $50.00 |
| 208 | Removal of pavement marking (line) (716-08.20) | LM | 11.50 | $5,730.00 | $5,550.00 | $5,584.00 | $5,000.00 |
| 209 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 40.50 | $7,450.00 | $7,220.00 | $7,259.00 | $6,500.00 |
| 210 | Mobilization (717-01) | LS | 1 | $2,289,200 | $6,000,000 | $12,985,000 | $14,250,000 |
| 211 | Field office (type 2) (722-01.02) | LS | 1 | $113,230 | $358,000 | $250,000 | $275,000 |
| 212 | CCTV pole removal (725-20.05) | EACH | 2 | $573.00 | $1,680.00 | $1,800.00 | $1,500.00 |
| 213 | CCTV camera system (see footnote) (725-20.94) | EACH | 8 | $11,760 | $6,170.00 | $6,300.00 | $5,500.00 |
| 214 | Network switch (see footnote) (725-21.15) | EACH | 8 | $9,900.00 | $11,200 | $6,030.00 | $5,500.00 |
| 215 | Removal of signal equipment (730-01.02) | EACH | 4 | $1,720.00 | $16,800 | $3,820.00 | $1,500.00 |
| 216 | Modification of existing traffic signal equipment (730-01.03) | EACH | 4 | $1,470.00 | $2,810.00 | $32,300 | $1,280.00 |
| 217 | Remove & relocate school signal equipment (730-01.05) | LS | 1 | $2,770.00 | $5,610.00 | $4,300.00 | $2,420.00 |
| 218 | Signal head assembly (130 A3 with backplate) (730-02.03) | EACH | 10 | $1,600.00 | $1,510.00 | $1,700.00 | $1,399.00 |
| 219 | Signal head assembly (130 pole mounted) (730-02.08) | EACH | 1 | $1,740.00 | $1,230.00 | $1,360.00 | $1,519.00 |
| 220 | Signal head assembly (130 with backplate) (730-02.09) | EACH | 52 | $1,600.00 | $1,510.00 | $1,690.00 | $1,399.00 |
| 221 | Signal head assembly (140 A4F with backplate) (730-02.59) | EACH | 33 | $2,290.00 | $1,800.00 | $2,075.00 | $2,002.00 |
| 222 | Install pull box (type B) (730-03.21) | EACH | 77 | $1,150.00 | $3,930.00 | $1,240.00 | $1,000.00 |
| 223 | Install pull box (fiber optic-type A) (730-03.23) | EACH | 8 | $3,030.00 | $5,610.00 | $3,500.00 | $2,640.00 |
| 224 | Fiber optic splice fusion (730-03.33) | EACH | 8 | $481.00 | $3,370.00 | $815.00 | $420.00 |
| 225 | Fiber optic cable (48F) (730-03.50) | LF | 27,000 | $3.00 | $7.10 | $5.20 | $2.60 |
| 226 | Fiber optic cable (12F) (730-03.51) | LF | 1,200 | $2.75 | $5.85 | $6.80 | $2.40 |
| 227 | Electrical service connection (730-05.01) | EACH | 11 | $9,170.00 | $3,930.00 | $5,300.00 | $8,000.00 |
| 228 | Signal cable - 5 conductor (730-08.02) | LF | 6,700 | $2.85 | $2.65 | $3.11 | $2.50 |
| 229 | Signal cable - 7 conductor (730-08.03) | LF | 21,000 | $3.15 | $3.10 | $3.90 | $2.75 |
| 230 | Signal cable - 9 conductor (730-08.04) | LF | 3,000 | $3.45 | $3.65 | $4.00 | $3.00 |
| 231 | Riser assembly (2" PVC) (730-11.10) | EACH | 14 | $688.00 | $3,370.00 | $1,066.00 | $600.00 |
| 232 | Conduit 2" diameter (PVC schedule 40) (730-12.02) | LF | 3,700 | $20.65 | $14.25 | $24.00 | $18.00 |
| 233 | Conduit 2" diameter (directional bore) (730-12.23) | LF | 90 | $68.75 | $22.45 | $69.00 | $60.00 |
| 234 | Conduit 3" diameter (directional bore) (730-12.24) | LF | 3,650 | $74.50 | $24.70 | $75.60 | $65.00 |
| 235 | Vehicle detector (radar/video) (730-13.16) | EACH | 8 | $43,510 | $40,400 | $39,200 | $37,965 |
| 236 | Cabinet (PHB) (730-15.07) | EACH | 1 | $28,910 | $30,300 | $27,500 | $25,225 |
| 237 | Cabinet (eight phase base mounted) (730-15.32) | EACH | 7 | $29,120 | $30,300 | $30,600 | $25,410 |
| 238 | Eight phase actuated controller (730-16.02) | EACH | 8 | $7,460.00 | $5,610.00 | $8,800.00 | $6,513.00 |
| 239 | Controller (flashing beacon) (730-16.03) | EACH | 3 | $3,870.00 | $1,120.00 | $2,200.00 | $3,376.00 |
| 240 | Controller (atc) (730-16.04) | EACH | 8 | $7,460.00 | $5,610.00 | $7,500.00 | $6,513.00 |
| 241 | Guying device (angle anchor) (730-22.02) | EACH | 47 | $688.00 | $2,810.00 | $1,200.00 | $600.00 |
| 242 | Pedestal pole (type A) (730-23.28) | EACH | 18 | $4,010.00 | $7,290.00 | $3,750.00 | $3,499.00 |
| 243 | Cantilever signal support (2 @ 40' & 45') (730-23.87) | EACH | 1 | $48,190 | $64,000 | $49,000 | $42,043 |
| 244 | Cantilever signal support (1 arm @ 45') (730-23.88) | EACH | 1 | $35,380 | $54,400 | $28,200 | $30,872 |
| 245 | Cantilever signal support (2 @ 40' & 50') (730-24.85) | EACH | 2 | $56,950 | $70,700 | $59,000 | $49,685 |
| 246 | Cantilever signal support (2 @ 40' & 55') (730-24.86) | EACH | 1 | $62,040 | $74,100 | $65,000 | $54,130 |
| 247 | Cantilever signal support (2 @ 40' & 65') (730-24.88) | EACH | 2 | $65,840 | $76,900 | $71,000 | $57,443 |
| 248 | Cantilever signal support (2 @ 40' & 90') (730-24.96) | EACH | 1 | $96,400 | $99,900 | $106,000 | $84,109 |
| 249 | Cantilever signal support (3 @ 40', 50', & 70') (730-24.97) | EACH | 1 | $85,940 | $92,000 | $98,000 | $74,981 |
| 250 | Cantilever signal support (1 arm @ 50') (730-25.01) | EACH | 3 | $35,490 | $54,400 | $34,000 | $30,963 |
| 251 | Cantilever signal support (1 arm @ 55') (730-25.07) | EACH | 4 | $44,110 | $60,900 | $44,000 | $38,482 |
| 252 | Cantilever signal support (2 @ 55' & 65') (730-25.10) | EACH | 1 | $67,010 | $78,000 | $76,000 | $58,462 |
| 253 | Cantilever signal support (1 arm @ 60') (730-25.11) | EACH | 2 | $47,320 | $63,100 | $48,200 | $41,283 |
| 254 | Cantilever signal support (1 arm @ 65') (730-25.13) | EACH | 1 | $51,030 | $70,100 | $64,000 | $44,519 |
| 255 | Cantilever signal support (1 arm @ 70') (730-25.14) | EACH | 2 | $53,200 | $67,600 | $65,300 | $46,415 |
| 256 | Cantilever signal support (1 arm @ 75') (730-25.15) | EACH | 1 | $46,840 | $62,800 | $78,000 | $40,867 |
| 257 | Cantilever signal support (1 arm @ 80') (730-25.16) | EACH | 2 | $66,420 | $77,400 | $94,000 | $57,955 |
| 258 | Cantilever signal support (1 arm @ 85') (730-25.17) | EACH | 1 | $70,800 | $80,800 | $83,000 | $61,768 |
| 259 | Cantilever signal support (1 arm @ 90') (730-25.18) | EACH | 1 | $72,480 | $81,900 | $105,000 | $63,236 |
| 260 | Audible pedestrian signal (730-26.04) | EACH | 52 | $1,980.00 | $2,810.00 | $1,180.00 | $1,728.00 |
| 261 | Pedestrian pushbutton post (730-26.06) | EACH | 2 | $1,300.00 | $6,170.00 | $3,000.00 | $1,136.00 |
| 262 | Battery back-UP system (730-35.06) | EACH | 7 | $11,840 | $11,200 | $17,800 | $10,333 |
| 263 | Pedestrian hybrid beacon assembly (730-50.25) | EACH | 2 | $10,150 | $3,930.00 | $4,700.00 | $8,856.00 |
| 264 | School speed limit flashing assembly (hard-wired) (730-50.31) | EACH | 6 | $5,300.00 | $11,200 | $6,300.00 | $4,626.00 |
| 265 | Geomembrane (740-06.01) | SY | 178 | $18.10 | $81.15 | $13.20 | $40.00 |
| 266 | Geogrid reinforcement type 2 (740-07.04) | SY | 819 | $5.75 | $5.55 | $14.00 | $8.50 |
| 267 | Uniaxial geogrid reinforcement type 2 (740-07.12) | SY | 82,262 | $4.25 | $3.00 | $6.60 | $4.10 |
| 268 | Geotextile (type III)(erosion control) (740-10.03) | SY | 3,553 | $4.60 | $4.10 | $4.50 | $3.30 |
| 269 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 119,236 | $4.05 | $5.05 | $5.40 | $3.00 |
| 270 | Temporary sediment tube 20IN (740-11.04) | LF | 22,151 | $4.60 | $2.10 | $5.00 | $3.60 |
| 271 | Fiber optic storage loop(installation only) (798-06.57) | EACH | 22 | $458.00 | $561.00 | $730.00 | $500.00 |
| 272 | Transfer fiberoptic cable (798-08.06) | EACH | 1 | $3,280.00 | $35,900 | $1,000.00 | $32,000 |
| 273 | Temporary seeding (with mulch) (801-01.07) | UNIT | 840 | $51.60 | $43.30 | $50.00 | $45.00 |
| 274 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 37 | $172.00 | $63.75 | $165.00 | $150.00 |
| 275 | Water (seeding & sodding) (801-03) | MG | 1,022 | $57.30 | $55.55 | $55.00 | $50.00 |
| 276 | Sodding (new sod) (803-01) | SY | 93,321 | $5.45 | $5.30 | $6.00 | $4.75 |
| 277 | Project mowing (806-02.03) | CYCL | 6 | $5,730.00 | $5,550.00 | $11,000 | $5,000.00 |
| 278 | Class A concrete (box bridges) (604-02.01) | CY | 170 | $1,310.00 | $1,330.00 | $2,100.00 | $1,400.00 |
| 279 | Steel bar reinforcement (box bridges) (604-02.02) | LB | 33,036 | $1.50 | $1.45 | $2.40 | $1.54 |
| 280 | Removal of asbestos (202-01.02) | LS | 1 | $56,160 | $54,400 | $58,000 | $52,700 |
| 281 | Removal of structures (exist. BR. no. 75-SR268-0.84) (202-04.01) | LS | 1 | $307,170 | $298,000 | $350,000 | $750,000 |
| 282 | Dry excavation (bridges) (204-02.01) | CY | 468 | $28.65 | $27.75 | $17.30 | $40.00 |
| 283 | Wet excavation (bridges) (204-03.01) | CY | 48 | $74.50 | $72.20 | $70.00 | $75.00 |
| 284 | Rock excavation (bridges) (204-04.01) | CY | 140 | $138.00 | $133.00 | $225.00 | $100.00 |
| 285 | Rock drilling (bridges) (204-05) | LF | 48 | $57.30 | $55.55 | $100.00 | $40.00 |
| 286 | Foundation preparation(pier no. 1, sta. 56+08.00) (204-10.01) | LS | 1 | $11,460 | $11,100 | $16,300 | $60,000 |
| 287 | Foundation preparation(pier no. 2, sta. 57+48.00) (204-10.02) | LS | 1 | $11,460 | $11,100 | $16,500 | $60,000 |
| 288 | Granular backfill (bridges) (303-01.02) | TON | 112 | $51.60 | $50.00 | $100.00 | $60.00 |
| 289 | Steel structures (602-03) | LS | 1 | $4,330,540 | $4,200,000 | $3,580,000 | $3,375,000 |
| 290 | Bearing device (2 1/2" reinforced elast. bearing pad) (602-10.60) | EACH | 16 | $5,850.00 | $5,670.00 | $320.00 | $5,000.00 |
| 291 | Epoxy coated reinforcing steel (604-02.03) | LB | 284,001 | $2.05 | $2.00 | $2.05 | $1.65 |
| 292 | Class A concrete (bridges) (604-03.01) | CY | 616 | $1,290.00 | $1,250.00 | $1,600.00 | $1,000.00 |
| 293 | Steel bar reinforcement (bridges) (604-03.02) | LB | 84,652 | $1.85 | $1.80 | $2.00 | $1.75 |
| 294 | Pavement @ bridge ends (604-03.04) | SY | 416 | $544.00 | $528.00 | $470.00 | $435.00 |
| 295 | Class DS concrete (604-03.32) | CY | 966 | $1,255.00 | $1,220.00 | $1,300.00 | $1,100.00 |
| 296 | Applied texture finish (new structures) (604-04.01) | SY | 1,721 | $18.35 | $17.75 | $20.00 | $14.50 |
| 297 | Bridge deck grooving (mechanical) (604-05.31) | SY | 2,987 | $5.15 | $5.00 | $13.50 | $3.98 |
| 298 | Steel piles (10 inch) (606-02.03) | LF | 742 | $94.00 | $91.10 | $130.00 | $98.00 |
| 299 | Pile tips (steel piles, 10 inch) (606-02.06) | EACH | 38 | $181.00 | $176.00 | $169.00 | $200.00 |
| 300 | Deck drains (grate type 2) (610-10.45) | EACH | 94 | $2,750.00 | $2,670.00 | $2,130.00 | $2,000.00 |
| 301 | Bridge deck crack sealing (617-02) | LF | 896 | $5.75 | $5.55 | $20.00 | $4.00 |
| 302 | Sealant (HMWM) (617-05) | GAL | 5 | $344.00 | $333.00 | $850.00 | $350.00 |
| 303 | Concrete parapet with structural tubing (620-05) | LF | 859 | $401.00 | $389.00 | $425.00 | $337.00 |
| 304 | Temporary shoring (621-05.01) | SF | 1,090 | $37.00 | $25.50 | $45.00 | $130.00 |
| 305 | 6" perforated pipe with vertical drain system (710-09.01) | LF | 258 | $50.45 | $48.90 | $32.00 | $75.00 |
| 306 | 6" pipe underdrain (710-09.02) | LF | 96 | $22.90 | $22.20 | $29.00 | $15.00 |
| 307 | Structural lighting (75F00050005) (714-01.01) | LS | 1 | $24,990 | $42,400 | $43,300 | $37,763 |
| 308 | Pole 45FT class H2 metal (790-04.09) | EACH | 22 | $5,920.00 | $5,800.00 | $4,900.00 | $5,168.40 |
| 309 | Pole 50FT class H2 metal (790-05.08) | EACH | 27 | $6,760.00 | $6,610.00 | $5,700.00 | $5,894.80 |
| 310 | Pole 55FT class H2 metal (790-06.08) | EACH | 10 | $7,690.00 | $7,530.00 | $6,700.00 | $6,713.20 |
| 311 | Pole 60FT class H2 metal (790-07.08) | EACH | 70 | $8,580.00 | $8,400.00 | $7,500.00 | $7,486.40 |
| 312 | Pole 65FT class H2 metal (790-08.04) | EACH | 23 | $9,560.00 | $9,360.00 | $8,500.00 | $8,344.40 |
| 313 | Pole 70FT class H2 metal (790-09.05) | EACH | 5 | $10,830 | $10,600 | $9,700.00 | $9,450.40 |
| 314 | Pole 70FT class H4 metal (790-09.07) | EACH | 4 | $12,590 | $12,300 | $11,500 | $10,988 |
| 315 | Pole 75FT class H2 metal (790-10.05) | EACH | 1 | $12,690 | $12,400 | $10,600 | $11,073 |
| 316 | Pole 75FT class H4 metal (790-10.07) | EACH | 1 | $14,630 | $14,300 | $13,000 | $12,766 |
| 317 | Pole 85FT class H4 metal (790-12.07) | EACH | 23 | $17,400 | $17,000 | $15,000 | $15,186 |
| 318 | Pole 90FT class H4 metal (790-13.07) | EACH | 4 | $19,000 | $18,600 | $20,000 | $16,580 |
| 319 | 1PH dde angle 25KV (790-22.11) | EACH | 1 | $809.00 | $792.00 | $1,200.00 | $706.20 |
| 320 | 1PH dead end tap W/ extension 25KV (790-22.15) | EACH | 32 | $665.00 | $651.00 | $1,500.00 | $580.00 |
| 321 | 1PH dde tangent 25KV (790-22.16) | EACH | 1 | $823.00 | $806.00 | $1,200.00 | $718.32 |
| 322 | 1PH SGL dead end xarm 25KV (790-22.18) | EACH | 6 | $1,410.00 | $1,380.00 | $2,200.00 | $1,228.40 |
| 323 | 3PH crossarm 25KV (790-26.01) | EACH | 1 | $1,220.00 | $1,200.00 | $1,800.00 | $1,065.20 |
| 324 | 3PH crossarm SGL LRG cond 25KV (790-26.03) | EACH | 61 | $1,180.00 | $1,150.00 | $1,600.00 | $1,028.40 |
| 325 | 3PH vertical tangent 25KV (790-26.10) | EACH | 2 | $1,280.00 | $1,250.00 | $1,835.00 | $1,116.60 |
| 326 | 3PH xarm DBL 10FT LRG cond SM angle 25KV (790-26.15) | EACH | 192 | $1,860.00 | $1,820.00 | $2,300.00 | $1,625.90 |
| 327 | 3PH vertical angle LRG cond 25KV (790-26.20) | EACH | 1 | $2,180.00 | $2,130.00 | $2,100.00 | $1,901.80 |
| 328 | 3PH vertical dde angle 25KV (790-26.21) | EACH | 6 | $2,940.00 | $2,880.00 | $2,700.00 | $2,568.30 |
| 329 | 3PH crossarm dead end 25KV (790-26.26) | EACH | 49 | $1,620.00 | $1,590.00 | $2,500.00 | $1,415.40 |
| 330 | 3PH crossarm FBRGLS dde 25KV (790-26.45) | EACH | 26 | $2,870.00 | $2,810.00 | $3,300.00 | $2,508.20 |
| 331 | 3PH special const crossarm dde 25KV (790-26.47) | EACH | 5 | $5,390.00 | $5,280.00 | $2,900.00 | $4,705.80 |
| 332 | Secondary assemblies LRG angle (790-30.02) | EACH | 116 | $196.00 | $192.00 | $690.00 | $171.00 |
| 333 | Secondary assemblies deadend (790-30.03) | EACH | 36 | $218.00 | $213.00 | $715.00 | $190.20 |
| 334 | Secondary conductor 6 AL duplex (790-30.06) | LF | 425 | $3.05 | $2.95 | $3.25 | $2.64 |
| 335 | Secondary conductor 2 AL triplex (790-30.13) | LF | 466 | $4.25 | $4.15 | $5.20 | $3.71 |
| 336 | Secondary conductor 1/0 AL triplex (790-30.14) | LF | 81 | $5.95 | $5.85 | $7.10 | $5.20 |
| 337 | Secondary conductor 4/0 AL triplex (790-30.17) | LF | 151 | $9.90 | $9.70 | $12.20 | $8.64 |
| 338 | Secondary conductor 1/0 AL qplex (790-30.22) | LF | 201 | $7.60 | $7.45 | $5.22 | $6.63 |
| 339 | Secondary conductor 4/0 AL qplex (790-30.25) | LF | 242 | $11.90 | $11.65 | $15.50 | $10.37 |
| 340 | Service assembly-pole type (790-31.02) | EACH | 1 | $1,020.00 | $999.00 | $1,800.00 | $890.00 |
| 341 | Down guy - through bolt type (790-32.01) | EACH | 15 | $416.00 | $407.00 | $425.00 | $362.80 |
| 342 | Down guy - through bolt type heavy duty (790-32.02) | EACH | 486 | $402.00 | $394.00 | $600.00 | $351.16 |
| 343 | OH guy - through bolt type (790-32.07) | EACH | 76 | $651.00 | $637.00 | $590.00 | $567.93 |
| 344 | Guy guard (790-32.23) | EACH | 14 | $28.40 | $27.85 | $51.00 | $24.80 |
| 345 | Rock anchor expanding type (790-33.17) | EACH | 11 | $563.00 | $551.00 | $1,110.00 | $491.12 |
| 346 | Anchor triple eye power installed (790-33.20) | EACH | 258 | $833.00 | $815.00 | $900.00 | $726.42 |
| 347 | Transfer capacitor bank (790-36.02) | EACH | 3 | $5,700.00 | $5,580.00 | $4,200.00 | $4,974.52 |
| 348 | Transfer service (790-36.04) | EACH | 14 | $309.00 | $303.00 | $1,360.00 | $270.00 |
| 349 | Transfer street light (790-36.13) | EACH | 9 | $332.00 | $325.00 | $450.00 | $290.00 |
| 350 | Transfer conductor (790-36.14) | EACH | 93 | $258.00 | $252.00 | $550.00 | $225.00 |
| 351 | OH cond 2 7/1 acsr sparate (790-40.02) | LF | 10,982 | $2.95 | $2.90 | $2.70 | $2.57 |
| 352 | OH cond 1/0 6/1 acsr raven (790-40.03) | LF | 3,167 | $3.45 | $3.35 | $3.50 | $2.99 |
| 353 | OH cond 3/0 6/1 acsr pigeon (790-40.05) | LF | 2,562 | $3.70 | $3.65 | $4.15 | $3.25 |
| 354 | OH cond 336.4 18/1 acsr merlin (790-40.09) | LF | 29,920 | $5.75 | $5.60 | $4.00 | $5.00 |
| 355 | OH cond 795 37 aac arbutus (790-40.49) | LF | 155,439 | $9.25 | $9.10 | $6.90 | $8.09 |
| 356 | OH cond 954 61 aac goldenrod (790-40.86) | LF | 16,212 | $13.20 | $12.90 | $10.70 | $11.50 |
| 357 | UG pri cond 4/0 AL 15KV (790-41.06) | LF | 1,890 | $16.45 | $16.10 | $16.70 | $14.35 |
| 358 | UG pri cond 1 AL 25KV (790-41.12) | LF | 3,189 | $17.60 | $17.25 | $26.70 | $15.37 |
| 359 | UG pri cond 4/0 AL 25KV (790-41.16) | LF | 2,319 | $14.90 | $14.60 | $16.70 | $13.10 |
| 360 | UG sec cond 2/0 AL TPLX (790-41.47) | LF | 90 | $7.25 | $7.10 | $9.25 | $6.34 |
| 361 | UG sec cond 4/0 AL TPLX (790-41.49) | LF | 933 | $8.30 | $8.15 | $11.70 | $7.26 |
| 362 | UG sec cond 350 AL TPLX (790-41.51) | LF | 50 | $14.25 | $13.95 | $16.70 | $12.42 |
| 363 | Conduit - rolled plastic 2IN dia (790-42.02) | LF | 1,972 | $24.20 | $23.70 | $6.15 | $21.12 |
| 364 | 1 duct @ 36IN-48IN depth (790-42.16) | LF | 928 | $217.00 | $212.00 | $24.00 | $189.26 |
| 365 | 2 duct bank @ 36IN-48IN depth (790-42.17) | LF | 2,806 | $244.00 | $238.00 | $28.00 | $212.54 |
| 366 | Loadbreak elbow 200A 15KV (790-43.01) | EACH | 20 | $419.00 | $411.00 | $1,070.00 | $366.00 |
| 367 | Loadbreak junction 4 PT 200A 15KV (790-43.06) | EACH | 21 | $2,130.00 | $2,090.00 | $2,135.00 | $1,860.33 |
| 368 | Elbow arrester 200A 15KV (790-43.08) | EACH | 23 | $1,130.00 | $1,110.00 | $1,640.00 | $986.86 |
| 369 | Loadbreak elbow 200A 25KV (790-43.17) | EACH | 47 | $478.00 | $468.00 | $1,550.00 | $417.40 |
| 370 | Loadbreak parking bushing 200A 25KV (790-43.19) | EACH | 17 | $304.00 | $298.00 | $1,240.00 | $265.60 |
| 371 | Splice 200A 25KV (790-43.26) | EACH | 61 | $397.00 | $389.00 | $1,500.00 | $346.54 |
| 372 | Outdoor terminator urd 25KV (790-43.27) | EACH | 32 | $746.00 | $731.00 | $1,975.00 | $651.26 |
| 373 | UG ground rod assembly (790-43.34) | EACH | 11 | $257.00 | $252.00 | $435.00 | $224.46 |
| 374 | Secondary pullbox large (790-43.46) | EACH | 34 | $1,480.00 | $1,450.00 | $2,750.00 | $1,290.20 |
| 375 | Primary pullbox (790-43.47) | EACH | 23 | $2,350.00 | $2,300.00 | $3,560.00 | $2,050.32 |
| 376 | Secondary riser W/ 2IN conduit (790-43.50) | EACH | 8 | $954.00 | $934.00 | $870.00 | $832.20 |
| 377 | Secondary riser W/ 3IN conduit (790-43.51) | EACH | 30 | $1,030.00 | $1,010.00 | $1,200.00 | $902.84 |
| 378 | Secondary riser W/ 4IN conduit (790-43.52) | EACH | 23 | $934.00 | $915.00 | $1,480.00 | $815.22 |
| 379 | Secondary pullbox (for smart grid fiber) (790-43.67) | EACH | 10 | $2,730.00 | $2,670.00 | $2,420.00 | $2,380.30 |
| 380 | Loadbreak bushing insert 25KV (790-43.80) | EACH | 10 | $403.00 | $394.00 | $465.00 | $351.24 |
| 381 | Loadbreak bushing insert 15KV (790-43.81) | EACH | 8 | $708.00 | $693.00 | $350.00 | $618.00 |
| 382 | Insulated protective cap (790-43.82) | EACH | 9 | $480.00 | $470.00 | $330.00 | $418.92 |
| 383 | 2PH XFMR BNK pole MTD W/ fuse/arresters (790-47.02) | EACH | 1 | $2,420.00 | $2,370.00 | $4,650.00 | $2,112.70 |
| 384 | 3PH XFMR BNK pole MTD no fuse/arresters (790-49.01) | EACH | 6 | $4,150.00 | $4,060.00 | $4,500.00 | $3,618.76 |
| 385 | 1PH pad MTD transformer radial feed (790-50.01) | EACH | 2 | $1,790.00 | $1,750.00 | $3,420.00 | $1,559.60 |
| 386 | 1PH pad MTD transformer loop feed (790-50.02) | EACH | 1 | $1,330.00 | $1,300.00 | $3,430.00 | $1,159.60 |
| 387 | 1PH transformer pad (790-50.03) | EACH | 3 | $1,260.00 | $1,240.00 | $3,600.00 | $1,102.00 |
| 388 | Cutout knife switch-SNGL loadbreak 25KV (790-59.03) | EACH | 99 | $896.00 | $877.00 | $2,650.00 | $782.00 |
| 389 | Golb switch 25KV (790-59.05) | EACH | 8 | $11,220 | $11,000 | $11,600 | $9,790.00 |
| 390 | 3PH sectionalizing cabinet 25KV (790-60.20) | EACH | 7 | $5,210.00 | $5,100.00 | $49,400 | $4,545.20 |
| 391 | 1PH sectionalizing cabinet 25KV (790-60.21) | EACH | 1 | $3,690.00 | $3,620.00 | $5,900.00 | $3,222.68 |
| 392 | 1PH fuse cutout xarm mount 25KV (790-61.01) | EACH | 54 | $585.00 | $573.00 | $1,540.00 | $510.32 |
| 393 | 3PH sectlr or recl W/ byp SW electc 25KV (790-61.11) | EACH | 1 | $16,690 | $16,300 | $9,400.00 | $14,564 |
| 394 | Lightning arrester arm MTD 9 KV (790-65.03) | EACH | 122 | $401.00 | $393.00 | $610.00 | $350.12 |
| 395 | Lightning arrester arm MTD 18 KV (790-65.05) | EACH | 51 | $307.00 | $300.00 | $900.00 | $267.56 |
| 396 | 3PH capacitor assembly 15KV (790-65.15) | EACH | 3 | $4,100.00 | $4,010.00 | $30,000 | $3,576.80 |
| 397 | Lightning arrester 3PH 46 KV (790-65.20) | EACH | 6 | $2,190.00 | $2,140.00 | $2,200.00 | $1,908.00 |
| 398 | Pole ground for air break switch (790-68.07) | EACH | 1 | $1,480.00 | $1,450.00 | $2,400.00 | $1,295.30 |
| 399 | Dead end shoe (790-68.11) | EACH | 46 | $182.00 | $178.00 | $540.00 | $158.80 |
| 400 | Large braces (790-68.12) | EACH | 8 | $191.00 | $187.00 | $750.00 | $166.54 |
| 401 | SGL phase mounting bracket - fiberglass (790-68.13) | EACH | 12 | $253.00 | $248.00 | $780.00 | $221.00 |
| 402 | Fiberglass crossarm assembly (790-69.04) | EACH | 28 | $772.00 | $755.00 | $960.00 | $673.00 |
| 403 | Hardware for SGL PH conv trans (790-69.06) | EACH | 37 | $759.00 | $743.00 | $630.00 | $661.92 |
| 404 | Ground-ground rod for ST pole (790-69.11) | EACH | 6 | $508.00 | $497.00 | $430.00 | $443.19 |
| 405 | Ground assembly ground plate type (790-69.12) | EACH | 183 | $162.00 | $159.00 | $340.00 | $141.54 |
| 406 | Pole top pin (790-69.22) | EACH | 2 | $225.00 | $220.00 | $425.00 | $196.46 |
| 407 | Epoxy dead end (790-69.24) | EACH | 5 | $141.00 | $138.00 | $490.00 | $123.40 |
| 408 | Extension link - epoxy -1FT (790-69.26) | EACH | 32 | $83.90 | $82.15 | $270.00 | $73.20 |
| 409 | Extension link - epoxy -6FT (790-69.28) | EACH | 305 | $131.00 | $128.00 | $410.00 | $114.02 |
| 410 | Arm pin (790-69.32) | EACH | 38 | $126.00 | $123.00 | $495.00 | $109.60 |
| 411 | 3PH sensor mount (790-69.44) | EACH | 3 | $861.00 | $843.00 | $3,900.00 | $751.60 |
| 412 | 3PH post insulator tangent 115KV (790-71.90) | EACH | 19 | $3,020.00 | $2,950.00 | $3,705.56 | $2,632.00 |
| 413 | 3PH post insulator small angle 115KV (790-71.91) | EACH | 5 | $3,970.00 | $3,890.00 | $4,825.00 | $3,466.00 |
| 414 | 3PH suspension insulator vertical double deadend 110KV (790-71.92) | EACH | 3 | $3,920.00 | $3,840.00 | $4,066.67 | $3,420.40 |
| 415 | 3PH suspension insulator vertical deadend 110KV (790-71.93) | EACH | 1 | $2,910.00 | $2,850.00 | $3,900.00 | $2,538.20 |
| 416 | 3PH horizontal deadend 110KV (790-71.94) | EACH | 1 | $10,730 | $10,500 | $5,000.00 | $9,360.80 |
| 417 | Switch golb 46KV (790-71.95) | EACH | 1 | $46,530 | $45,600 | $40,600 | $40,598 |
| 418 | Line post (790-73.03) | EACH | 3 | $1,950.00 | $1,910.00 | $1,060.00 | $1,698.00 |
| 419 | 6M strand (790-74.01) | LF | 5,759 | $3.00 | $4.45 | $5.80 | $5.50 |
| 420 | 24 fiber(material only) (790-74.05) | LF | 1,007 | $4.20 | $1.22 | $1.60 | $1.50 |
| 421 | 144 fiber(material only) (790-74.10) | LF | 5,426 | $5.50 | $2.90 | $3.60 | $3.50 |
| 422 | 12-96 fiber(installation only) (790-74.19) | LF | 1,007 | $2.60 | $3.90 | $5.25 | $5.50 |
| 423 | 108-144 fiber(installation only) (790-74.20) | LF | 5,426 | $2.60 | $4.80 | $5.90 | $5.50 |
| 424 | Fiber splice-12 fiber ribbon (790-74.25) | EACH | 64 | $384.00 | $470.00 | $690.00 | $625.00 |
| 425 | Fiber tangent assembly (790-74.31) | EACH | 28 | $404.00 | $552.00 | $780.00 | $725.00 |
| 426 | Fiber deadend assembly (790-74.32) | EACH | 6 | $595.00 | $439.00 | $610.00 | $575.00 |
| 427 | Fiber double deadend assembly (790-74.33) | EACH | 4 | $1,110.00 | $552.00 | $725.00 | $675.00 |
| 428 | Fiber storage single loop (790-74.34) | EACH | 6 | $732.00 | $477.00 | $660.00 | $625.00 |
| 429 | Fiber splice enclosure(see footnote) (790-74.40) | EACH | 5 | $610.00 | $645.00 | $644.44 | $800.00 |
| 430 | Remove wire (790-98.01) | LF | 248,778 | $2.10 | $2.10 | $2.20 | $1.85 |
| 431 | Remove poles (790-98.02) | EACH | 235 | $745.00 | $572.00 | $810.00 | $650.00 |
| 432 | Remove framing/associated apparatus (790-98.03) | EACH | 1,657 | $378.00 | $250.00 | $430.00 | $330.00 |
| 433 | Remove fiber optic cable (790-98.04) | LF | 6,045 | $2.00 | $1.55 | $1.35 | $1.75 |
| 434 | Tree and brush removal off row (790-98.20) | LS | 1 | $143,270 | $132,000 | $45,000 | $125,000 |
| 435 | Tree and brush removal off row (790-98.20) | LS | 1 | $143,270 | $132,000 | $94,000 | $125,000 |
| 436 | 2IN steel gas main (791-01.02) | LF | 175 | $148.00 | $96.00 | $104.50 | $260.00 |
| 437 | 4IN steel gas main (791-01.04) | LF | 625 | $172.00 | $106.00 | $121.00 | $330.00 |
| 438 | 6IN steel gas main (791-01.05) | LF | 50 | $257.00 | $168.00 | $158.40 | $340.00 |
| 439 | 8IN steel gas main (791-01.06) | LF | 22,900 | $229.00 | $278.00 | $270.00 | $680.00 |
| 440 | 2IN HDPE gas main (791-03.02) | LF | 3,350 | $77.60 | $87.00 | $82.50 | $38.00 |
| 441 | 4IN HDPE gas main (791-03.04) | LF | 18,530 | $40.55 | $52.00 | $50.60 | $48.00 |
| 442 | 6IN HDPE gas main (791-03.05) | LF | 10 | $712.00 | $87.00 | $82.50 | $88.00 |
| 443 | HDD 4IN PE pipe - unconsolidated (791-04.04) | LF | 120 | $285.00 | $174.00 | $165.00 | $360.00 |
| 444 | HDD 8IN steel pipe - unconsolidated (791-04.24) | LF | 1,010 | $484.00 | $610.00 | $577.50 | $982.00 |
| 445 | Connect to 2IN EX. PE main (791-06.02) | EACH | 23 | $1,480.00 | $3,485.00 | $3,300.00 | $550.00 |
| 446 | Connect to 4IN EX. PE main (791-06.03) | EACH | 3 | $2,540.00 | $4,065.00 | $3,850.00 | $850.00 |
| 447 | Connect to 6IN EX. PE main (791-06.04) | EACH | 1 | $4,100.00 | $7,550.00 | $7,150.00 | $2,100.00 |
| 448 | Connect to 8IN EX. STL main (791-06.13) | EACH | 1 | $19,560 | $30,830 | $20,350 | $10,500 |
| 449 | Connect to 2IN EX. STL main W/ stopple (791-06.31) | EACH | 2 | $5,750.00 | $13,940 | $5,060.00 | $9,200.00 |
| 450 | Connect to 4IN EX. STL main W/ stopple (791-06.32) | EACH | 3 | $9,640.00 | $18,890 | $9,680.00 | $15,000 |
| 451 | Connect to 6IN EX. STL main W/ stopple (791-06.33) | EACH | 1 | $34,990 | $25,600 | $14,025 | $25,000 |
| 452 | 2IN PE gas valve assembly (791-07.01) | EACH | 19 | $1,600.00 | $870.00 | $825.00 | $650.00 |
| 453 | 4IN PE gas valve assembly (791-07.02) | EACH | 17 | $2,410.00 | $1,510.00 | $1,650.00 | $850.00 |
| 454 | 2IN steel gas valve assembly (791-07.09) | EACH | 1 | $3,610.00 | $5,250.00 | $825.00 | $5,740.00 |
| 455 | 4IN steel gas valve assembly (791-07.10) | EACH | 8 | $4,800.00 | $8,690.00 | $1,925.00 | $7,500.00 |
| 456 | 6IN steel gas valve assembly (791-07.11) | EACH | 1 | $6,790.00 | $14,000 | $3,025.00 | $1,600.00 |
| 457 | 8IN steel gas valve assembly (791-07.12) | EACH | 7 | $40,620 | $61,700 | $35,475 | $32,000 |
| 458 | 3/4IN service assembly (791-08.02) | EACH | 23 | $1,110.00 | $1,510.00 | $1,430.00 | $290.00 |
| 459 | 3/4IN PE service pipe (791-08.07) | LF | 1,850 | $71.90 | $122.00 | $115.50 | $48.00 |
| 460 | 3-wire cathodic protection station (791-09.02) | EACH | 13 | $1,650.00 | $1,452.00 | $1,375.00 | $250.00 |
| 461 | Regulator station (791-09.04) | EACH | 7 | $14,890 | $17,300 | $8,800.00 | $15,000 |
| 462 | Remove regulator station (791-09.08) | EACH | 9 | $7,070.00 | $10,800 | $2,750.00 | $4,500.00 |
| 463 | Fault current mitigation system (791-09.22) | EACH | 4 | $13,150 | $25,850 | $24,480 | $15,600 |
| 464 | Retire gas main (791-10.10) | LS | 1 | $48,820 | $14,000 | $11,000 | $3,500.00 |
| 465 | 32LB magnesium anode (791-12.04) | EACH | 16 | $1,960.00 | $1,750.00 | $1,650.00 | $600.00 |
| 466 | 8IN ansi 300 weld-in insulator (791-12.30) | EACH | 1 | $22,490 | $27,300 | $15,950 | $20,000 |
| 467 | Anchor 1IN (793-01.41) | EACH | 131 | $1,150.00 | $1,060.00 | $1,375.00 | $950.00 |
| 468 | 12IN pedestal (793-11.10) | EACH | 19 | $2,870.00 | $1,110.00 | $1,455.00 | $1,000.00 |
| 469 | Handhole 24INX36INX24IN (793-11.23) | EACH | 6 | $4,130.00 | $5,550.00 | $2,475.00 | $5,000.00 |
| 470 | 1 duct formation @ 36IN depth (793-13.12) | LF | 836 | $77.95 | $67.30 | $46.70 | $60.00 |
| 471 | Underground to overhead riser (793-14.26) | EACH | 19 | $688.00 | $555.00 | $528.00 | $500.00 |
| 472 | Remove poles all sizes (793-98.04) | EACH | 1 | $458.00 | $833.00 | $730.00 | $750.00 |
| 473 | Remove pedestals (793-98.06) | EACH | 7 | $344.00 | $150.00 | $235.00 | $225.00 |
| 474 | Remove underground to overhead riser (793-98.07) | EACH | 3 | $344.00 | $250.00 | $292.00 | $225.00 |
| 475 | Remove anchor (any size) (793-98.08) | EACH | 57 | $344.00 | $250.00 | $138.00 | $225.00 |
| 476 | 6IN dip slip joint water line (795-01.04) | LF | 975 | $137.00 | $255.00 | $150.00 | $240.00 |
| 477 | 8IN dip slip joint water line (795-01.06) | LF | 1,750 | $181.00 | $280.00 | $175.00 | $260.00 |
| 478 | 10IN dip slip joint water line (795-01.08) | LF | 225 | $253.00 | $310.00 | $218.00 | $300.00 |
| 479 | 12IN dip slip joint water line (795-01.10) | LF | 350 | $363.00 | $335.00 | $229.00 | $310.00 |
| 480 | 16IN dip slip joint water line (795-01.14) | LF | 6,100 | $233.00 | $370.00 | $420.00 | $425.00 |
| 481 | 20IN dip slip joint water line (795-01.18) | LF | 11,360 | $285.80 | $440.00 | $460.00 | $535.00 |
| 482 | 24IN dip slip joint water line (795-01.20) | LF | 400 | $434.00 | $530.00 | $645.00 | $795.00 |
| 483 | 4IN PVC casing pipe open cut (795-05.92) | LF | 2,000 | $108.00 | $70.00 | $208.00 | $140.00 |
| 484 | Connect to 6IN water line (795-06.04) | EACH | 2 | $2,840.00 | $8,000.00 | $8,500.00 | $5,500.00 |
| 485 | Connect to 8IN water line (795-06.05) | EACH | 8 | $3,570.00 | $8,250.00 | $8,900.00 | $5,500.00 |
| 486 | Connect to 10IN water line (795-06.06) | EACH | 2 | $5,640.00 | $8,500.00 | $9,400.00 | $6,000.00 |
| 487 | Connect to 12IN water line (795-06.07) | EACH | 1 | $7,100.00 | $9,000.00 | $9,500.00 | $6,000.00 |
| 488 | Connect to 16IN water line (795-06.09) | EACH | 7 | $11,870 | $18,000 | $9,600.00 | $7,000.00 |
| 489 | Connect to 20IN water line (795-06.11) | EACH | 7 | $14,290 | $20,000 | $11,000 | $8,500.00 |
| 490 | Cut and cap 4IN water line (795-06.32) | EACH | 1 | $2,610.00 | $3,000.00 | $4,300.00 | $4,800.00 |
| 491 | Cut and cap 8IN water line (795-06.34) | EACH | 5 | $4,000.00 | $3,500.00 | $5,400.00 | $5,000.00 |
| 492 | Cut & cap 10IN water line (795-06.36) | EACH | 2 | $4,420.00 | $3,500.00 | $4,700.00 | $5,100.00 |
| 493 | Cut and cap 12IN water line (795-06.37) | EACH | 9 | $5,170.00 | $3,750.00 | $5,120.00 | $5,200.00 |
| 494 | Cut and cap 16IN water line (795-06.39) | EACH | 18 | $6,680.00 | $4,750.00 | $6,780.00 | $10,500 |
| 495 | Cut and cap 20IN water line (795-06.42) | EACH | 25 | $7,860.00 | $5,500.00 | $6,780.00 | $6,000.00 |
| 496 | 20IN X 20IN tapping sleeve and valve (795-07.27) | EACH | 1 | $75,340 | $105,000 | $88,000 | $65,000 |
| 497 | Insertion valve (16IN) (795-07.37) | EACH | 2 | $60,780 | $55,000 | $97,000 | $52,000 |
| 498 | Insertion valve (20IN) (795-07.39) | EACH | 2 | $82,490 | $75,000 | $110,000 | $72,000 |
| 499 | 6IN gate valve assembly (795-08.04) | EACH | 39 | $3,480.00 | $3,000.00 | $3,600.00 | $3,300.00 |
| 500 | 8IN gate valve assembly (795-08.05) | EACH | 18 | $4,480.00 | $4,250.00 | $4,700.00 | $4,100.00 |
| 501 | 10IN gate valve assembly (795-08.06) | EACH | 2 | $5,970.00 | $6,250.00 | $6,700.00 | $5,500.00 |
| 502 | 12IN gate valve assembly (795-08.09) | EACH | 1 | $7,190.00 | $7,650.00 | $8,100.00 | $6,800.00 |
| 503 | 16IN butterfly valve assembly (795-08.13) | EACH | 22 | $11,465 | $19,000 | $16,300 | $9,500.00 |
| 504 | 20IN butterfly valve assembly (795-08.17) | EACH | 27 | $14,435 | $25,500 | $23,000 | $12,000 |
| 505 | Relocate/reconnect service assembly (795-09.09) | EACH | 29 | $2,530.00 | $1,000.00 | $1,250.00 | $2,900.00 |
| 506 | 1IN pex service pipe (795-09.62) | LF | 700 | $81.05 | $40.00 | $39.00 | $100.00 |
| 507 | 2IN pexa service pipe (795-09.64) | LF | 200 | $91.35 | $50.00 | $193.00 | $120.00 |
| 508 | Fire hydrant assembly (795-11.02) | EACH | 33 | $10,990 | $17,000 | $18,500 | $8,500.00 |
| 509 | Reconnect fire hydrant (795-11.03) | EACH | 3 | $3,520.00 | $6,500.00 | $9,450.00 | $1,700.00 |
| 510 | Relocate fire hydrant (795-11.04) | EACH | 2 | $13,620 | $7,000.00 | $9,950.00 | $8,000.00 |
| 511 | Retire in place existing water main (795-11.12) | LF | 19,100 | $0.75 | $7.00 | $22.00 | $8.00 |
| 512 | Pipe grouting (795-12.03) | LS | 1 | $292,590 | $350,000 | $28,000 | $70,000 |
| 513 | Adjust existing valve boxes (795-12.20) | EACH | 30 | $464.00 | $625.00 | $1,000.00 | $650.00 |
| 514 | DI fittings (795-13.01) | LB | 99,500 | $8.80 | $12.00 | $14.50 | $6.75 |
| 515 | 20IN steel casing pipe open cut method (795-15.05) | LF | 75 | $440.00 | $530.00 | $780.00 | $315.00 |
| 516 | 24IN steel casing pipe open cut method (795-15.07) | LF | 85 | $595.00 | $630.00 | $875.00 | $375.00 |
| 517 | 42IN steel casing pipe open cut method (795-15.12) | LF | 175 | $959.00 | $1,530.00 | $1,370.00 | $535.00 |
| 518 | 16IN steel casing pipe open cut method (795-15.25) | LF | 815 | $309.00 | $410.00 | $660.00 | $165.00 |
| 519 | Retire water meter assemblies (795-21.01) | LS | 1 | $26,030 | $21,500 | $29,000 | $35,000 |
| 520 | Retire water valves and hydrants (795-21.02) | LS | 1 | $23,710 | $21,500 | $38,900 | $40,000 |
| 521 | 12IN dip force main (797-01.05) | LF | 100 | $533.00 | $740.00 | $430.00 | $335.00 |
| 522 | 16IN dip force main (797-01.07) | LF | 1,850 | $448.00 | $535.00 | $320.00 | $460.00 |
| 523 | 8IN dip gravity sewer 0FT-6FT depth (797-05.01) | LF | 1,100 | $272.00 | $418.00 | $158.00 | $225.00 |
| 524 | 8IN dip gravity sewer 6FT-12FT depth (797-05.02) | LF | 242 | $394.00 | $714.00 | $182.00 | $280.00 |
| 525 | 8IN dip gravity sewer 12FT-18FT depth (797-05.03) | LF | 1,160 | $387.00 | $544.00 | $228.00 | $380.00 |
| 526 | 10IN dip gravity sewer 6FT-12FT depth (797-05.06) | LF | 100 | $478.00 | $500.00 | $198.00 | $330.00 |
| 527 | 16IN dip gravity sewer 6FT-12FT depth (797-05.14) | LF | 150 | $708.00 | $705.00 | $296.00 | $425.00 |
| 528 | __in dip gravity sewer 0FT-6FT depth (797-05.29) | LF | 2,990 | $484.00 | $634.00 | $428.00 | $495.00 |
| 529 | __in dip gravity sewer 6FT-12FT depth (797-05.30) | LF | 5,450 | $544.00 | $751.00 | $520.00 | $560.00 |
| 530 | __in dip gravity sewer 12FT-18FT depth (797-05.31) | LF | 150 | $1,080.00 | $1,197.00 | $550.00 | $590.00 |
| 531 | __in dip gravity sewer >18FT depth (797-05.32) | LF | 1,260 | $1,225.00 | $1,197.00 | $800.00 | $785.00 |
| 532 | 15IN PVC gravity sewer 6FT-12FT depth (797-05.64) | LF | 650 | $368.00 | $450.00 | $326.00 | $275.00 |
| 533 | 15IN PVC gravity sewer 12FT-18FT depth (797-05.65) | LF | 700 | $281.00 | $585.00 | $360.00 | $345.00 |
| 534 | 48IN manhole 0FT-4FT depth (797-07.01) | EACH | 3 | $8,160.00 | $8,750.00 | $5,700.00 | $5,500.00 |
| 535 | 48IN manhole 4FT-6FT depth (797-07.02) | EACH | 5 | $9,340.00 | $8,750.00 | $6,800.00 | $6,000.00 |
| 536 | 48IN manhole 6FT-8FT depth (797-07.03) | EACH | 1 | $10,220 | $8,750.00 | $7,700.00 | $6,500.00 |
| 537 | 48IN manhole 8FT-10FT depth (797-07.04) | EACH | 6 | $11,090 | $9,000.00 | $8,500.00 | $7,000.00 |
| 538 | 48IN manhole 10FT-12FT depth (797-07.05) | EACH | 4 | $11,970 | $9,500.00 | $9,500.00 | $7,500.00 |
| 539 | 48IN manhole 12FT-14FT depth (797-07.06) | EACH | 2 | $13,410 | $9,500.00 | $10,200 | $9,000.00 |
| 540 | 48IN manhole 14FT-16FT depth (797-07.07) | EACH | 3 | $15,400 | $11,000 | $11,000 | $10,000 |
| 541 | 48IN manhole 16FT-20FT depth (797-07.08) | EACH | 2 | $18,370 | $13,500 | $12,550 | $12,000 |
| 542 | 60IN manhole 4FT-6FT depth (797-07.13) | EACH | 1 | $10,410 | $12,500 | $8,900.00 | $8,500.00 |
| 543 | 60IN manhole 6FT-8FT depth (797-07.14) | EACH | 2 | $11,570 | $12,500 | $9,500.00 | $9,000.00 |
| 544 | 60IN manhole 8FT-10FT depth (797-07.15) | EACH | 3 | $13,290 | $12,500 | $10,600 | $9,500.00 |
| 545 | 60IN manhole 10FT-12FT depth (797-07.16) | EACH | 13 | $15,430 | $13,500 | $12,300 | $11,000 |
| 546 | 60IN manhole 12FT-14FT depth (797-07.17) | EACH | 5 | $17,230 | $14,000 | $13,500 | $12,000 |
| 547 | 60IN manhole 14FT-16FT depth (797-07.18) | EACH | 12 | $19,030 | $14,500 | $14,500 | $13,000 |
| 548 | 60IN manhole 16FT-20FT depth (797-07.19) | EACH | 6 | $21,850 | $17,000 | $19,100 | $15,000 |
| 549 | 60IN manhole 20FT-24FT depth (797-07.20) | EACH | 7 | $25,550 | $25,000 | $31,200 | $17,000 |
| 550 | 72IN manhole 10FT-12FT depth (797-07.27) | EACH | 2 | $18,950 | $15,500 | $38,000 | $13,000 |
| 551 | Manhole drop connection assembly (797-07.56) | EACH | 6 | $10,190 | $3,500.00 | $7,000.00 | $3,200.00 |
| 552 | Adjust existing manhole (797-07.60) | EACH | 20 | $1,850.00 | $4,250.00 | $1,300.00 | $2,300.00 |
| 553 | Remove sewer manhole (797-07.80) | EACH | 3 | $1,270.00 | $5,000.00 | $3,900.00 | $875.00 |
| 554 | 6IN clean out assembly (797-08.08) | EACH | 25 | $1,250.00 | $4,500.00 | $3,800.00 | $1,700.00 |
| 555 | 8IN clean out assembly (797-08.09) | EACH | 25 | $1,140.00 | $6,500.00 | $5,100.00 | $1,720.00 |
| 556 | Connect service lines (all sizes) (797-08.20) | EACH | 43 | $9,420.00 | $24,500 | $25,000 | $4,600.00 |
| 557 | 16IN gate valve assembly (797-08.67) | EACH | 2 | $23,420 | $27,500 | $21,000 | $21,500 |
| 558 | Connect EX. 8IN sewer to new manhole (797-10.09) | EACH | 14 | $3,300.00 | $8,500.00 | $9,300.00 | $6,300.00 |
| 559 | Connect EX.10-18IN sewer to new manhole (797-10.10) | EACH | 6 | $5,510.00 | $11,000 | $22,800 | $6,400.00 |
| 560 | Connect EX. >18IN sewer to new manhole (797-10.11) | EACH | 2 | $9,660.00 | $61,500 | $34,000 | $6,500.00 |
| 561 | Connect to existing pump station (797-10.12) | EACH | 1 | $8,640.00 | $21,000 | $8,000.00 | $7,000.00 |
| 562 | Connect to 2IN force main (797-10.14) | EACH | 1 | $6,370.00 | $8,000.00 | $5,500.00 | $5,000.00 |
| 563 | Connect to 3IN force main (797-10.15) | EACH | 1 | $5,850.00 | $8,000.00 | $6,500.00 | $5,500.00 |
| 564 | Connect to 4IN force main (797-10.16) | EACH | 2 | $5,600.00 | $8,500.00 | $9,600.00 | $5,500.00 |
| 565 | Connect to 8IN force main (797-10.18) | EACH | 1 | $11,730 | $13,500 | $13,000 | $6,000.00 |
| 566 | Connect to 12IN force main (797-10.20) | EACH | 2 | $7,030.00 | $9,500.00 | $17,500 | $7,000.00 |
| 567 | Retirein place 48IN manhole (797-11.25) | EACH | 25 | $2,140.00 | $3,300.00 | $3,800.00 | $1,500.00 |
| 568 | Retirein place 60IN manhole (797-11.26) | EACH | 6 | $3,540.00 | $3,300.00 | $7,700.00 | $1,500.00 |
| 569 | Retirein place 72IN manhole (797-11.27) | EACH | 4 | $4,860.00 | $3,500.00 | $15,000 | $1,500.00 |
| 570 | Retirein place existing sewer 8IN-14IN (797-11.31) | LF | 1,408 | $37.60 | $20.00 | $35.00 | $15.00 |
| 571 | Retirein place existing sewer 15IN-24IN (797-11.32) | LF | 8,565 | $32.00 | $40.00 | $45.00 | $15.00 |
| 572 | Remove existing sewer 8IN-14IN (797-11.35) | LF | 540 | $30.45 | $75.00 | $45.00 | $20.00 |
| 573 | Remove existing sewer 15IN-24IN (797-11.36) | LF | 1,173 | $49.00 | $75.00 | $50.00 | $20.00 |
| 574 | By-pass pumping (797-11.38) | LS | 1 | $171,920 | $900,000 | $579,000 | $150,000 |
| 575 | TV inspection (797-11.39) | LF | 17,000 | $4.00 | $4.00 | $9.20 | $2.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of June 26, 2026. Compiled by Mirage Metrics.